PRPWRW20252486
Public Works Right of Way Permit
Issued
O'NEAL STACIE
PW ROW Cable or Fiber
Section 4 Bore 5556 ft to install Fiber and conduit M&A Drilling Sub
06/16/2025
07/21/2025
09/19/2025
Locations
Contacts
ERVIN CABLE CONSTRUCTION LLC, Address:PO BOX 10, Phone:(270) 333-3366  
O'NEAL STACIE, Address:3204 SW SADDLEBRED TER  
Amie Logan, Address:909 TROOST AVE, Phone:(913) 972-2332  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
ROW Length of Boring $765.00 $765.00 Paid 07/21/2025
ROW Street Crossing $1,600.00 $1,600.00 Paid 07/21/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
06/16/2025 Map
06/16/2025 MCI137-E-LSM147-4PERMIT - COMBINED
06/16/2025 MCI137-E-LSM147-4 PERMIT (1) section 5
07/21/2025 Certificate/License PW ROW Permit
07/21/2025 Receipt Receipt for transaction:2025-005644
07/23/2025 Letter PW ROW Inspections Report
07/25/2025 Letter PW ROW Inspections Report
07/28/2025 Letter PW ROW Inspections Report
07/31/2025 Letter PW ROW Inspections Report
07/31/2025 3224 SW Arbor Ridge Crack
07/31/2025 3224 SW Arbor Ridge crack0
07/31/2025 3208 SW Arbor Sound chipped wing
07/31/2025 3208 SW Arbor Sound chipped wing0
07/31/2025 3212 SW Arbor Sound lifted and cracked approach
08/04/2025 Letter PW ROW Inspections Report
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home