Summary
PRRES20231510
Building Permit - Residential
Expired
NEW OTHER (RESIDENTIAL)
NEW INGROUND POOL
04/07/2023
04/18/2023
Locations
Contacts
RE-BUILD LLC, Address:302 E PARK ST, Phone:(913) 339-8020  
sean@rebuildkc.com  
ELECTRICAL INVESTMENTS, Address:8014 REEDER ST, Phone:(816) 210-1597  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 04/18/2023 04/18/2023
Andrea Sessler
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Other $675.00 $675.00 Paid 04/18/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Final Inspection - Residential Pending
Plot Plan Inspection Pending
Pool Final - Residential Pending
Pool Steel/Bonding - Residential Partial 4/19/2023 4/19/2023 04/19/2023
Misc
Corrective Action Required
04/19/2023
-Bonded at 6 points on the pool and 2 points on the hot tub -Ok to pour floor
Pool Steel/Bonding - Residential Partial 5/11/2023 5/11/2023 05/11/2023
Misc
Corrective Action Required
04/19/2023
-Bonded at 6 points on the pool and 2 points on the hot tub - Grounding wire to top of pool walls. Shawn Hoffman 05/11/2023 10:52 AM -Ok to pour floor
Gas Piping Inspection - Residential Failed 8/3/2023 8/3/2023 08/03/2023
Misc
Corrective Action Required
08/03/2023
Underground gas pipe depth okay Okay to cover Provide minimum 10psi at pressure gauges (current gauge is faulty) Paint gas line at equipment slab
Gas Piping Inspection - Residential Partial 8/8/2023 08/08/2023
Misc
Corrective Action Required
08/03/2023
Underground gas pipe depth okay Okay to cover *PAINT EXTERIOR METALLIC GAS LINES WITH CORROSION RESISTANT PAINT
Gas Piping Inspection - Residential Passed 8/16/2023 08/16/2023
Misc
Resolved
08/16/2023
Underground gas pipe depth okay Okay to cover *PAINT EXTERIOR METALLIC GAS LINES WITH CORROSION RESISTANT PAINT
Pool Steel/Bonding - Residential Passed 8/16/2023 8/16/2023 08/16/2023
Misc
Resolved
08/16/2023
-Bonded at 6 points on the pool and 2 points on the hot tub - Grounding wire to top of pool walls. Shawn Hoffman 05/11/2023 10:52 AM -Ok to pour floor
Documents & Images
Date Uploaded File Type Document Name
04/07/2023 Letter FENCE AGREEMENT
04/07/2023 Scope of Work SCOPE OF WORK
04/18/2023 Plot Plan APPROVED PLOT PLAN
04/18/2023 Permit DS Building Permit
04/18/2023 Receipt Receipt for transaction:2023-002194
04/19/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
08/03/2023 Letter INSPECTION SUMMARY
08/08/2023 Letter INSPECTION SUMMARY
08/16/2023 Letter INSPECTION SUMMARY
08/16/2023 Letter INSPECTION SUMMARY
01/03/2024 Letter Codes 140 Day Letter
02/12/2024 Letter Codes 180 Day Letter
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: