Summary
PRRES20182431
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE COVERED PATIO UNIFINISHED BASEMENT
07/31/2018
08/09/2018
06/28/2019
Locations
Contacts
CMH PARKS INC, Address:5000 CLAYTON RD  
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
KIMBEL MECHANICAL SYSTEMS, INC, Address:1936 N SHILOH DR, Phone:(479) 756-1099  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 08/02/2018 08/08/2018
Steve Conrick
As-graded plot plan
Corrective Action Required
08/02/2018

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy. ***Please add "AS-GRADED PLOT PLAN IS REQUIRED TO SODDING" in a bubble***
Residential Plan Review Approved 08/03/2018 08/01/2018
Brandon Kalwei
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,216.99 $1,216.99 Paid 08/09/2018
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 08/09/2018
8331504-EFHB Middle Big Creek, Full $602.64 $602.64 Paid 08/09/2018
8331507-Sewer Connection Fee $540.00 $540.00 Paid 08/09/2018
8350015-Water Meter Fee $408.37 $408.37 Paid 08/09/2018
8331401-Water Tap Fee $3,409.00 $3,409.00 Paid 08/09/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Failed 9/5/2018 at 11:45 AM 09/05/2018
Misc
Corrective Action Required
09/05/2018
-PROVIDE COMPACTION TESTS FROM ENGINEER AND VERIFICATION OF THE SOIL BEARING CAPACITY BELOW THE GRAVEL. -NO PLANS ON SITE, NO STEEL IN PLACE
Water Service Inspection - R Partial 09/17/2018
Sewer Service Inspection - R Passed 9/17/2018 (1:00) 9/17/2018 at 1:30 PM 09/17/2018
Water Service Inspection - R Passed 9/18/2018 9/18/2018 at 10:15 AM 09/18/2018
Underslab Plumbing Inspection - Residential Passed 10/2/2018 10/2/2018 at 7:30 AM 10/02/2018
Piers/Caissons Inspection - Residential Passed 10/22/2018 10/22/2018 at 10:00 AM 10/22/2018
All Rough Inspection - Residential Failed 11/26/2018 11/27/2018 11/27/2018
Misc
Corrective Action Required
11/27/2018
NO PLANS ON SITE
All Rough Inspection - Residential Failed 11/28/2018 11/28/2018 at 2:45 PM 11/28/2018
Misc
Resolved
11/28/2018
NO PLANS ON SITE
Misc
Corrective Action Required
11/28/2018
• add 2 studs at steel beam in garage and move outside outlet to accomadate studs. • Strap top plate in southeast corner of garage • Fire block at heat flue 2nd fl. Where pan ends around plumbing vent stack., and above heat vent. Block stud space. • Flexible duct work is resting on top of can light fixture in master bath water closet • Fire stop all unused electrical penetrations on 2nd fl
Gas Piping Inspection - Residential Failed 11/28/2018 11/28/2018 11/28/2018
Misc
Corrective Action Required
11/28/2018
0 PSI IN GAS LINE
Gas Service Inspection - Residential Failed 11/28/2018 11/28/2018 11/28/2018
Misc
Corrective Action Required
11/28/2018
0 PSI IN GAS LINE.
Electrical Service Inspection Passed 11/28/2018 11/28/2018 11/28/2018
All Rough Inspection - Residential Passed 12/6/2018 12/6/2018 at 11:00 AM 12/06/2018
Misc
Resolved
12/06/2018
• add 2 studs at steel beam in garage and move outside outlet to accomadate studs. • Strap top plate in southeast corner of garage • Fire block at heat flue 2nd fl. Where pan ends around plumbing vent stack., and above heat vent. Block stud space. • Flexible duct work is resting on top of can light fixture in master bath water closet • Fire stop all unused electrical penetrations on 2nd fl
Gas Piping Inspection - Residential Passed 12/6/2018 12/6/2018 12/06/2018
Misc
Resolved
12/06/2018
0 PSI IN GAS LINE
Gas Service Inspection - Residential Passed 12/6/2018 12/6/2018 12/06/2018
Misc
Corrective Action Required
11/28/2018
0 PSI IN GAS LINE.
Driveway Inspection Partial 1/4/2019 1/4/2019 01/04/2019
Misc
Corrective Action Required
01/04/2019
The driveway approach is set up and ready to pour however the curb has significant cracking and chips. The contractor is going to Replace the section of curb prior to installing the drive approach.
Occupancy Inspection - Codes Residential Failed 2/14/2019 2/14/2019 at 9:00 AM 02/14/2019
Misc
Resolved
05/15/2019
1. final grading 2. sod 3. pour driveway appraoch 4. provide as graded plot plan prior to sod
Driveway Inspection Partial 3/8/2019 (A.M.) 3/8/2019 03/08/2019
Misc
Corrective Action Required
01/04/2019
The driveway approach is set up and ready to pour however the curb has significant cracking and chips. The contractor is going to Replace the section of curb prior to installing the drive approach.
Misc
Informational
03/08/2019
The curb has been replaced. Pre pour inspection. The forms are set and there appears to be sufficient compacted aggregate.
Driveway Inspection Passed 3/12/2019 03/15/2019
Misc
Corrective Action Required
03/08/2019
The driveway approach is set up and ready to pour however the curb has significant cracking and chips. The contractor is going to Replace the section of curb prior to installing the drive approach.
Misc
Informational
03/08/2019
The curb has been replaced. Pre pour inspection. The forms are set and there appears to be sufficient compacted aggregate.
Plot Plan Inspection Failed 5/8/2019 05/09/2019
Occupancy Inspection - Codes Residential Temporary C of O 5/15/2019 5/15/2019 at 8:01 AM 05/15/2019
Misc
Resolved
05/15/2019
1. final grading 2. sod 3. pour driveway appraoch 4. provide as graded plot plan prior to sod
Misc
Corrective Action Required
05/15/2019
final grade sod provide as graded plot plan
Plot Plan Inspection Passed 6/28/2019 06/28/2019
Occupancy Inspection - Codes Residential Full C of O 6/28/2019 6/28/2019 at 11:00 AM 06/28/2019
Misc
Resolved
06/28/2019
final grade sod provide as graded plot plan
Documents & Images
Date Uploaded File Type Document Name
08/02/2018 Letter Codes Residential Plan Review
08/09/2018 Receipt Receipt for transaction: 2018-005625
08/09/2018 Letter Codes Building Permit
08/09/2018 Plot Plan DOC080918-08092018162920
09/05/2018 Letter Inspection Summary
09/17/2018 Letter Inspection Summary
09/18/2018 Letter Inspection Summary
10/02/2018 Letter Inspection Summary
10/22/2018 Letter Inspection Summary
11/27/2018 Letter INSPECTION SUMMARY
11/28/2018 Letter INSPECTION SUMMARY
11/28/2018 Letter INSPECTION SUMMARY
11/28/2018 Letter INSPECTION SUMMARY
11/28/2018 Letter INSPECTION SUMMARY
12/06/2018 Letter INSPECTION SUMMARY
12/06/2018 Letter INSPECTION SUMMARY
12/06/2018 Letter INSPECTION SUMMARY
01/04/2019 image
01/04/2019 image0
01/04/2019 Letter INSPECTION SUMMARY
01/04/2019 Letter INSPECTION SUMMARY
02/14/2019 Letter INSPECTION SUMMARY
03/08/2019 Letter INSPECTION SUMMARY
03/15/2019 Letter INSPECTION SUMMARY
05/09/2019 Letter INSPECTION SUMMARY
05/15/2019 Letter Codes Temporary Certificate of Occupancy
06/27/2019 Plot Plan LOT 71 NEW ASBUILT 6-27-19
06/28/2019 Letter Codes Final Certificate of Occupancy
06/28/2019 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home