Permit Application Status

PRPWRW20236259


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRPWRW20236259
Public Works Right of Way Permit
Closed
CITY OF LEES SUMMIT
PW ROW Cable or Fiber
UNDERGROUND - PULLING AND REPLACING FIBER - NO NEW DIGGING TAKING PLACE, - ALL EXISITING CONDUIT, FROM 10 NE TUDOR RD TO 818 NE DOUGLAS RD - SEE DASHED LINE ON MAP
11/28/2023
11/29/2023
01/29/2024
12/20/2023
Locations
Property
52900043700000000

Address
10 NE TUDOR RD, LEES SUMMIT, MO 64086

52-900-04-38-00-0-00-000
Contacts
ERVIN CABLE CONSTRUCTION LLC, Address:PO BOX 10, Phone:(270) 333-3366  
CITY OF LEES SUMMIT, Address:207 SW MARKET ST  
Bethany Wilson, Address:909 Troost Avenue, Phone:(913) 238-0403  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110073-ROW Street Crossing $80.00 $80.00 Paid 11/29/2023
9110073-ROW Temporary Obstruction $85.00 $85.00 Paid 11/29/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
11/28/2023 LSM99 - DOUGLAS ST CROSSING MAP
11/28/2023 NE TUDOR RD AT NE DOUGLAS ST - COMBINED TCP
11/29/2023 Certificate/License PW ROW Permit
11/29/2023 Receipt Receipt for transaction:2023-008764
12/20/2023 Letter PW ROW Inspections Report
12/20/2023 Blackwell langsford pic1
12/20/2023 blackwell langsford pic2
12/20/2023 blackwell langsford pic3
12/20/2023 Letter PW ROW Inspections Report
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home