Permit Application Status

PRPWFC20163086


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRPWFC20163086
Public Works Infrastructure Permit - Commercial
Final Acceptance
SAINT LUKES EAST HOSPITAL
DEVELOPMENT COMPLETE
PARKING LOT EXPANSION
11/30/2016
12/14/2016
11/10/2017
Locations
Contacts
SAINT LUKES EAST HOSPITAL, Address:901 E 104TH ST MAILSTOP 900N  
GEORGE J SHAW CONSTRUCTION CO INC, Address:1601 BELLEFONTAINE, Phone:(816) 231-8200  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/30/2016 12/14/2016
Steve Robbins
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $30.00 $30.00 Paid 12/02/2016
9110068-Storm Fee $8,082.23 $8,082.23 Paid 12/02/2016
9110081-Paved Surface Inspection Fee $16,332.77 $16,332.77 Paid 12/02/2016
$16,332.78
9110071-Site Grading Fee $5,685.77 $5,685.77 Paid 12/02/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Storm Sewer Construction Inspection Partial 12/14/2016 12/14/2016
PW-Misc
Informational
12/14/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
Erosion Control Inspection Passed 12/15/2016
Storm Sewer Construction Inspection Partial 12/15/2016 12/19/2016
PW-Misc
Informational
12/14/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/19/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/19/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
Storm Sewer Construction Inspection Partial 12/20/2016 12/20/2016
PW-Misc
Informational
12/19/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/19/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/19/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/20/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
Storm Sewer Construction Inspection Partial 12/21/2016 12/21/2016
PW-Misc
Informational
12/20/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/20/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/20/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/20/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
12/21/2016
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
Storm Sewer Construction Inspection Partial 12/22/2016 12/22/2016
PW-Misc
Informational
12/21/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/21/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/21/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/21/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
12/21/2016
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
12/22/2016
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
Storm Sewer Construction Inspection Partial 12/27/2016 12/28/2016
PW-Misc
Informational
12/22/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/22/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/22/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/22/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
12/22/2016
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
12/22/2016
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
12/28/2016
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
Storm Sewer Construction Inspection Partial 12/29/2016 12/29/2016
PW-Misc
Informational
12/28/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/28/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/28/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/28/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
12/28/2016
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
12/28/2016
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
12/28/2016
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
12/29/2016
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
Storm Sewer Construction Inspection Partial 12/30/2016 12/30/2016
PW-Misc
Informational
12/29/2016
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
12/29/2016
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
12/29/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/29/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/29/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/29/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
12/29/2016
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
12/29/2016
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
12/30/2016
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
Storm Sewer Construction Inspection Partial 1/4/2017 01/04/2017
PW-Misc
Informational
12/30/2016
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
12/30/2016
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
12/30/2016
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
12/30/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/30/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
12/30/2016
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
12/30/2016
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
12/30/2016
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
12/30/2016
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/04/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
Storm Sewer Construction Inspection Partial 1/5/2017 01/06/2017
PW-Misc
Informational
01/04/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/04/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/04/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/04/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/04/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/04/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/04/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/04/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/04/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/04/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/06/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
Storm Sewer Construction Inspection Partial 1/9/2017 01/09/2017
PW-Misc
Informational
01/06/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/06/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/06/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/06/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/06/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/06/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/06/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/06/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/06/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/06/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/06/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/09/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
Storm Sewer Construction Inspection Partial 1/10/2017 01/10/2017
PW-Misc
Informational
01/09/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/09/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/09/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/09/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/09/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/09/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/09/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/09/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/09/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/09/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/09/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/09/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/10/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
Storm Sewer Construction Inspection Partial 1/11/2017 01/11/2017
PW-Misc
Informational
01/10/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/10/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/10/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/10/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/10/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/10/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/10/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/10/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/10/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/10/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/10/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/10/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/10/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/11/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
Storm Sewer Construction Inspection Partial 1/12/2017 01/12/2017
PW-Misc
Informational
01/11/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/11/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/11/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/11/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/11/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/11/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/11/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/11/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/11/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/11/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/11/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/11/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/11/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/11/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/12/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
Storm Sewer Construction Inspection Partial 1/17/2017 01/17/2017
PW-Misc
Informational
01/12/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/12/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/12/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/12/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/12/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/12/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/12/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/12/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/12/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/12/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/12/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/12/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/12/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/12/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/12/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/17/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
Storm Sewer Construction Inspection Partial 1/18/2017 01/18/2017
PW-Misc
Informational
01/17/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/17/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/17/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/17/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/17/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/17/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/17/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/17/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/17/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/17/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/17/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/17/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/17/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/17/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/17/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/17/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/18/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
Storm Sewer Construction Inspection Partial 1/19/2017 01/19/2017
PW-Misc
Informational
01/18/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/18/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/18/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/18/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/18/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/18/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/18/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/18/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/18/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/18/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/18/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/18/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/18/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/18/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/18/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/18/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/18/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/19/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
Storm Sewer Construction Inspection Partial 1/20/2017 01/20/2017
PW-Misc
Informational
01/19/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/19/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/19/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/19/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/19/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/19/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/19/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/19/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/19/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/19/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/19/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/19/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/19/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/19/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/19/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/19/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/19/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/19/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/20/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
Storm Sewer Construction Inspection Partial 1/23/2017 01/23/2017
PW-Misc
Informational
01/20/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/20/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/20/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/20/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/20/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/20/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/20/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/20/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/20/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/20/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/20/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/20/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/20/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/20/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/20/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/20/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/20/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/20/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/20/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/23/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
Storm Sewer Construction Inspection Partial 1/24/2017 01/24/2017
PW-Misc
Informational
01/23/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/23/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/23/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/23/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/23/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/23/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/23/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/23/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/23/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/23/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/23/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/23/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/23/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/23/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/23/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/23/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/23/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/23/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/23/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/23/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
01/24/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
Storm Sewer Construction Inspection Partial 1/25/2017 01/25/2017
PW-Misc
Informational
01/24/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/24/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/24/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/24/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/24/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/24/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/24/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/24/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/24/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/24/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/24/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/24/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/24/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/24/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/24/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/24/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/24/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/24/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/24/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/24/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
01/24/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
01/25/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
Storm Sewer Construction Inspection Partial 1/26/2017 01/26/2017
PW-Misc
Informational
01/25/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/25/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/25/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/25/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/25/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/25/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/25/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/25/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/25/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/25/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/25/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/25/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/25/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/25/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/25/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/25/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/25/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/25/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/25/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/25/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
01/25/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
01/25/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
01/26/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
Storm Sewer Construction Inspection Partial 1/27/2017 01/27/2017
PW-Misc
Informational
01/26/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/26/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/26/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/26/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/26/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/26/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/26/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/26/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/26/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/26/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/26/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/26/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/26/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/26/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/26/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/26/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/26/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/26/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/26/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/26/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
01/26/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
01/26/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
01/26/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
PW-Misc
Informational
01/27/2017
Today they were doing grading in the parking lot. Next week they are planning on starting with the geo-grid and rock if the weather is good.Steve Robbins 01/27/2017 2:35 PM
Storm Sewer Construction Inspection Partial 1/30/2017 01/30/2017
PW-Misc
Informational
01/27/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/27/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/27/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/27/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/27/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/27/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/27/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/27/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/27/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/27/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/27/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/27/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/27/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/27/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/27/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/27/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/27/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/27/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/27/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/27/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
01/27/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
01/27/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
01/27/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
PW-Misc
Informational
01/27/2017
Today they were doing grading in the parking lot. Next week they are planning on starting with the geo-grid and rock if the weather is good.Steve Robbins 01/27/2017 2:35 PM
PW-Misc
Informational
01/30/2017
Nobody was working here today.Steve Robbins 01/30/2017 3:26 PM
Grading/Excavation/Fill Inspection Partial 01/31/2017
PW-Misc
Informational
01/31/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
Grading/Excavation/Fill Inspection Partial 2/1/2017 02/01/2017
PW-Misc
Informational
01/31/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
PW-Misc
Informational
02/01/2017
Today they had their own proofroll for the dirt done, it passed. In the morning they will begin to put rock and geo-grid in , then we will have our proofroll.Steve Robbins 02/01/2017 3:33 PM
Grading/Excavation/Fill Inspection Partial 2/2/2017 02/02/2017
PW-Misc
Informational
02/01/2017
Today they had their own proofroll for the dirt done, it passed. In the morning they will begin to put rock and geo-grid in , then we will have our proofroll.Steve Robbins 02/01/2017 3:33 PM
PW-Misc
Informational
02/02/2017
Today they are installing geo-grid and also putting in the rock. They are also rolling in and compacting the rock as they go.Steve Robbins 02/02/2017 3:56 PM
PW-Misc
Informational
02/01/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
Grading/Excavation/Fill Inspection Partial 2/3/2017 02/03/2017
PW-Misc
Informational
02/02/2017
Today they are installing geo-grid and also putting in the rock. They are also rolling in and compacting the rock as they go.Steve Robbins 02/02/2017 3:56 PM
PW-Misc
Informational
02/03/2017
Today they finished installing all the geo-grid and they are about 3/4 of the way done with the rock in the parking lot. They are rolling and compacting the rock as they go.Steve Robbins 02/03/2017 3:18 PM
PW-Misc
Informational
02/02/2017
Today they had their own proofroll for the dirt done, it passed. In the morning they will begin to put rock and geo-grid in , then we will have our proofroll.Steve Robbins 02/01/2017 3:33 PM
PW-Misc
Informational
02/02/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
Grading/Excavation/Fill Inspection Partial 2/6/2017 02/06/2017
PW-Misc
Informational
02/03/2017
Today they finished installing all the geo-grid and they are about 3/4 of the way done with the rock in the parking lot. They are rolling and compacting the rock as they go.Steve Robbins 02/03/2017 3:18 PM
PW-Misc
Informational
02/06/2017
Today they installed rock on top of the geo-grid and was compacting it, I told them to call when they are ready for a curb proofroll before they install any curbs. We are thinking maybe wednesday for a proofroll.Steve Robbins 02/06/2017 3:03 PM
PW-Misc
Informational
02/03/2017
Today they are installing geo-grid and also putting in the rock. They are also rolling in and compacting the rock as they go.Steve Robbins 02/02/2017 3:56 PM
PW-Misc
Informational
02/03/2017
Today they had their own proofroll for the dirt done, it passed. In the morning they will begin to put rock and geo-grid in , then we will have our proofroll.Steve Robbins 02/01/2017 3:33 PM
PW-Misc
Informational
02/03/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
Curb - Proof Roll Partial 2/7/2017 02/07/2017
PW-Misc
Informational
02/07/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
Curb - Proof Roll Partial 2/8/2017 02/08/2017
PW-Misc
Informational
02/07/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/08/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
Curb - Proof Roll Partial 2/9/2017 02/09/2017
PW-Misc
Informational
02/08/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/09/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/08/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
Curb - Proof Roll Partial 2/13/2017 02/13/2017
PW-Misc
Informational
02/09/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/13/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/09/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/09/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
Curb - Proof Roll Partial 2/14/2017 02/14/2017
PW-Misc
Informational
02/13/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/14/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/13/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/13/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/13/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
Curb - Proof Roll Partial 2/15/2017 02/15/2017
PW-Misc
Informational
02/14/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/14/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/14/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/14/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/14/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/15/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
Curb - Proof Roll Partial 2/16/2017 02/16/2017
PW-Misc
Informational
02/16/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/15/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/15/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/15/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/15/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/15/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/15/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
Curb - Proof Roll Partial 2/17/2017 02/17/2017
PW-Misc
Informational
02/16/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/17/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/16/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/16/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/16/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/16/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/16/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/16/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
Curb - Proof Roll Partial 2/21/2017 02/21/2017
PW-Misc
Informational
02/17/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/17/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/17/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/17/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/17/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/17/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/17/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/17/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
02/21/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
Curb - Proof Roll Partial 2/22/2017 02/22/2017
PW-Misc
Informational
02/21/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/21/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/21/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/21/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/21/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/21/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/21/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/21/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
02/21/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
PW-Misc
Informational
02/22/2017
Today they continued to install the bases for the parking lot light posts and they were doing some clean-up around the lot.Steve Robbins 02/22/2017 3:08 PM
Curb - Proof Roll Partial 2/23/2017 02/23/2017
PW-Misc
Informational
02/22/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/22/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/22/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
02/22/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
PW-Misc
Informational
02/22/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/22/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/22/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/22/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/22/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/22/2017
Today they continued to install the bases for the parking lot light posts and they were doing some clean-up around the lot.Steve Robbins 02/22/2017 3:08 PM
PW-Misc
Informational
02/23/2017
They poured curb around the sencond entrance today, they were also forming sidewalk and getting ready to pour.Steve Robbins 02/23/2017 3:46 PM
Curb - Proof Roll Partial 2/24/2017 02/24/2017
PW-Misc
Informational
02/23/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/23/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/23/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
02/23/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
PW-Misc
Informational
02/23/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/23/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/23/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/23/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/23/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/23/2017
Today they continued to install the bases for the parking lot light posts and they were doing some clean-up around the lot.Steve Robbins 02/22/2017 3:08 PM
PW-Misc
Informational
02/23/2017
They poured curb around the sencond entrance today, they were also forming sidewalk and getting ready to pour.Steve Robbins 02/23/2017 3:46 PM
PW-Misc
Informational
02/24/2017
Today they were taking off forms on the sidewalks and just cleaning up around the job site.Steve Robbins 02/24/2017 3:54 PM
Curb - Proof Roll Partial 2/28/2017 02/28/2017
PW-Misc
Informational
02/24/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
02/24/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/24/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
02/24/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
PW-Misc
Informational
02/24/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/24/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/24/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/24/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/24/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/24/2017
Today they continued to install the bases for the parking lot light posts and they were doing some clean-up around the lot.Steve Robbins 02/22/2017 3:08 PM
PW-Misc
Informational
02/24/2017
They poured curb around the sencond entrance today, they were also forming sidewalk and getting ready to pour.Steve Robbins 02/23/2017 3:46 PM
PW-Misc
Informational
02/24/2017
Today they were taking off forms on the sidewalks and just cleaning up around the job site.Steve Robbins 02/24/2017 3:54 PM
PW-Misc
Informational
02/28/2017
Not much going on here today, doing some more clean-up, they still have some work to do on the 2 entrances.Steve Robbins 02/28/2017 4:06 PM
Curb - Proof Roll Partial 3/1/2017 03/01/2017
PW-Misc
Informational
02/28/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
03/01/2017
Today they were grading the parking lot and checking the dept. They are getting close to having asphalt, they still need to do a parking lot proofroll.Steve Robbins 03/01/2017 4:13 PM
PW-Misc
Informational
02/28/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
02/28/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
02/28/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
PW-Misc
Informational
02/28/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
02/28/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
02/28/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
02/28/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
02/28/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
02/28/2017
Today they continued to install the bases for the parking lot light posts and they were doing some clean-up around the lot.Steve Robbins 02/22/2017 3:08 PM
PW-Misc
Informational
02/28/2017
They poured curb around the sencond entrance today, they were also forming sidewalk and getting ready to pour.Steve Robbins 02/23/2017 3:46 PM
PW-Misc
Informational
02/28/2017
Today they were taking off forms on the sidewalks and just cleaning up around the job site.Steve Robbins 02/24/2017 3:54 PM
PW-Misc
Informational
02/28/2017
Not much going on here today, doing some more clean-up, they still have some work to do on the 2 entrances.Steve Robbins 02/28/2017 4:06 PM
ESC - (Vegetation/Ground Cover) Partial 3/2/2017 03/02/2017
PW-Misc
Informational
03/02/2017
Today they started to install the seed and straw rolls on the hill of the detention basin that has been installed. They are on the west side of th detention basin.Steve Robbins 03/02/2017 10:41 AM
ESC - (Vegetation/Ground Cover) Partial 3/3/2017 03/03/2017
PW-Misc
Informational
03/02/2017
Today they started to install the seed and straw rolls on the hill of the detention basin that has been installed. They are on the west side of th detention basin.Steve Robbins 03/02/2017 10:41 AM
PW-Misc
Informational
03/03/2017
The straw matting was finished being installed today around the detention basin.Steve Robbins 03/03/2017 2:33 PM
Curb - Proof Roll Passed 3/6/2017 03/06/2017
PW-Misc
Informational
03/01/2017
Today they were grading the parking lot and checking the dept. They are getting close to having asphalt, they still need to do a parking lot proofroll.Steve Robbins 03/01/2017 4:13 PM
PW-Misc
Informational
03/06/2017
Today we did a proofroll for the parking lot. The proofroll passed and they are planning on laying asphalt on wednesday, it is suppose to rain this evening so I let them know if it does rain much the proofroll will probably need to be done over.Steve Robbins 03/06/2017 2:23 PM
PW-Misc
Informational
03/01/2017
Today they did a proofroll for the curbs only on the parking lot. The geo-grid and rock has been installed 1 foot behind where the curbs will be. We did 17 tons in a dump truck. They are going to start installing curbs with a curb machine.Steve Robbins 02/07/2017 2:42 PM
PW-Misc
Informational
03/01/2017
Today they used the curb machine to pour curbs in the parking lot, They also dug out the approach on the west side, they already have the east side ready to go, they still have to cut out the existing curbs for the entrance. They did all the curbs that are straight, they will start on the others tomorrow.Steve Robbins 02/08/2017 2:09 PM
PW-Misc
Informational
03/01/2017
Today they are putting in more sidewalks and are getting the entry ready. Instead of putting asphalt they are going to put 8" of concrete on the 2 entrances .Steve Robbins 02/15/2017 3:08 PM
PW-Misc
Informational
03/01/2017
Today they are continuing with installing the light posts. There are 2 entrances and the other one is only getting an asphalt entrance. Also on the south side of the parking lot they are going to install an asphalt curb, they will do that when the pavement comes.Steve Robbins 02/21/2017 1:47 PM
PW-Misc
Informational
03/01/2017
They did not work on the curbs today, the weather was too cold. They will do the curbs on the islands tomorrow.Steve Robbins 02/09/2017 4:03 PM
PW-Misc
Informational
03/01/2017
Today they poured one of the 2 entrances on the parking lot, 40 feet of concrete, 6".Steve Robbins 02/17/2017 3:08 PM
PW-Misc
Informational
03/01/2017
Today they are pouring curbs around the entry. Instead of doing ashpalt they are doing 8" of concrete for 20' into the parking lot.Steve Robbins 02/16/2017 3:40 PM
PW-Misc
Informational
03/01/2017
Today they were forming and pouring sidewalks around the parking lot.Steve Robbins 02/14/2017 4:17 PM
PW-Misc
Informational
03/01/2017
They are continuing to finish the curbs in the parking lot. They are doing the islands around the light poles.Steve Robbins 02/13/2017 3:29 PM
PW-Misc
Informational
03/01/2017
Today they continued to install the bases for the parking lot light posts and they were doing some clean-up around the lot.Steve Robbins 02/22/2017 3:08 PM
PW-Misc
Informational
03/01/2017
They poured curb around the sencond entrance today, they were also forming sidewalk and getting ready to pour.Steve Robbins 02/23/2017 3:46 PM
PW-Misc
Informational
03/01/2017
Today they were taking off forms on the sidewalks and just cleaning up around the job site.Steve Robbins 02/24/2017 3:54 PM
PW-Misc
Informational
03/01/2017
Not much going on here today, doing some more clean-up, they still have some work to do on the 2 entrances.Steve Robbins 02/28/2017 4:06 PM
Grading/Excavation/Fill Inspection Partial 3/7/2017 03/07/2017
PW-Misc
Informational
02/06/2017
Today they installed rock on top of the geo-grid and was compacting it, I told them to call when they are ready for a curb proofroll before they install any curbs. We are thinking maybe wednesday for a proofroll.Steve Robbins 02/06/2017 3:03 PM
PW-Misc
Informational
02/06/2017
Today they finished installing all the geo-grid and they are about 3/4 of the way done with the rock in the parking lot. They are rolling and compacting the rock as they go.Steve Robbins 02/03/2017 3:18 PM
PW-Misc
Informational
02/06/2017
Today they are installing geo-grid and also putting in the rock. They are also rolling in and compacting the rock as they go.Steve Robbins 02/02/2017 3:56 PM
PW-Misc
Informational
02/06/2017
Today they had their own proofroll for the dirt done, it passed. In the morning they will begin to put rock and geo-grid in , then we will have our proofroll.Steve Robbins 02/01/2017 3:33 PM
PW-Misc
Informational
02/06/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
PW-Misc
Informational
03/07/2017
Most of the grading is completed, everything around the detention basin has been graded and most around the parking lot. They are going to install asphalt tomorrow, the rain did not damage the parking lot or proofrolll.Steve Robbins 03/07/2017 1:02 PM
Pavement-Surface Partial 3/8/2017 03/08/2017
PW-Misc
Informational
03/08/2017
Today Seal-O-Matic Paving Company is installing 6" of base aphalt. I have checked the temperatures of the ashpalt when it was going down and coming out of the trucks. About 2-3 trucks were running about 290 degrees. The pavement going down was about 265 -270, I asked that they get the asphalt a little hotter at the plant, after that the next trucks I checked were 275-285. They are not going to finish the entire parking lot today, They will finish in the morning if weather permits.Steve Robbins 03/08/2017 2:41 PM
Pavement-Surface Passed 3/9/2017 03/09/2017
PW-Misc
Informational
03/08/2017
Today Seal-O-Matic Paving Company is installing 6" of base aphalt. I have checked the temperatures of the ashpalt when it was going down and coming out of the trucks. About 2-3 trucks were running about 290 degrees. The pavement going down was about 265 -270, I asked that they get the asphalt a little hotter at the plant, after that the next trucks I checked were 275-285. They are not going to finish the entire parking lot today, They will finish in the morning if weather permits.Steve Robbins 03/08/2017 2:41 PM
PW-Misc
Informational
03/09/2017
This morning they finished installing all the base rock for the parking lot.Steve Robbins 03/09/2017 3:34 PM
Street - Surface Course Partial 03/09/2017
PW-Misc
Informational
03/09/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
Street - Surface Course Partial 3/10/2017 03/10/2017
PW-Misc
Informational
03/09/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/10/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
Street - Surface Course Partial 3/13/2017 03/13/2017
PW-Misc
Informational
03/10/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/13/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
PW-Misc
Informational
03/10/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
Street - Surface Course Partial 3/14/2017 03/14/2017
PW-Misc
Informational
03/13/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
PW-Misc
Informational
03/13/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/13/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/14/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
Street - Surface Course Partial 3/16/2017 03/16/2017
PW-Misc
Informational
03/14/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
PW-Misc
Informational
03/16/2017
They are installing the surface 2" for the remaining part of the parking lot. At about 3 p.m. they were not done but thought they would finish this afternoon.Steve Robbins 03/16/2017 4:29 PM
PW-Misc
Informational
03/14/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/14/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/14/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
Street - Surface Course Partial 3/17/2017 03/17/2017
PW-Misc
Informational
03/16/2017
They are installing the surface 2" for the remaining part of the parking lot. At about 3 p.m. they were not done but thought they would finish this afternoon.Steve Robbins 03/16/2017 4:29 PM
PW-Misc
Informational
03/17/2017
The surface course has been in 2", they still have a small section by each approach to finish. Today they were working on light posts.Steve Robbins 03/17/2017 4:20 PM
PW-Misc
Informational
03/16/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
PW-Misc
Informational
03/16/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/16/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/16/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
Street - Surface Course Partial 3/20/2017 03/20/2017
PW-Misc
Informational
03/17/2017
The surface course has been in 2", they still have a small section by each approach to finish. Today they were working on light posts.Steve Robbins 03/17/2017 4:20 PM
PW-Misc
Informational
03/20/2017
Today I talked with Shaw Construction about the asphalt curbs, they are going to put in concrete ones instead, They were forming them up today.Steve Robbins 03/20/2017 4:23 PM
PW-Misc
Informational
03/17/2017
They are installing the surface 2" for the remaining part of the parking lot. At about 3 p.m. they were not done but thought they would finish this afternoon.Steve Robbins 03/16/2017 4:29 PM
PW-Misc
Informational
03/17/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
PW-Misc
Informational
03/17/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/17/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/17/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
Street - Surface Course Partial 3/21/2017 03/21/2017
PW-Misc
Informational
03/20/2017
Today I talked with Shaw Construction about the asphalt curbs, they are going to put in concrete ones instead, They were forming them up today.Steve Robbins 03/20/2017 4:23 PM
PW-Misc
Informational
03/21/2017
Today they poured the temporary curb that was going to be asphalt, they decided to go with concrete. Steve Robbins 03/21/2017 3:49 PM
PW-Misc
Informational
03/20/2017
The surface course has been in 2", they still have a small section by each approach to finish. Today they were working on light posts.Steve Robbins 03/17/2017 4:20 PM
PW-Misc
Informational
03/20/2017
They are installing the surface 2" for the remaining part of the parking lot. At about 3 p.m. they were not done but thought they would finish this afternoon.Steve Robbins 03/16/2017 4:29 PM
PW-Misc
Informational
03/20/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
PW-Misc
Informational
03/20/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/20/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/20/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
Street - Surface Course Partial 3/22/2017 03/23/2017
PW-Misc
Informational
03/21/2017
Today they poured the temporary curb that was going to be asphalt, they decided to go with concrete. Steve Robbins 03/21/2017 3:49 PM
Corrective Action Required
03/23/2017
PW-Misc
Informational
03/21/2017
Today I talked with Shaw Construction about the asphalt curbs, they are going to put in concrete ones instead, They were forming them up today.Steve Robbins 03/20/2017 4:23 PM
PW-Misc
Informational
03/23/2017
They still have a small strip of asphalt to install in fromt of th approaches. They are also installing the light posts. Steve Robbins 03/23/2017 4:06 PM
PW-Misc
Informational
03/21/2017
The surface course has been in 2", they still have a small section by each approach to finish. Today they were working on light posts.Steve Robbins 03/17/2017 4:20 PM
PW-Misc
Informational
03/21/2017
They are installing the surface 2" for the remaining part of the parking lot. At about 3 p.m. they were not done but thought they would finish this afternoon.Steve Robbins 03/16/2017 4:29 PM
PW-Misc
Informational
03/21/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
PW-Misc
Informational
03/21/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/21/2017
They did not work today doing any ashplat because of the cold temerature, we are expecting snow over the weekend so it will have to warm up.Steve Robbins 03/10/2017 3:36 PM
PW-Misc
Informational
03/21/2017
No work done today. Too cold and rainy.Steve Robbins 03/13/2017 3:46 PM
Proof roll parking lot Passed 3/27/2017 03/27/2017
Corrective Action Required
03/27/2017
PW-Misc
Informational
03/27/2017
The proofroll passed on this parking lot.Steve Robbins 03/27/2017 3:26 PM
Storm Sewer Construction Inspection Partial 12/20/2016 03/27/2017
PW-Misc
Informational
12/19/2016
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
12/19/2016
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
Grading/Excavation/Fill Inspection Passed 3/27/2017 03/27/2017
PW-Misc
Informational
03/07/2017
Today they installed rock on top of the geo-grid and was compacting it, I told them to call when they are ready for a curb proofroll before they install any curbs. We are thinking maybe wednesday for a proofroll.Steve Robbins 02/06/2017 3:03 PM
PW-Misc
Informational
03/07/2017
Today they finished installing all the geo-grid and they are about 3/4 of the way done with the rock in the parking lot. They are rolling and compacting the rock as they go.Steve Robbins 02/03/2017 3:18 PM
PW-Misc
Informational
03/07/2017
Today they are installing geo-grid and also putting in the rock. They are also rolling in and compacting the rock as they go.Steve Robbins 02/02/2017 3:56 PM
PW-Misc
Informational
03/07/2017
Today they had their own proofroll for the dirt done, it passed. In the morning they will begin to put rock and geo-grid in , then we will have our proofroll.Steve Robbins 02/01/2017 3:33 PM
PW-Misc
Informational
03/07/2017
Today they were doing grading in the parking lot trying to get it ready for a dirt proofroll.Steve Robbins 01/31/2017 3:26 PM
PW-Misc
Informational
03/07/2017
Most of the grading is completed, everything around the detention basin has been graded and most around the parking lot. They are going to install asphalt tomorrow, the rain did not damage the parking lot or proofrolll.Steve Robbins 03/07/2017 1:02 PM
PW-Misc
Informational
03/27/2017
All the grading for this project has been finished. They still have some vegetaion to get in. The light poles have all been installed.Steve Robbins 03/27/2017 3:33 PM
Storm Sewer Construction Inspection Partial 3/28/2017 03/28/2017
PW-Misc
Informational
01/30/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
01/30/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
01/30/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
01/30/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
01/30/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
01/30/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
01/30/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
01/30/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
01/30/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
01/30/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
01/30/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
01/30/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
01/30/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
01/30/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
01/30/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
01/30/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
01/30/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
01/30/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
01/30/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
01/30/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
01/30/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
01/30/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
01/30/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
PW-Misc
Informational
01/30/2017
Today they were doing grading in the parking lot. Next week they are planning on starting with the geo-grid and rock if the weather is good.Steve Robbins 01/27/2017 2:35 PM
PW-Misc
Informational
01/30/2017
Nobody was working here today.Steve Robbins 01/30/2017 3:26 PM
PW-Misc
Informational
03/28/2017
All the storm boxes and storm pipe has been installed. When all the other work is done I am going to give them substantial completion so they can let people park in the new parking lot and this will give them room to be able to install the last storm box and install the asphalt and curbs on the last section. I talked to Kent about this and he agreed.Steve Robbins 03/28/2017 10:55 AM
ESC - (Vegetation/Ground Cover) Partial 3/30/2017 03/30/2017
PW-Misc
Informational
03/03/2017
The straw matting was finished being installed today around the detention basin.Steve Robbins 03/03/2017 2:33 PM
PW-Misc
Informational
03/03/2017
Today they started to install the seed and straw rolls on the hill of the detention basin that has been installed. They are on the west side of th detention basin.Steve Robbins 03/02/2017 10:41 AM
PW-MULCHING AND HYDRO MULCH
Informational
03/30/2017
The hydro seed has been installed over all the areas that it needs to be except for the area that has not yet been torn out.Steve Robbins 03/30/2017 2:38 PM
Storm Sewer Construction Inspection Partial 4/12/2017 04/12/2017
PW-Misc
Informational
03/28/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
03/28/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
03/28/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
03/28/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
03/28/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
03/28/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
03/28/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
03/28/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
03/28/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
03/28/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
03/28/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
03/28/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
03/28/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
03/28/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
03/28/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
03/28/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
03/28/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
03/28/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
03/28/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
03/28/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
03/28/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
03/28/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
03/28/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
PW-Misc
Informational
03/28/2017
Today they were doing grading in the parking lot. Next week they are planning on starting with the geo-grid and rock if the weather is good.Steve Robbins 01/27/2017 2:35 PM
PW-Misc
Informational
03/28/2017
Nobody was working here today.Steve Robbins 01/30/2017 3:26 PM
PW-Misc
Informational
03/28/2017
All the storm boxes and storm pipe has been installed. When all the other work is done I am going to give them substantial completion so they can let people park in the new parking lot and this will give them room to be able to install the last storm box and install the asphalt and curbs on the last section. I talked to Kent about this and he agreed.Steve Robbins 03/28/2017 10:55 AM
Informational
04/12/2017
Today no work was done, they still have a storm box to install.Steve Robbins 04/12/2017 3:47 PM
Street - Surface Course Passed 4/13/2017 04/14/2017
PW-Misc
Corrective Action Required
03/23/2017
PW-Misc
Informational
04/14/2017
All the surface for the parking lot has been completed including the saw- cuts they made by the approaches. They also did the striping. I talked to Kent and we agreed to let them park on the parking lot while they finish south end of the parking lot which includes installed a curb inlet and curbs and asphalt that will connect to the south end parking lot. They have to have a place for the other cars to go so they can get the work done. I chose not to give them a substantial completion because there is still some work to be done.Steve Robbins 04/14/2017 9:23 AM
PW-Misc
Informational
03/23/2017
They still have a small strip of asphalt to install in fromt of th approaches. They are also installing the light posts. Steve Robbins 03/23/2017 4:06 PM
PW-Misc
Informational
03/23/2017
This afternoon they starting installing the 2" of surface for the parking lot on the end that they finished the base on yesterday. It started raining at about 1:30 so they shut down for the day, it is suppose to be about 30 degreees in the morning so it is unlikely they with lay any surface tomorrow.Steve Robbins 03/09/2017 3:37 PM
PW-Misc
Informational
03/23/2017
No asphalt today. Probably not until thursday.Steve Robbins 03/14/2017 3:37 PM
PW-Misc
Informational
03/23/2017
They are installing the surface 2" for the remaining part of the parking lot. At about 3 p.m. they were not done but thought they would finish this afternoon.Steve Robbins 03/16/2017 4:29 PM
PW-Misc
Informational
03/23/2017
The surface course has been in 2", they still have a small section by each approach to finish. Today they were working on light posts.Steve Robbins 03/17/2017 4:20 PM
PW-Misc
Informational
03/23/2017
Today I talked with Shaw Construction about the asphalt curbs, they are going to put in concrete ones instead, They were forming them up today.Steve Robbins 03/20/2017 4:23 PM
PW-Misc
Informational
03/23/2017
Today they poured the temporary curb that was going to be asphalt, they decided to go with concrete. Steve Robbins 03/21/2017 3:49 PM
Storm Sewer Construction Inspection Partial 4/19/2017 04/19/2017
PW-Misc
Informational
04/12/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
04/12/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
04/12/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
04/12/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
04/12/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
04/12/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
04/12/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
04/12/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
04/12/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
04/12/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
04/12/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
04/12/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
04/12/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
04/12/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
04/12/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
04/12/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
04/12/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
04/12/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
04/12/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
04/12/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
04/12/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
04/12/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
04/12/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
PW-Misc
Informational
04/12/2017
Today they were doing grading in the parking lot. Next week they are planning on starting with the geo-grid and rock if the weather is good.Steve Robbins 01/27/2017 2:35 PM
PW-Misc
Informational
04/12/2017
Nobody was working here today.Steve Robbins 01/30/2017 3:26 PM
PW-Storm Sewer Inspection
Informational
04/19/2017
Yesterday they took out the part of the parking lot on the south side so they can do their connection to the existing parking lot. They are also getting ready to install the remaining storm box in the parking lot, they also have rock and geo-grid to install.Steve Robbins 04/19/2017 3:04 PM
Storm Sewer Construction Inspection Passed 4/20/2017 04/20/2017
PW-Misc
Informational
04/19/2017
They put storm pipe from structure 104 to 103, Steve Robbins 12/22/2016 4:26 PM
PW-Misc
Informational
04/19/2017
Structure 102 and 103 was installed along with the pipe and rock.Steve Robbins 12/28/2016 8:14 AM
PW-Misc
Informational
04/19/2017
No work was done today due to the cold and snow.Steve Robbins 12/19/2016 3:52 PM
PW-Misc
Informational
04/19/2017
Today they installed aproximately 55 ft. of 60" concrete stormpipe and put in rock. Steve Robbins 12/14/2016 3:40 PM
PW-Misc
Informational
04/19/2017
No work was done today due to the cold weather and snow.Steve Robbins 12/19/2016 3:48 PM
PW-Misc
Informational
04/19/2017
Structure 109 and 108 have been installed and the collars have been poured on them. Today they installed structure 107 and 106 and the pipe with rock, tomorrow they are planning on pouring the collars for those structures.Steve Robbins 12/20/2016 3:44 PM
PW-Misc
Informational
04/19/2017
So far today they have installed structure 105 and 104, they are planning on pouring the collars for the last 4 structures this afternoon after lunch. They have the pipe and rock for structure 104Steve Robbins 12/21/2016 12:06 PM
PW-Misc
Informational
04/19/2017
They have installed structure 301 and all the pipe and rock. Today they are finishing all the collars on the other structures. Line 2 is what they will start next and they will have to have cars moved in order to do it.Steve Robbins 12/29/2016 10:35 AM
PW-Misc
Informational
04/19/2017
Today they installed structure 101 and structure 202. Structure 202 has been tied into existing 24" pipe. Also structure 202 was tied into the existing 24" pipe coming out of existing structure 201. Steve Robbins 12/30/2016 1:55 PM
PW-Misc
Informational
04/19/2017
Yesterday they did some grading . Today they are putting in the 6" perforated HDPE underdrain pipe, they are starting on the south end of the parking lot. Steve Robbins 01/04/2017 11:02 AM
PW-Misc
Informational
04/19/2017
Yesterday and today there was no work done on the this site due to the cold and snow.Steve Robbins 01/06/2017 1:58 PM
PW-Misc
Informational
04/19/2017
Today they are continuing to work on the underdrain in the parking lot, they are also installing rip rap by the detention basin.Steve Robbins 01/09/2017 10:50 AM
PW-Misc
Informational
04/19/2017
Today they were doing some grading and also digging the trench for the underdarain pipe.Steve Robbins 01/10/2017 4:30 PM
PW-Misc
Informational
04/19/2017
Today they continued to put in the underdrain pipes with rock. They were also doing a little bit of grading by the basin.Steve Robbins 01/11/2017 2:37 PM
PW-Misc
Informational
04/19/2017
Today they finished installing the 6" underdrain perforated pipe and rock. They are not planning on working tomorrow.Steve Robbins 01/12/2017 3:56 PM
PW-Misc
Informational
04/19/2017
Yesterday was a holiday so I did not work, it looks like they have finished all the underdrains for the parking lot. They still have rip rap to install in the retention basin. They are not working today.Steve Robbins 01/17/2017 11:01 AM
PW-Misc
Informational
04/19/2017
No work being done today.Steve Robbins 01/18/2017 4:20 PM
PW-Misc
Informational
04/19/2017
Not working today, too much mudd. They still have 501 and 502 to complete when the weather gets better.Steve Robbins 01/19/2017 2:38 PM
PW-Misc
Informational
04/19/2017
Today they are making the final connections of the underdrains to the storm structures. They will be finished this afternoon.Steve Robbins 01/20/2017 3:29 PM
PW-Misc
Informational
04/19/2017
No work was done here today. No erosion control problems.,Steve Robbins 01/23/2017 2:35 PM
PW-Misc
Informational
04/19/2017
Nobody worked on this job site today.Steve Robbins 01/24/2017 3:49 PM
PW-Misc
Informational
04/19/2017
No work was done on this site today.Steve Robbins 01/25/2017 3:03 PM
PW-Misc
Informational
04/19/2017
No work was done today.Steve Robbins 01/26/2017 2:51 PM
PW-Misc
Informational
04/19/2017
Today they were doing grading in the parking lot. Next week they are planning on starting with the geo-grid and rock if the weather is good.Steve Robbins 01/27/2017 2:35 PM
PW-Misc
Informational
04/19/2017
Nobody was working here today.Steve Robbins 01/30/2017 3:26 PM
PW-Storm Sewer Inspection
Informational
04/19/2017
Yesterday they took out the part of the parking lot on the south side so they can do their connection to the existing parking lot. They are also getting ready to install the remaining storm box in the parking lot, they also have rock and geo-grid to install.Steve Robbins 04/19/2017 3:04 PM
PW-Grout storm boxes
Informational
04/20/2017
Storm boxes 501 and 502 have been installed and converted . The pipe was installed and the collars for the pipes have also been installled. This now completes all the storm pipe installation.Steve Robbins 04/20/2017 3:48 PM
Pavement-Stabilized Subgrade Partial 4/24/2017 04/24/2017
PW-Misc
Informational
04/24/2017
Today they continued to get the grade ready for rock and ge-grid, this is south end of the parking lot that they are merging with the existing. The subgrade is ready to have rock and geo-grid installed.Steve Robbins 04/24/2017 2:32 PM
Pavement-Stabilized Subgrade Partial 4/25/2017 04/25/2017
PW-Misc
Informational
04/24/2017
Today they continued to get the grade ready for rock and ge-grid, this is south end of the parking lot that they are merging with the existing. The subgrade is ready to have rock and geo-grid installed.Steve Robbins 04/24/2017 2:32 PM
PW-Misc
Informational
04/25/2017
Today they are installing the geo-grid for the remaining part of the parking lot. This afternoon they are bringing in the base rock.Steve Robbins 04/25/2017 12:36 PM
Pavement-Stabilized Subgrade Partial 4/26/2017 04/27/2017
PW-Misc
Informational
04/25/2017
Today they continued to get the grade ready for rock and ge-grid, this is south end of the parking lot that they are merging with the existing. The subgrade is ready to have rock and geo-grid installed.Steve Robbins 04/24/2017 2:32 PM
PW-Misc
Informational
04/25/2017
Today they are installing the geo-grid for the remaining part of the parking lot. This afternoon they are bringing in the base rock.Steve Robbins 04/25/2017 12:36 PM
PW-Misc
Informational
04/27/2017
All the rock and geo-grid has been installed, yesterday they were putting the stakes in with stringline for the curbs. We go some rain yesterday.Steve Robbins 04/27/2017 7:06 AM
Pavement-Stabilized Subgrade Passed 4/28/2017 04/28/2017
PW-Misc
Informational
04/27/2017
Today they continued to get the grade ready for rock and ge-grid, this is south end of the parking lot that they are merging with the existing. The subgrade is ready to have rock and geo-grid installed.Steve Robbins 04/24/2017 2:32 PM
PW-Misc
Informational
04/28/2017
I talked to the contractor and they will call when they are ready for a proofroll. It is suppose to rain all weekendlSteve Robbins 04/28/2017 2:42 PM
PW-Misc
Informational
04/27/2017
Today they are installing the geo-grid for the remaining part of the parking lot. This afternoon they are bringing in the base rock.Steve Robbins 04/25/2017 12:36 PM
PW-Misc
Informational
04/27/2017
All the rock and geo-grid has been installed, yesterday they were putting the stakes in with stringline for the curbs. We go some rain yesterday.Steve Robbins 04/27/2017 7:06 AM
Proof roll parking lot Partial 5/2/2017 05/02/2017
Informational
05/02/2017
Today I did a proofroll for the curbs to go in on the remaining portion of the parking lot. We will see how much it rains tonight. The parking lot has good flow so if it doesn't rain much I will let them pour the curbs tomorrow or thursday. I will need another proofroll before the base goes in.Steve Robbins 05/02/2017 3:19 PM
Commercial Curb Inspection Passed 5/8/2017 05/08/2017
Informational
05/08/2017
The remaining portion of the curbs has been installed. We still have to have a proofroll before the base goes in.Steve Robbins 05/08/2017 8:55 AM
Proof roll parking lot Partial 5/15/2017 05/15/2017
Informational
05/15/2017
I talked to the contractor about a prooroll and they said they are getting close. They have installed all the curbs and the parking lot has been drying out.Steve Robbins 05/15/2017 10:04 AM
ESC - (Vegetation/Ground Cover) Partial 5/16/2017 05/16/2017
PW-Misc
Informational
03/30/2017
The straw matting was finished being installed today around the detention basin.Steve Robbins 03/03/2017 2:33 PM
PW-Misc
Informational
03/30/2017
Today they started to install the seed and straw rolls on the hill of the detention basin that has been installed. They are on the west side of th detention basin.Steve Robbins 03/02/2017 10:41 AM
PW-MULCHING AND HYDRO MULCH
Informational
03/30/2017
The hydro seed has been installed over all the areas that it needs to be except for the area that has not yet been torn out.Steve Robbins 03/30/2017 2:38 PM
PW-Misc
Informational
05/16/2017
The vegetation has come in on the detension basin and it has been coming in good around the whole area. They still have a few spots to touch up after the rest of the parking lot gets finished.Steve Robbins 05/16/2017 7:10 AM
Proof roll parking lot Partial 5/18/2017 05/18/2017
Informational
05/18/2017
We are waiting on a proofroll for the last small section.Steve Robbins 05/18/2017 3:51 PM
Proof roll parking lot Partial 5/22/2017 05/22/2017
Informational
05/22/2017
Today they drained the water out of the area that was holding water and let it dry out. They are looking to get a proofroll for the remaining section this week.Steve Robbins 05/22/2017 3:50 PM
Proof roll parking lot Partial 5/26/2017 05/26/2017
Informational
05/26/2017
The parking lot that remains is now ready for a proofroll next week, depending on how much rain we get over the weekendlSteve Robbins 05/26/2017 2:41 PM
Proof roll parking lot Passed 6/2/2017 06/02/2017
Informational
06/02/2017
The last section for a proofroll has been done and it passed.Steve Robbins 06/02/2017 3:17 PM
Pavement-Surface Passed 6/2/2017 06/16/2017
PW-Misc
Informational
06/16/2017
The remaining section of base asphlalt was installed on 6/2/17Steve Robbins 06/16/2017 9:25 AM
Street - Surface Course Passed 6/2/2017 06/16/2017
PW-Misc
Informational
06/16/2017
The surface was also installed on 6/2/17 in the afternoon. This now completes all the ashpalt in the parking lot .Steve Robbins 06/16/2017 9:28 AM
ESC - (Vegetation/Ground Cover) Partial 8/17/2017 at 11:35 AM 08/17/2017
PW-Misc
Informational
05/16/2017
The straw matting was finished being installed today around the detention basin.Steve Robbins 03/03/2017 2:33 PM
PW-Misc
Informational
05/16/2017
Today they started to install the seed and straw rolls on the hill of the detention basin that has been installed. They are on the west side of th detention basin.Steve Robbins 03/02/2017 10:41 AM
PW-MULCHING AND HYDRO MULCH
Informational
05/16/2017
The hydro seed has been installed over all the areas that it needs to be except for the area that has not yet been torn out.Steve Robbins 03/30/2017 2:38 PM
PW-Misc
Informational
05/16/2017
The vegetation has come in on the detension basin and it has been coming in good around the whole area. They still have a few spots to touch up after the rest of the parking lot gets finished.Steve Robbins 05/16/2017 7:10 AM
PW-Misc
Informational
08/17/2017
70% vegetation has not been established.Steve Robbins 08/17/2017 11:37 AM
ESC - (Vegetation/Ground Cover) Passed 11/8/2017 11/08/2017
PW-Misc
Informational
08/17/2017
PW-Misc
Informational
08/17/2017
Today they started to install the seed and straw rolls on the hill of the detention basin that has been installed. They are on the west side of th detention basin.Steve Robbins 03/02/2017 10:41 AM
PW-MULCHING AND HYDRO MULCH
Informational
08/17/2017
The hydro seed has been installed over all the areas that it needs to be except for the area that has not yet been torn out.Steve Robbins 03/30/2017 2:38 PM
PW-Misc
Informational
08/17/2017
The vegetation has come in on the detension basin and it has been coming in good around the whole area. They still have a few spots to touch up after the rest of the parking lot gets finished.Steve Robbins 05/16/2017 7:10 AM
Documents & Images
Date Uploaded File Type Document Name
12/02/2016 Receipt Receipt for transaction: 2016-007032
12/08/2016 Letter PW-Permit
12/14/2016 Letter PW-Daily Inspection Summary
12/19/2016 Letter PW-Daily Inspection Summary
12/20/2016 Letter PW-Daily Inspection Summary
12/21/2016 Letter PW-Daily Inspection Summary
12/22/2016 Letter PW-Daily Inspection Summary
12/28/2016 Letter PW-Daily Inspection Summary
12/29/2016 Letter PW-Daily Inspection Summary
12/30/2016 Letter PW-Daily Inspection Summary
01/04/2017 Letter PW-Daily Inspection Summary
01/06/2017 Letter PW-Daily Inspection Summary
01/09/2017 Letter PW-Daily Inspection Summary
01/10/2017 Letter PW-Daily Inspection Summary
01/11/2017 Letter PW-Daily Inspection Summary
01/12/2017 Letter PW-Daily Inspection Summary
01/17/2017 Letter PW-Daily Inspection Summary
01/17/2017 St Lukes
01/18/2017 Letter PW-Daily Inspection Summary
01/19/2017 Letter PW-Daily Inspection Summary
01/20/2017 Letter PW-Daily Inspection Summary
01/23/2017 Letter PW-Daily Inspection Summary
01/24/2017 Letter PW-Daily Inspection Summary
01/25/2017 Letter PW-Daily Inspection Summary
01/26/2017 Letter PW-Daily Inspection Summary
01/27/2017 Letter PW-Daily Inspection Summary
01/30/2017 Letter PW-Daily Inspection Summary
01/31/2017 Letter PW-Daily Inspection Summary
02/01/2017 Letter PW-Daily Inspection Summary
02/02/2017 Letter PW-Daily Inspection Summary
02/03/2017 Letter PW-Daily Inspection Summary
02/06/2017 Letter PW-Daily Inspection Summary
02/07/2017 Letter PW-Daily Inspection Summary
02/08/2017 Letter PW-Daily Inspection Summary
02/09/2017 Letter PW-Daily Inspection Summary
02/13/2017 Letter PW-Daily Inspection Summary
02/14/2017 Letter PW-Daily Inspection Summary
02/15/2017 Letter PW-Daily Inspection Summary
02/16/2017 Letter PW-Daily Inspection Summary
02/17/2017 Letter PW-Daily Inspection Summary
02/21/2017 Letter PW-Daily Inspection Summary
02/22/2017 Letter PW-Daily Inspection Summary
02/23/2017 Letter PW-Daily Inspection Summary
02/24/2017 Letter PW-Daily Inspection Summary
02/28/2017 Letter PW-Daily Inspection Summary
03/01/2017 Letter PW-Daily Inspection Summary
03/02/2017 Letter PW-Daily Inspection Summary
03/03/2017 Letter PW-Daily Inspection Summary
03/06/2017 Letter PW-Daily Inspection Summary
03/07/2017 Letter PW-Daily Inspection Summary
03/08/2017 Letter PW-Daily Inspection Summary
03/09/2017 Letter PW-Daily Inspection Summary
03/09/2017 Letter PW-Daily Inspection Summary
03/10/2017 Letter PW-Daily Inspection Summary
03/13/2017 Letter PW-Daily Inspection Summary
03/14/2017 Letter PW-Daily Inspection Summary
03/16/2017 Letter PW-Daily Inspection Summary
03/17/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/21/2017 Letter PW-Daily Inspection Summary
03/23/2017 Letter PW-Daily Inspection Summary
03/27/2017 Letter PW-Daily Inspection Summary
03/27/2017 Letter PW-Daily Inspection Summary
03/28/2017 Letter PW-Daily Inspection Summary
04/12/2017 Letter PW-Daily Inspection Summary
04/12/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/19/2017 Letter PW-Daily Inspection Summary
04/20/2017 Letter PW-Daily Inspection Summary
04/24/2017 Letter PW-Daily Inspection Summary
04/25/2017 Letter PW-Daily Inspection Summary
04/27/2017 Letter PW-Daily Inspection Summary
04/28/2017 Letter PW-Daily Inspection Summary
05/02/2017 Letter PW-Daily Inspection Summary
05/08/2017 Letter PW-Daily Inspection Summary
05/15/2017 Letter PW-Daily Inspection Summary
05/16/2017 Letter PW-Daily Inspection Summary
05/18/2017 Letter PW-Daily Inspection Summary
05/22/2017 Letter PW-Daily Inspection Summary
05/26/2017 Letter PW-Daily Inspection Summary
06/02/2017 Letter PW-Daily Inspection Summary
06/16/2017 Letter PW-Daily Inspection Summary
06/16/2017 Letter PW-Daily Inspection Summary
06/16/2017 Letter PW-Certificate of Substantial Completion Single Lot
06/16/2017 Letter PW-Punch List
06/20/2017 St. Lukes Hospital Substantial and Punch List
08/17/2017 Letter PW-Daily Inspection Summary
11/10/2017 Letter DE-Certificate of Final Acceptance (Commercial)
11/10/2017 St Lukes East -West Parking Lot
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home