Summary
PRRES20233629
Building Permit - Residential
Issued
SUMMIT VIEW FARMS DEVELOPMENT GROUP LLC
NEW SINGLE FAMILY
NEW HOUSE. COVERED DECK. FINISHED/UNFINISHED BASEMENT. SUSPENDED SLAB.
07/26/2023
08/15/2023
01/28/2024
Locations
Contacts
WOOD BROTHERS CONSTRUCTION INC, Address:PO BOX 553, Phone:(816) 564-5024  
SUMMIT VIEW FARMS DEVELOPMENT GROUP LLC, Address:13450 E STATE ROUTE 150  
Wood Brothers Construction INC, Address:PO Box 553  
EDCO AIRE II LLC, Address:13934 VARNER RD, Phone:(816) 847-0100  
ICO Electric, Address:1810 NW 1000th St  
PREFERRED PLUMBING INC, Address:1664 NW 415TH RD, Phone:(816) 828-1680  
WOODBROTHERSINC@GMAIL.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Water Tap Fee $3,760.00 $3,760.00 Paid 08/15/2023
Water Meter Fee $680.46 $680.46 Paid 08/15/2023
Sanitary Sewer Development Fee $2,159.00 $2,159.00 Paid 08/15/2023
Right of Way Permit Fee $85.00 $85.00 Paid 08/15/2023
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 08/15/2023
Valuation Fee New Single Family $1,677.50 $1,677.50 Paid 08/15/2023
Valuation Fee New Single Family $89.42 $89.42 Paid 02/07/2025
$1,766.92
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Sidewalk Inspection Pending
Misc
Informational
07/29/2024
7-22-24 Dustin A, SW at rear of lot. It is formed and compacted to city specs and slopes are in compliance. Approved to pour 7-29-24 Dustin A, SW is poured and slopes are in compliance. Cannot pass until forms are pulled
Erosion Control Inspection Residential Pending
DCM5 ESC INSP DENIED
Corrective Action Required
03/12/2025
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
03/12/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Footing Inspection - Residential Passed 08/30/2023
Underslab Plumbing Inspection - Residential Passed 10/3/2023 10/3/2023 10/03/2023
Sewer Service Inspection - R Passed 10/11/2023 (10:00) 10/11/2023 10/11/2023
Water Service Inspection - R Partial 10/11/2023
Misc
Corrective Action Required
10/11/2023
Water ran roughly 15’ from foundation
Water Service Inspection - R Passed 10/13/2023 10/13/2023
Misc
Resolved
10/13/2023
Water ran roughly 15’ from foundation
All Rough Inspection - Residential Partial 11/22/2023 11/22/2023 11/22/2023
Misc
Informational
11/22/2023
Garage portal inspected only, no plans on site for any other inspections.
All Rough Inspection - Residential Partial 11/28/2023 11/28/2023 11/28/2023
Misc
Informational
11/22/2023
Garage portal inspected and covered deck roof
Piers/Caissons Inspection - Residential Failed 12/7/2023 12/7/2023 12/07/2023
Misc
Corrective Action Required
12/07/2023
Plans call for 24”x36” piers in the center 2 Outside corner piers okay at 18”x36”
Piers/Caissons Inspection - Residential Passed 12/8/2023 12/8/2023 12/08/2023
Misc
Resolved
12/08/2023
Erosion Control Inspection Residential Failed 02/07/2024
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/07/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. MAINTAIN EROSION CONTROL AT FRONT OF LOT.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
02/07/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
All Rough Inspection - Residential Failed 3/22/2024 3/22/2024 03/22/2024
Misc
Resolved
03/22/2024
Garage portal inspected and covered deck roof
Misc
Corrective Action Required
03/22/2024
-(2) king studs each side of front door opening -plans call for (7) studs each end of beam in garage -anchor all steel columns in basement -columns to be of correct size. See plans -secure conduit within 12” of service panel -outlet required for stairwell wall space
Electrical Service Inspection Passed 3/22/2024 3/22/2024 03/22/2024
Gas Service Inspection - Residential Passed 3/22/2024 3/22/2024 03/22/2024
Driveway Inspection Partial 4/4/2024 4/4/2024 04/04/2024
Misc
Informational
04/04/2024
4-4-24 Dustin A, DW is formed to city specs, Approved to pour
Driveway Inspection Passed 4/11/2024 4/11/2024 04/11/2024
Misc
Informational
04/04/2024
4-4-24 Dustin A, DW is formed to city specs, Approved to pour 4-11-24 Dustin A, DW poured to city specs, Passed
All Rough Inspection - Residential Passed 4/18/2024 4/18/2024 04/18/2024
Misc
Resolved
04/18/2024
-(2) king studs each side of front door opening -plans call for (7) studs each end of beam in garage -anchor all steel columns in basement -columns to be of correct size. See plans -secure conduit within 12” of service panel -outlet required for stairwell wall space
Erosion Control Inspection Residential Failed 07/11/2024
DCM3 ESC REQUIRED 2 DAY
Resolved
07/11/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. MAINTAIN EROSION CONTROL AT FRONT OF LOT.
DCM2 ESC DEFICIENT INSTALLATION
Resolved
07/11/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/11/2024
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -MAINTAIN SILT FENCE -MAINTAIN OVERGROWN VEGETATION
Sidewalk Inspection Partial 7/22/2024 07/22/2024
Misc
Informational
07/22/2024
7-22-24 Dustin A, SW at rear of lot. It is formed and compacted to city specs and slopes are in compliance. Approved to pour
Sidewalk Inspection Partial 7/29/2024 7/29/2024 07/29/2024
Misc
Informational
07/22/2024
7-22-24 Dustin A, SW at rear of lot. It is formed and compacted to city specs and slopes are in compliance. Approved to pour 7-29-24 Dustin A, SW is poured and slopes are in compliance. Cannot pass until forms are pulled
Erosion Control Inspection Residential Partial 10/14/2024 10/14/2024 10/14/2024
DCM3 ESC REQUIRED 2 DAY
Informational
10/14/2024
10-14-24 Dustin A, Stopped and talked to builder about erosion control. He is sodding this week,
Erosion Control Inspection Residential Partial 12/10/2024 12/10/2024 12/11/2024
DCM3 ESC REQUIRED 2 DAY
Informational
10/14/2024
10-14-24 Dustin A, Stopped and talked to builder about erosion control. He is sodding this week,
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
12/10/2024
12-10-24 Dustin A, Silt fence down in rear lot, debris on public sidewalk EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 12-11-24 Jamie S, Silt fence has been installed. SW has been cleaned.
Erosion Control Inspection Residential Partial 12/13/2024 12/13/2024 12/13/2024
DCM3 ESC REQUIRED 2 DAY
Informational
12/10/2024
10-14-24 Dustin A, Stopped and talked to builder about erosion control. He is sodding this week,
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
12/10/2024
12-10-24 Dustin A, Silt fence down in rear lot, debris on public sidewalk EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 12-13-24 Dustin A, Silt fence has been corrected.
All Rough Inspection - Residential Failed 3/12/2025 03/12/2025
Misc
Corrective Action Required
03/12/2025
No address posted inspection denied.
Erosion Control Inspection Residential Failed 03/12/2025
DCM3 ESC REQUIRED 2 DAY
Resolved
03/12/2025
10-14-24 Dustin A, Stopped and talked to builder about erosion control. He is sodding this week,
DCM3 ESC REQUIRED 2 DAY
Resolved
03/12/2025
12-10-24 Dustin A, Silt fence down in rear lot, debris on public sidewalk EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 12-13-24 Dustin A, Silt fence has been corrected.
DCM5 ESC INSP DENIED
Corrective Action Required
03/12/2025
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
03/12/2025
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
All Rough Inspection - Residential Failed 3/13/2025 03/13/2025
Misc
Resolved
03/13/2025
No address posted inspection denied.
Misc
Corrective Action Required
03/13/2025
-seal all penetrations in return air joist spaces -fireblock furr downs see basement bath/ closet -fireblock wall to ceiling furr down at stairs -fireblock beam ends in basement
All Rough Inspection - Residential Passed 3/21/2025 03/21/2025
Misc
Resolved
03/21/2025
-seal all penetrations in return air joist spaces -fireblock furr downs see basement bath/ closet -fireblock wall to ceiling furr down at stairs -fireblock beam ends in basement
Documents & Images
Date Uploaded File Type Document Name
07/26/2023 VSE_SVF103 Spec-Lee's Summit - Sealed Plans (July 7, 2023)
07/26/2023 Excise tax App
07/31/2023 Signed Residental Permit Application_1 (4)
08/01/2023 Approved Plans APPROVED PLANS
08/01/2023 Permit Codes Residential Plan Review
08/01/2023 IMG_20230801_112605
08/02/2023 Plot Plan APPROVED PLOT PLAN
08/02/2023 Permit Codes Residential Plan Review
08/15/2023 Permit DS Building Permit
08/15/2023 Receipt Receipt for transaction:2023-006323
08/25/2023 M L Crose 3215 SW Enoch St LSMO Footing Inspection Report 8-24-23
08/30/2023 Letter INSPECTION SUMMARY
10/03/2023 Letter INSPECTION SUMMARY
10/11/2023 Letter INSPECTION SUMMARY
10/11/2023 Letter INSPECTION SUMMARY
10/13/2023 Letter INSPECTION SUMMARY
11/22/2023 Letter INSPECTION SUMMARY
11/28/2023 Letter INSPECTION SUMMARY
12/07/2023 Letter INSPECTION SUMMARY
12/08/2023 Letter INSPECTION SUMMARY
02/07/2024 Letter INSPECTION SUMMARY
03/22/2024 Letter INSPECTION SUMMARY
03/22/2024 Letter INSPECTION SUMMARY
03/22/2024 Letter INSPECTION SUMMARY
04/04/2024 Letter INSPECTION SUMMARY
04/11/2024 Letter INSPECTION SUMMARY
04/17/2024 Engineer Report Struct_LSMO_Wood Brothers
04/18/2024 Letter INSPECTION SUMMARY
07/11/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter INSPECTION SUMMARY
07/29/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
12/10/2024 Letter INSPECTION SUMMARY
12/10/2024 Letter INSPECTION SUMMARY
12/11/2024 Letter INSPECTION SUMMARY
12/13/2024 Letter INSPECTION SUMMARY
02/04/2025 Application Form BASEMENT FINISH SCOPE OF WORK
02/07/2025 Approved Plans APPROVED BASEMENT DRAWING
02/07/2025 Receipt Receipt for transaction:2025-000829
03/12/2025 Letter INSPECTION SUMMARY
03/12/2025 Letter INSPECTION SUMMARY
03/13/2025 Letter INSPECTION SUMMARY
03/21/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home