Permit Application Status

PRRES20193576


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20193576
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - ROOF TRUSS PACKAGE
12/10/2019
01/02/2020
06/30/2020
Locations
Contacts
CMH PARKS INC, Address:5000 CLAYTON RD  
CLAYTON PROPERTIES GROUP, INC, Address:10450 Holmes Rd Suite 100, Phone:(816) 246-6700  
PERMITTING@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 12/12/2019 12/31/2019
Dylan Eppert
Easements
Corrective Action Required
12/11/2019

All easements with dimensions must be provided on the plot plan. MISSING U/E IN REAR YARD.
Planning Review (RES) Approved 12/13/2019 12/12/2019
Dylan Eppert
Residential Plan Review Approved 12/12/2019 12/11/2019
Dylan Eppert
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee New Single Family $858.98 $858.98 Paid 01/02/2020
8331507-Sewer Connection Fee $360.00 $360.00 Paid 01/02/2020
Water Tap Fee $3,477.00 $3,477.00 Paid 01/02/2020
Water Meter Fee $425.02 $425.02 Paid 01/02/2020
Right of Way Permit Fee $80.00 $80.00 Paid 01/02/2020
Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 01/02/2020
Not Ready Inspection Fee $50.00 $50.00 Paid 06/22/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 1/15/2020 1/15/2020 01/15/2020
Underslab Plumbing Inspection - Residential Passed 2/27/2020 2/27/2020 02/27/2020
Water Service Inspection - R Passed 2/28/2020 02/28/2020
Sewer Service Inspection - R Passed 3/3/2020 03/03/2020
All Rough Inspection - Residential Failed 5/5/2020 5/5/2020 05/05/2020
Misc
Corrective Action Required
05/05/2020
- Erosion control not installed, install before any future inspections - Fire stopping at tub traps, shower, floor and ceiling penetrations, flue chase/heat chase 1st floor - Use approved tape on bath exhaust fan discharge line - Support DWV every 4’ oc - Provide clearance between dryer exhaust duct and hvac duct in laundry - (2) 2x10 header above basement egress per plans - Support hvac ductwork every 10’ oc basement - (3) 2x10 floor joists flush between B piers in basement at stairs - Remove green bonding screw at electric sub panel and set bonding screw on main panel - Color code ufer ground at panel - Protection plates at all water lines and DWV - 6" clearance to single wall flue basement - Nail dbl truss per plans - Strap top plates at intersection of 3rd at NW corner
Electrical Service Inspection Failed 5/5/2020 5/5/2020 05/05/2020
Misc
Corrective Action Required
05/05/2020
- Remove green bonding screw at electric sub panel and set bonding screw on main panel - Color code ufer ground at panel
Gas Piping Inspection - Residential Passed 5/5/2020 5/5/2020 05/05/2020
Gas Service Inspection - Residential Passed 5/5/2020 05/05/2020
Erosion Control Inspection Residential Failed 5/5/2020 05/05/2020
Misc
Corrective Action Required
05/05/2020
- Erosion control not installed on lot, mud gravel in street and trash debris blowing around on lot. Correct before any future inspection -
Misc
Corrective Action Required
05/05/2020
- Erosion control not installed on lot, mud gravel in street and trash debris blowing around on lot. Correct before any future inspection -
Misc
Resolved
05/05/2020
All Rough Inspection - Residential Not Ready 5/7/2020 5/7/2020 05/07/2020
Misc
Corrective Action Required
05/05/2020
- Erosion control not installed, install before any future inspections - Fire stopping at tub traps, shower, floor and ceiling penetrations, flue chase/heat chase 1st floor - Use approved tape on bath exhaust fan discharge line - Support DWV every 4’ oc - Provide clearance between dryer exhaust duct and hvac duct in laundry - (2) 2x10 header above basement egress per plans - Support hvac ductwork every 10’ oc basement - (3) 2x10 floor joists flush between B piers in basement at stairs - Remove green bonding screw at electric sub panel and set bonding screw on main panel - Color code ufer ground at panel - Protection plates at all water lines and DWV - 6" clearance to single wall flue basement - Nail dbl truss per plans - Strap top plates at intersection of 3rd at NW corner
Electrical Service Inspection Passed 5/11/2020 05/11/2020
Misc
Resolved
05/11/2020
All Rough Inspection - Residential Failed 5/11/2020 5/11/2020 05/11/2020
Misc
Corrective Action Required
05/07/2020
- Maintain silt fence, clean street - - Fire stopping at floor and ceiling penetrations, flue chase/heat chase 1st floor - (3) 2x10 floor joists flush between B piers in basement at stairs - Nail dbl truss per plans - Strap top plates at intersection of 3rd at NW corner
Erosion Control Inspection Residential Failed 5/11/2020 05/11/2020
Misc
Corrective Action Required
05/05/2020
- Erosion control not installed on lot, mud gravel in street and trash debris blowing around on lot. Correct before any future inspection -
Misc
Corrective Action Required
05/05/2020
- Erosion control not installed on lot, mud gravel in street and trash debris blowing around on lot. Correct before any future inspection -
DCM6 ESC INSP DENIED STREET CLEAN UP
Corrective Action Required
05/11/2020
STREET CLEAN UP REQUIRED IMMEDIATELY, AND SHALL BE COMPLETED PRIOR TO REQUESTED INSPECTION(S) BEING PERFORMED. - Maintain silt fence -
All Rough Inspection - Residential Failed 5/12/2020 5/12/2020 05/12/2020
Misc
Corrective Action Required
05/11/2020
- Fire stopping at floor and ceiling penetrations, flue chase/heat chase 1st floor - UNABLE TO INSPECT AS HOUSE HAS BEEN INSULATED AND MAJORITY OF WALLS HAD DRYWALL INSTALLED DURING TIME OF INSPECTION - (3) 2x10 floor joists flush between B piers in basement at stairs
Misc
Informational
05/12/2020
- Engineer letter for egress header received. RES Engineering, Bradley Huxol 5/8/20
All Rough Inspection - Residential Failed 5/14/2020 5/13/2020 05/13/2020
Misc
Corrective Action Required
05/12/2020
- (3) 2x10 floor joists flush between B piers in basement at stairs
Misc
Informational
05/12/2020
- Engineer letter for egress window header received. RES Engineering, Bradley Huxol 5/8/20
All Rough Inspection - Residential Passed 5/15/2020 5/15/2020 05/14/2020
Misc
Resolved
05/14/2020
Misc
Resolved
05/14/2020
Occupancy Inspection - Codes Residential Failed 6/16/2020 6/16/2020 06/16/2020
Misc
Corrective Action Required
06/16/2020
- GFCI protection at laundry - Complete patio door handle/lock, two locking devices required on sliding doors - Complete floor outlet living room - Security screws front door hinge, provide (2) 3” screws - Complete security light, back of house - Complete grade and sod - Seal all exterior penetrations - Place splashblocks at all downspout and sump pump discharge locations for minimum distance from foundation 36”
Occupancy Inspection - Codes Residential Temporary C of O 6/22/2020 6/22/2020 06/22/2020
Misc
Corrective Action Required
06/16/2020
- Lower water meter lid/irrigation system lid to grade height OK for TCO
Plot Plan Inspection Passed 06/22/2020
Driveway Inspection Passed 6/30/2020 (P.M.) 6/30/2020 06/30/2020
Misc
Informational
05/18/2020
Drive approach passes field inspection on 5-17-2020
Occupancy Inspection - Codes Residential Full C of O 6/30/2020 6/30/2020 06/30/2020
Misc
Resolved
06/30/2020
Documents & Images
Date Uploaded File Type Document Name
12/27/2019 Letter Codes Residential Plan Review
01/02/2020 Receipt Receipt for transaction: 2020-000004
01/02/2020 Letter DS Building Permit
01/06/2020 Plot Plan DOC010620-01062020080641
01/15/2020 Letter INSPECTION SUMMARY
02/27/2020 Letter INSPECTION SUMMARY
02/28/2020 Letter INSPECTION SUMMARY
03/03/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
05/07/2020 Letter INSPECTION SUMMARY
05/11/2020 Letter INSPECTION SUMMARY
05/11/2020 Engineer Report/Study 68 Hawthorne Ridge Double Rim Joist Letter
05/11/2020 Letter INSPECTION SUMMARY
05/11/2020 Letter INSPECTION SUMMARY
05/12/2020 Letter INSPECTION SUMMARY
05/13/2020 Letter INSPECTION SUMMARY
05/14/2020 Engineer Report/Study 68 Hawthorne Ridge Framing Letter
05/14/2020 Letter INSPECTION SUMMARY
06/16/2020 Letter INSPECTION SUMMARY
06/22/2020 Receipt Receipt for transaction: 2020-003367
06/22/2020 Letter Codes Temporary Certificate of Occupancy
06/22/2020 Letter INSPECTION SUMMARY
06/30/2020 Letter INSPECTION SUMMARY
06/30/2020 Letter Field Certificate of Occupancy
06/30/2020 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: