Summary


PRPWFC20161240
Public Works Infrastructure Permit - Commercial
Final Acceptance
THE UNITED METHODIST CHURCH OF LEES SUMM
DEVELOPMENT COMPLETE
The Summit Church (View High Dr. and Chipman Rd.)
05/27/2016
10/11/2017
Locations
Contacts
THE UNITED METHODIST CHURCH OF LEES SUMM, Address:114 SE DOUGLAS ST  
A L HUBER INC, Address:10770 EL MONTE, Phone:(913) 341-4880  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 05/27/2016 06/08/2016
Steve Robbins
Fees
Paid Fees Amount Paid Owing Date Paid
91100C9-Water Insp Fee $3,530.22 $3,530.22 Paid 05/27/2016
9110072-Water Test Fee $200.00 $200.00 Paid 05/27/2016
9110068-Storm Fee $4,143.15 $4,143.15 Paid 05/27/2016
9110081-Paved Surface Inspection Fee $21,411.36 $21,411.36 Paid 05/27/2016
9110071-Site Grading Fee $1,503.51 $1,503.51 Paid 05/27/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Storm - Pipe Partial 7/20/2016 07/20/2016
PW-Misc
Informational
07/20/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robbins 07/20/2016 2:58 PM
Storm - Pipe Partial 7/26/2016 08/30/2016
PW-Misc
Informational
07/20/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robbins 07/20/2016 2:58 PM
PW-Misc
Informational
08/30/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
Storm - Pipe Partial 8/31/2016 08/31/2016
PW-Misc
Informational
08/30/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robbins 07/20/2016 2:58 PM
PW-Misc
Informational
08/30/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
Storm - Pipe Partial 9/6/2016 09/06/2016
PW-Misc
Informational
08/31/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
PW-Misc
Informational
09/06/2016
Talked to Mark today and he said things will start happening tomorrow. They will have 2 or 3 crews going to try and get things done quicker,. Steve Robbins 09/06/2016 4:12 PM
PW-Misc
Informational
08/31/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robbins 07/20/2016 2:58 PM
Storm - Pipe Partial 9/7/2016 09/13/2016
PW-Misc
Informational
09/06/2016
Talked to Mark today and he said things will start happening tomorrow. They will have 2 or 3 crews going to try and get things done quicker,. Steve Robbins 09/06/2016 4:12 PM
PW-Misc
Informational
09/06/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
PW-Misc
Informational
09/06/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robb
PW-Misc
Informational
09/13/2016
On friday 9/10/16 curb inlet 1-2 was installed and also flared end section 1-1 was also installed. On monday 9/12/16 curb inlet 1-3 and the pipe was installed. Today 9/13 curb inlet 1-4 has been installed along with the pipe and rock. Steve Robbins 09/13/2016 11:32 AM
Storm - Pipe Partial 9/15/2016 09/15/2016
PW-Misc
Informational
09/13/2016
Talked to Mark today and he said things will start happening tomorrow. They will have 2 or 3 crews going to try and get things done quicker,. Steve Robbins 09/06/2016 4:12 PM
PW-Misc
Informational
09/13/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
PW-Misc
Informational
09/13/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robb
PW-Misc
Informational
09/13/2016
On friday 9/10/16 curb inlet 1-2 was installed and also flared end section 1-1 was also installed. On monday 9/12/16 curb inlet 1-3 and the pipe was installed. Today 9/13 curb inlet 1-4 has been installed along with the pipe and rock. Steve Robbins 09/13/2016 11:32 AM
PW-Misc
Informational
09/15/2016
Curb inlet 1-5 has been installed along with all pipe and rock leading up to the inlet. They are working today , but it is very muddy. Steve Robbins 09/15/2016 9:22 AM
Storm - Pipe Partial 9/19/2016 09/20/2016
PW-Misc
Informational
09/20/2016
On 9/16/16 not much was done becuase of rain for most of the week. Over the weekend They poured the collars for 1-2 to 1-5 and now those are all complete. On 9/19/16 they are installing pipe from 1-2 to inlet 2-1 . Steve Robbins 09/20/2016 12:04 PM
PW-Misc
Informational
09/15/2016
On friday 9/10/16 curb inlet 1-2 was installed and also flared end section 1-1 was also installed. On monday 9/12/16 curb inlet 1-3 and the pipe was installed. Today 9/13 curb inlet 1-4 has been installed along with the pipe and rock. Steve Robbins 09/13/2016 11:32 AM
PW-Misc
Informational
09/15/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robb
PW-Misc
Informational
09/15/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
PW-Misc
Informational
09/15/2016
Talked to Mark today and he said things will start happening tomorrow. They will have 2 or 3 crews going to try and get things done quicker,. Steve Robbins 09/06/2016 4:12 PM
PW-Misc
Informational
09/15/2016
Curb inlet 1-5 has been installed along with all pipe and rock leading up to the inlet. They are working today , but it is very muddy. Steve Robbins 09/15/2016 9:22 AM
Storm - Pipe Partial 9/21/2016 09/21/2016
PW-Misc
Informational
09/21/2016
Grate inlet 2-1 has been installed, along with all the pipe , today they are installing grate inlet 2-2 and wil finish laying all the pipe on storm line 2 Steve Robbins 09/21/2016 8:15 AM
PW-Misc
Informational
09/21/2016
Grate inlet 2-1 and 2-2 have been installed with pipe and rock, after 2-2 it reduces down for gutter drains, they are going to stop their and move over to the retention pond. They may pour the collars this afternoon. Steve Robbins 09/21/2016 9:11 AM
PW-Misc
Informational
09/20/2016
On 9/16/16 not much was done becuase of rain for most of the week. Over the weekend They poured the collars for 1-2 to 1-5 and now those are all complete. On 9/19/16 they are installing pipe from 1-2 to inlet 2-1 . Steve Robbins 09/20/2016 12:04 PM
PW-Misc
Informational
09/20/2016
On friday 9/10/16 curb inlet 1-2 was installed and also flared end section 1-1 was also installed. On monday 9/12/16 curb inlet 1-3 and the pipe was installed. Today 9/13 curb inlet 1-4 has been installed along with the pipe and rock. Steve Robbins 09/13/2016 11:32 AM
PW-Misc
Informational
09/20/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robb
PW-Misc
Informational
09/20/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
PW-Misc
Informational
09/20/2016
Talked to Mark today and he said things will start happening tomorrow. They will have 2 or 3 crews going to try and get things done quicker,. Steve Robbins 09/06/2016 4:12 PM
PW-Misc
Informational
09/20/2016
Curb inlet 1-5 has been installed along with all pipe and rock leading up to the inlet. They are working today , but it is very muddy. Steve Robbins 09/15/2016 9:22 AM
Storm - Pipe Partial 9/22/2016 09/22/2016
PW-Misc
Informational
09/22/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
Storm - Pipe Partial 9/26/2016 09/26/2016
PW-Misc
Informational
09/22/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
PW-Misc
Informational
09/26/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
PW-Misc
Informational
09/28/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
Storm - Pipe Partial 9/28/2016 09/28/2016
PW-Misc
Informational
09/26/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
PW-Misc
Informational
09/26/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
Storm - Pipe Partial 9/28/2016 09/28/2016
PW-Misc
Informational
09/28/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
PW-Misc
Informational
09/28/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
PW-Misc
Informational
09/28/2016
Curb inlets 1-6, 1-7, and 1-8 have been installed. They still have to do the collars, they are now going toward 1-9.Steve Robbins 09/28/2016 12:25 PM
Storm - Pipe Partial 9/29/2016 09/29/2016
PW-Misc
Informational
09/28/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
PW-Misc
Informational
09/28/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
PW-Misc
Informational
09/28/2016
Curb inlets 1-6, 1-7, and 1-8 have been installed. They still have to do the collars, they are now going toward 1-9.Steve Robbins 09/28/2016 12:25 PM
PW-Misc
Informational
09/29/2016
Curb inlet 1-9 and 1-10 were installed today, all pipe and rock has been installed, and collars and inverts have been poured on everything up to this point. About 50 ft. of storm pipe for storm line 6 has been installed. The flared end section has not been installed yet. Steve Robbins 09/29/2016 4:04 PM
Storm - Pipe Partial 9/30/2016 10/06/2016
PW-Misc
Informational
09/29/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
PW-Misc
Informational
10/06/2016
Yesterday storm inlet 5-1 was installed , it was installed according to plans, but it is about 3 ft below the grade. I talked to Gene about it and I talked with Mark from A.L. Huber and the engineer will be consulted about what to do and they will okay it with Gene. Steve Robbins 10/06/2016 3:40 PM
PW-Misc
Informational
09/29/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
PW-Misc
Informational
09/29/2016
Curb inlets 1-6, 1-7, and 1-8 have been installed. They still have to do the collars, they are now going toward 1-9.Steve Robbins 09/28/2016 12:25 PM
PW-Misc
Informational
09/29/2016
Curb inlet 1-9 and 1-10 were installed today, all pipe and rock has been installed, and collars and inverts have been poured on everything up to this point. About 50 ft. of storm pipe for storm line 6 has been installed. The flared end section has not been installed yet. Steve Robbins 09/29/2016 4:04 PM
Storm - Pipe Partial 10/11/2016 10/12/2016
PW-Misc
Informational
10/12/2016
Brice Lawson 10/12/2016 7:27 AM On 10/11/16 Central Plumbing installed the remaining approx. 30' of 8" HDPE roof drain pipe on the north side of the building. This section connected to the 6" PVC pipe at the building and ran to the north. They installed the 10" HDPE roof drain pipe on the west side of the building with the 90 degree elbow fitting and a short section of 12" HDPE roof drain pipe. This section connected to the building and was installed to the west just past the 90 degree elbow fitting.
PW-Misc
Informational
10/25/2016
Yesterday and today they installed the perferated pipe and the bio swale in the detention basin. They still have curb inlet 6-3 to install.Steve Robbins 10/25/2016 4:04 PM
Water Line - Fire Hydrant Partial 10/13/2016 10/13/2016
PW-Misc
Informational
10/12/2016
Brice Lawson 10/12/2016 4:34 PM Central Plumbing installed the fire hydrant assembly at STA.9+09.25.
Water Line - Construction Inspection Partial 10/13/2016 10/13/2016
PW-Misc
Informational
10/12/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/13/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
Water Line - Construction Taps Removed Partial 10/17/2016 10/17/2016
PW-Misc
Informational
10/17/2016
I was out of the office for 3 days last week, while I was gone they started the water line for fire and domestic coming out of the building, they came out about 20 ft and made the turn toward chipman rd. and laid about 40 feet of fire and domestic,.Steve Robbins 10/17/2016 7:38 AM
Water Line - Construction Inspection Partial 10/14/2016 10/17/2016
PW-Misc
Informational
10/13/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/13/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
Water Line - Construction Inspection Partial 10/19/2016 10/19/2016
PW-Misc
Informational
10/19/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/19/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
PW-Misc
Informational
10/19/2016
The water line has been installed up to approximately where the backfow preventer vault will be installed. The fire hydrants and thrust blocks have all been installed. Today they will be working on the backflow preventer.Steve Robbins 10/19/2016 7:01 AM
Sewer Service Inspection Partial 10/20/2016 10/21/2016
PW-Misc
Informational
10/21/2016
Brice Lawson 10/21/2016 7:58 AM On 10/20/16 Central Plumbing installed approx. 95' of SDR 26 sewer pipe. They connected to the building stub with a strong back fernco and ran the lateral pipe to the south approx. 95'. They poured flowable fill around these pipes at the point where these utilities cross due to the clearance issue. The end of the lateral is capped and marked with a 2 by 4 board placed vertically in the ground.
Water Line - Construction Inspection Partial 10/24/2016 10/24/2016
PW-Misc
Informational
10/19/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/24/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
PW-Misc
Informational
10/19/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
PW-Misc
Informational
10/19/2016
The water line has been installed up to approximately where the backfow preventer vault will be installed. The fire hydrants and thrust blocks have all been installed. Today they will be working on the backflow preventer.Steve Robbins 10/19/2016 7:01 AM
Water Line - Construction Inspection Partial 10/26/2016 10/25/2016
PW-Misc
Informational
10/24/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
PW-Misc
Informational
10/24/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/24/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
PW-Misc
Informational
10/24/2016
PW-Misc
Informational
10/25/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd. They were connecting the water line pipe to the backflow preventer getting ready for the water tie tomorrow. They also installed the perferated pipe that goes in the bio - swale today and yesterday.Steve Robbins 10/25/2016 3:55 PM
Water Line - Construction Inspection Partial 10/25/2016 10/25/2016
PW-Misc
Informational
10/25/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
PW-Misc
Informational
10/25/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/25/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
PW-Misc
Informational
10/25/2016
PW-Misc
Informational
10/25/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd. They were connecting the water line pipe to the backflow preventer getting ready for the water tie tomorrow. They also installed the perferated pipe that goes in the bio - swale today and yesterday.Steve Robbins 10/25/2016 3:55 PM
PW-Misc
Informational
10/25/2016
The backflow preventer has been installed and the 8"water line connected and is ready for the tie in tomorrow.Steve Robbins 10/25/2016 4:11 PM
Storm Sewer Construction Inspection Partial 10/25/2016 10/25/2016
PW-Misc
Informational
10/25/2016
The bio-swale and perforated pipe has also been installed in the detention basin.Steve Robbins 10/25/2016 4:18 PM
Water Line - Construction Inspection Partial 10/26/2016 10/26/2016
PW-Misc
Informational
10/25/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
PW-Misc
Informational
10/25/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/25/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
PW-Misc
Informational
10/25/2016
PW-Misc
Informational
10/25/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd. They were connecting the water line pipe to the backflow preventer getting ready for the water tie tomorrow. They also installed the perferated pipe that goes in the bio - swale today and yesterday.Steve Robbins 10/25/2016 3:55 PM
PW-Misc
Informational
10/25/2016
The backflow preventer has been installed and the 8"water line connected and is ready for the tie in tomorrow.Steve Robbins 10/25/2016 4:11 PM
PW-Misc
Informational
10/26/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
Water Line - Construction Inspection Passed 10/27/2016 10/26/2016
PW-Misc
Informational
10/26/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
PW-Misc
Informational
10/26/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/26/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
PW-Misc
Informational
10/26/2016
PW-Misc
Informational
10/26/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd. They were connecting the water line pipe to the backflow preventer getting ready for the water tie tomorrow. They also installed the perferated pipe that goes in the bio - swale today and yesterday.Steve Robbins 10/25/2016 3:55 PM
PW-Misc
Informational
10/26/2016
The backflow preventer has been installed and the 8"water line connected and is ready for the tie in tomorrow.Steve Robbins 10/25/2016 4:11 PM
PW-Misc
Informational
10/26/2016
The fire line and domestic line have been completed up to the backflow preventer vault which was installed on 10/20/16, I passed out door hangars today for a water shutdown on wednesday for the water tie in on the main line on chipman rd.Steve Robbins 10/24/2016 3:53 PM
Storm Sewer Construction Inspection Passed 10/26/2016 10/26/2016
PW-Misc
Informational
10/25/2016
The bio-swale and perforated pipe has also been installed in the detention basin.Steve Robbins 10/25/2016 4:18 PM
Fire Line Construction Inspection Partial 10/26/2016 10/26/2016
PW-Misc
Informational
10/26/2016
Today they tied in the 8' fire line to the public main water line. They poured the thrust block and polywrapped the connections. The water dept. also came out and did the 2' domestic water tap.Steve Robbins 10/26/2016 4:29 PM
Fire Line - Flush Passed 11/2/2016 11/04/2016
Fire Line - Hydrostatic Test Passed 10/28/2016 11/09/2016
PW-Misc
Informational
11/09/2016
Hydrostatic pressure test has been completed.Steve Robbins 11/09/2016 2:57 PM
Storm - Rip Rap Passed 10/27/2016 11/11/2016
PW-Misc
Informational
11/11/2016
On 10/27/16 the rip rap for the north detention basin was installed . The bio-swale has been installed and the perferated pipe also.Steve Robbins 11/11/2016 2:49 PM
Curb - Proof Roll Partial 11/17/2016 11/17/2016
PW-Misc
Informational
11/17/2016
They did a proofroll on the dirt, and today they started installing the geo-grid and rock. They will still need a proofroll after they get all the geo-grid and rock down.Steve Robbins 11/17/2016 4:09 PM
Fire Line Construction Inspection Passed 10/27/2016 12/02/2016
PW-Misc
Informational
10/26/2016
Today they tied in the 8' fire line to the public main water line. They poured the thrust block and polywrapped the connections. The water dept. also came out and did the 2' domestic water tap.Steve Robbins 10/26/2016 4:29 PM
PW-Misc
Informational
12/02/2016
Steve Robbins 12/02/2016 11:38 AMAll the fire lines have been completed and and fire hydrants have been installed.
Proof roll parking lot Partial 12/14/2016
PW-Misc
Informational
12/14/2016
The curbs are installed in the parking lot, they did a proofroll for the parking lot before they started installing type 3 rock and geo-grid. So far the south and east sides of the parking lot have been rocked with geo-grid installed. We probably will not do a proof roll until spring because no ashpalt will be installed this winter.Steve Robbins 12/14/2016 3:53 PM
Curb - Proof Roll Passed 11/18/2016 12/14/2016
PW-Misc
Informational
11/17/2016
They did a proofroll on the dirt, and today they started installing the geo-grid and rock. They will still need a proofroll after they get all the geo-grid and rock down.Steve Robbins 11/17/2016 4:09 PM
PW-Misc
Corrective Action Required
12/14/2016
All the curbs have been installed and they are putting in rock and geo-grid now.Steve Robbins 12/14/2016 4:09 PM
Proof roll parking lot Partial 12/15/2016 12/15/2016
PW-Misc
Informational
12/14/2016
The curbs are installed in the parking lot, they did a proofroll for the parking lot before they started installing type 3 rock and geo-grid. So far the south and east sides of the parking lot have been rocked with geo-grid installed. We probably will not do a proof roll until spring because no ashpalt will be installed this winter.Steve Robbins 12/14/2016 3:53 PM
PW-Misc
Informational
12/15/2016
Today they are grading west side of the parking lot trying to get it ready for geo-grid and rock.Steve Robbins 12/15/2016 2:49 PM
Proof roll parking lot Partial 12/21/2016 12/21/2016
PW-Misc
Informational
12/15/2016
The curbs are installed in the parking lot, they did a proofroll for the parking lot before they started installing type 3 rock and geo-grid. So far the south and east sides of the parking lot have been rocked with geo-grid installed. We probably will not do a proof roll until spring because no ashpalt will be installed this winter.Steve Robbins 12/14/2016 3:53 PM
PW-Misc
Informational
12/15/2016
Today they are grading west side of the parking lot trying to get it ready for geo-grid and rock.Steve Robbins 12/15/2016 2:49 PM
PW-Misc
Informational
12/21/2016
So far all the parking lot has curb, rock and geo -grid installed except for the west side which they are working on today to get in graded so they can put the rock and geo-grid down.Steve Robbins 12/21/2016 10:50 AM
Pavement-Stabilized Subgrade Partial 12/27/2016 12/27/2016
PW-Misc
Informational
12/27/2016
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
Storm - Pipe Partial 9/22/2016 12/28/2016
PW-Misc
Informational
09/21/2016
Grate inlet 2-1 has been installed, along with all the pipe , today they are installing grate inlet 2-2 and wil finish laying all the pipe on storm line 2 Steve Robbins 09/21/2016 8:15 AM
PW-Misc
Informational
12/28/2016
They still have one more structure to install in order to complete all the storm.Steve Robbins 12/28/2016 7:23 AM
PW-Misc
Informational
09/21/2016
On 9/16/16 not much was done becuase of rain for most of the week. Over the weekend They poured the collars for 1-2 to 1-5 and now those are all complete. On 9/19/16 they are installing pipe from 1-2 to inlet 2-1 . Steve Robbins 09/20/2016 12:04 PM
PW-Misc
Informational
09/21/2016
On friday 9/10/16 curb inlet 1-2 was installed and also flared end section 1-1 was also installed. On monday 9/12/16 curb inlet 1-3 and the pipe was installed. Today 9/13 curb inlet 1-4 has been installed along with the pipe and rock. Steve Robbins 09/13/2016 11:32 AM
PW-Misc
Informational
09/21/2016
Yesterday 7/19/16 and today they were digging for storm pipe to go in and putting in a field inlet, they discovered that they have 2 wrong inlet boxes , so they will not be working until they can get the new boxes delivered.Steve Robb
PW-Misc
Informational
09/21/2016
The correct storm boxes have been delivered and now they are waiting to get rid of some of the water and mudd so they can resume work. Steve Robbins 08/30/2016 7:30 AM
PW-Misc
Informational
09/21/2016
Talked to Mark today and he said things will start happening tomorrow. They will have 2 or 3 crews going to try and get things done quicker,. Steve Robbins 09/06/2016 4:12 PM
PW-Misc
Informational
09/21/2016
Curb inlet 1-5 has been installed along with all pipe and rock leading up to the inlet. They are working today , but it is very muddy. Steve Robbins 09/15/2016 9:22 AM
Pavement-Stabilized Subgrade Partial 12/28/2016 12/29/2016
PW-Misc
Informational
12/27/2016
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
12/29/2016
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
Pavement-Stabilized Subgrade Partial 12/30/2016 12/30/2016
PW-Misc
Informational
12/29/2016
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
12/30/2016
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
12/29/2016
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
Pavement-Stabilized Subgrade Partial 1/3/2017 01/04/2017
PW-Misc
Informational
12/30/2016
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/04/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
12/30/2016
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
12/30/2016
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
Pavement-Stabilized Subgrade Partial 1/6/2017 01/06/2017
PW-Misc
Informational
01/04/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/04/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/04/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/04/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/06/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
Water Line - Thrust Restraint Passed 10/14/2016 01/06/2017
PW-Misc
Informational
01/06/2017
All thrust blocks and restraints have been installed and inspected.Steve Robbins 01/06/2017 2:09 PM
Water Line - Valve Passed 1/13/2017 01/06/2017
Pavement-Stabilized Subgrade Partial 1/9/2017 01/09/2017
PW-Misc
Informational
01/06/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/09/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/06/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/06/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/06/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/06/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
Pavement-Stabilized Subgrade Partial 1/10/2017 01/11/2017
PW-Misc
Informational
01/09/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/11/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/09/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/09/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/09/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/09/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/09/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
Pavement-Stabilized Subgrade Partial 1/12/2017 01/12/2017
PW-Misc
Informational
01/12/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/11/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/11/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/11/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/11/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/11/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/11/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/11/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
Driveway Inspection Partial 1/19/2017 01/19/2017
PW-Misc
Informational
01/19/2017
The driveway entrance on the south end of the church off ashurst has been formed , rocked , copacted and concrete installed.There will be one more driveway entrance on the north side.Steve Robbins 01/19/2017 9:36 AM
Pavement-Stabilized Subgrade Partial 1/13/2017 01/19/2017
PW-Misc
Informational
01/12/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/19/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/12/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/12/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/12/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/12/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/12/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/12/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/12/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
Pavement-Stabilized Subgrade Partial 1/20/2017 01/20/2017
PW-Misc
Informational
01/19/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/19/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/19/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/19/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/19/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/19/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/19/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/19/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/19/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/20/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
Pavement-Stabilized Subgrade Partial 1/23/2017 01/23/2017
PW-Misc
Informational
01/23/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/20/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/20/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/20/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/20/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/20/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/20/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/20/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/20/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/20/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/20/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
Pavement-Stabilized Subgrade Partial 1/24/2017 01/24/2017
PW-Misc
Informational
01/23/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/24/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/23/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/23/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/23/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/23/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/23/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/23/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/23/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/23/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/23/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/23/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
Pavement-Stabilized Subgrade Partial 1/25/2017 01/25/2017
PW-Misc
Informational
01/24/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/24/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/24/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/24/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/24/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/24/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/24/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/24/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/24/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/24/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/24/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/24/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
01/25/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 1/26/2017 01/26/2017
PW-Misc
Informational
01/25/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/26/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
01/25/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/25/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/25/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/25/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/25/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/25/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/25/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/25/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/25/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/25/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/25/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
01/25/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 1/27/2017 01/27/2017
PW-Misc
Informational
01/26/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
01/27/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
01/26/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/26/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/26/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/26/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/26/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/26/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/26/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/26/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/26/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/26/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/26/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/26/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
01/26/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 1/30/2017 01/30/2017
PW-Misc
Informational
01/30/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
01/27/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
01/27/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
01/27/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/27/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/27/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/27/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/27/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/27/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/27/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/27/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/27/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/27/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/27/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/27/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
01/27/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 1/31/2017 01/31/2017
PW-Misc
Informational
01/30/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
01/31/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
01/30/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
01/30/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
01/30/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/30/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/30/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/30/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/30/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/30/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/30/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/30/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/30/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/30/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/30/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/30/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
01/30/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 2/1/2017 02/01/2017
PW-Misc
Informational
02/01/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
01/31/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
01/31/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
01/31/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
01/31/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
01/31/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
01/31/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
01/31/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
01/31/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
01/31/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
01/31/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
01/31/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
01/31/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
01/31/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
01/31/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
01/31/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
01/31/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
01/31/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 2/2/2017 02/02/2017
PW-Misc
Informational
02/01/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/02/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/01/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/01/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/01/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/01/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/01/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/01/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/01/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/01/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/01/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/01/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/01/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/01/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/01/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/01/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/01/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/01/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/01/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 2/3/2017 02/03/2017
PW-Misc
Informational
02/02/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/03/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/02/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/02/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/02/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/02/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/02/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/02/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/02/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/02/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/02/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/02/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/02/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/02/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/02/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/02/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/02/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/02/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/02/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/02/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 2/6/2017 02/06/2017
PW-Misc
Informational
02/03/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/06/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/03/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/03/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/03/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/03/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/03/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/03/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/03/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/03/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/03/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/03/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/03/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/03/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/03/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/03/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/03/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/03/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/03/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/03/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/03/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
Pavement-Stabilized Subgrade Partial 2/7/2017 02/07/2017
PW-Misc
Informational
02/06/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/06/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/06/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/06/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/06/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/06/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/06/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/06/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/06/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/06/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/06/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/06/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/06/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/06/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/06/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/06/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/06/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/06/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/06/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/06/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/06/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/07/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/8/2017 02/08/2017
PW-Misc
Informational
02/07/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/08/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/07/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/07/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/07/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/07/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/07/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/07/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/07/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/07/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/07/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/07/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/07/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/07/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/07/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/07/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/07/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/07/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/07/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/07/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/07/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/07/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/07/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/9/2017 02/09/2017
PW-Misc
Informational
02/08/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/09/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/08/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/08/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/08/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/08/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/08/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/08/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/08/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/08/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/08/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/08/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/08/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/08/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/08/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/08/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/08/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/08/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/08/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/08/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/08/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/08/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/08/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/08/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Storm - Pipe Passed 2/9/2017 02/09/2017
PW-Misc
Informational
10/12/2016
Brice Lawson 10/12/2016 7:27 AM On 10/11/16 Central Plumbing installed the remaining approx. 30' of 8" HDPE roof drain pipe on the north side of the building. This section connected to the 6" PVC pipe at the building and ran to the north. They installed the 10" HDPE roof drain pipe on the west side of the building with the 90 degree elbow fitting and a short section of 12" HDPE roof drain pipe. This section connected to the building and was installed to the west just past the 90 degree elbow fitting.
PW-Misc
Informational
02/09/2017
Today they put the new section on top of inlet 5-1 which was about 2 ft too low. this completes all the storm inlets.Steve Robbins 02/09/2017 11:30 AM
Storm - Pipe Passed 10/7/2016 02/09/2017
PW-Misc
Informational
10/06/2016
Yesterday storm inlet 5-1 was installed , it was installed according to plans, but it is about 3 ft below the grade. I talked to Gene about it and I talked with Mark from A.L. Huber and the engineer will be consulted about what to do and they will okay it with Gene. Steve Robbins 10/06/2016 3:40 PM. It rained today so there so not anyone working.
PW-Misc
Informational
10/06/2016
Curb inlet 3-1,3-2, and 3-3, were installed today along with rock and pipe. They will probably pour the collars tomorrow. They also asked about the tree that is in the way for the flared end section coming out of structure 7-2, I talked to Gene and he said they can remove the tree as long as its in the ROW or on the church property. It is in the way of the rip rap they need to install.Steve Robbins 09/26/2016 2:29 PM
PW-Misc
Informational
10/06/2016
On storm line 2 grate inlet 2-1 and 2-2 has been installed with pipe and all the rock. They also poured the collars for these 2 structures. Structure 7.2 has been installed in the retention pond along with the pipe and flared end section. They are going to need to cut down a tree before they put in the rip rap, there are also cable lines and power lines in the way,. Steve Robbins 09/22/2016 5:05 PM
PW-Misc
Informational
10/06/2016
Curb inlets 1-6, 1-7, and 1-8 have been installed. They still have to do the collars, they are now going toward 1-9.Steve Robbins 09/28/2016 12:25 PM
PW-Misc
Informational
10/06/2016
Curb inlet 1-9 and 1-10 were installed today, all pipe and rock has been installed, and collars and inverts have been poured on everything up to this point. About 50 ft. of storm pipe for storm line 6 has been installed. The flared end section has not been installed yet. Steve Robbins 09/29/2016 4:04 PM
PW-Misc
Informational
02/09/2017
Today they installed inlet 5-1 and brought it up to grade level which was about 3 ft low. This plan was approved by Gene and the engineer for summit church.Steve Robbins 02/09/2017 11:35 AM
Pavement-Stabilized Subgrade Partial 2/13/2017 02/13/2017
PW-Misc
Informational
02/09/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/13/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/09/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/09/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/09/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/09/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/09/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/09/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/09/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/09/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/09/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/09/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/09/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/09/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/09/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/09/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/09/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/09/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/09/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/09/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/09/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/09/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/09/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/09/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/09/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/14/2017 02/14/2017
PW-Misc
Informational
02/13/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/14/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/13/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/13/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/13/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/13/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/13/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/13/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/13/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/13/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/13/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/13/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/13/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/13/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/13/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/13/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/13/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/13/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/13/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/13/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/13/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/13/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/13/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/13/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/13/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/13/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/15/2017 02/15/2017
PW-Misc
Informational
02/14/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/15/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/14/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/14/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/14/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/14/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/14/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/14/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/14/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/14/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/14/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/14/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/14/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/14/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/14/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/14/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/14/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/14/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/14/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/14/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/14/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/14/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/14/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/14/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/14/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/14/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/14/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/16/2017 02/16/2017
PW-Misc
Informational
02/15/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/16/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/15/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/15/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/15/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/15/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/15/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/15/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/15/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/15/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/15/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/15/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/15/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/15/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/15/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/15/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/15/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/15/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/15/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/15/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/15/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/15/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/15/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/15/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/15/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/15/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/15/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/15/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/17/2017 02/17/2017
PW-Misc
Informational
02/17/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/16/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/16/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/16/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/16/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/16/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/16/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/16/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/16/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/16/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/16/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/16/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/16/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/16/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/16/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/16/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/16/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/16/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/16/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/16/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/16/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/16/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/16/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/16/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/16/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/16/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/16/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/16/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/16/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
Pavement-Stabilized Subgrade Partial 2/21/2017 02/21/2017
PW-Misc
Informational
02/17/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/17/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/17/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/17/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/17/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/17/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/17/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/17/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/17/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/17/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/17/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/17/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/17/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/17/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/17/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/17/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/17/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/17/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/17/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/17/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/17/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/17/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/17/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/17/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/17/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/17/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/17/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/17/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/17/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/21/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/21/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/21/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/21/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/21/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/21/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/21/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/21/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/21/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/21/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/21/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/21/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/21/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/21/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/21/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/21/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/21/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/21/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/21/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/21/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/21/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/21/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/21/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/21/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/21/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/21/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/21/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
Pavement-Stabilized Subgrade Partial 2/22/2017 02/22/2017
PW-Misc
Informational
02/21/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/22/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
02/21/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/21/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/21/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/21/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/21/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/21/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/21/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/21/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/21/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/21/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/21/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/21/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/21/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/21/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/21/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/21/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/21/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/21/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/21/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/21/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/21/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/21/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/21/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/21/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/21/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/21/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/21/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/21/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/21/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/21/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/21/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/21/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/21/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/21/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/21/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/21/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/21/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/21/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/21/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/21/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/21/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/21/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/21/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/21/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/21/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/21/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/21/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/21/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/21/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/21/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/21/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/21/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/21/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
Pavement-Stabilized Subgrade Partial 2/23/2017 02/23/2017
PW-Misc
Informational
02/22/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
02/22/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/22/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/22/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/22/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/22/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/22/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/22/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/22/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/22/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/22/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/22/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/22/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/22/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/22/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/22/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/22/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/22/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/22/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/22/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/22/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/22/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/22/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/22/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/22/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/22/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/22/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/22/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/22/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/22/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/22/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/22/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/22/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/22/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/22/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/22/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/22/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/22/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/22/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/22/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/22/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/22/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/22/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/22/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/22/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/22/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/22/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/22/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/22/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/22/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/22/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/22/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/22/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/22/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/22/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/22/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/22/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/22/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/22/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/22/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
02/23/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
Pavement-Stabilized Subgrade Partial 2/24/2017 02/24/2017
PW-Misc
Informational
02/23/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
02/24/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
02/23/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/23/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/23/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/23/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/23/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/23/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/23/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/23/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/23/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/23/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/23/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/23/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/23/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/23/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/23/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/23/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/23/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/23/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/23/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/23/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/23/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/23/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/23/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/23/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/23/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/23/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/23/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/23/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/23/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/23/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/23/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/23/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/23/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/23/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/23/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/23/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/23/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/23/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/23/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/23/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/23/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/23/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/23/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/23/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/23/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/23/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/23/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/23/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/23/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/23/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/23/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/23/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/23/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/23/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/23/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/23/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/23/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/23/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/23/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
02/23/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
Pavement-Stabilized Subgrade Partial 2/28/2017 02/28/2017
PW-Misc
Informational
02/24/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
02/28/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
02/24/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
02/24/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/24/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/24/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/24/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/24/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/24/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/24/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/24/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/24/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/24/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/24/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/24/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/24/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/24/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/24/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/24/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/24/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/24/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/24/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/24/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/24/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/24/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/24/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/24/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/24/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/24/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/24/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/24/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/24/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/24/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/24/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/24/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/24/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/24/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/24/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/24/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/24/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/24/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/24/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/24/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/24/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/24/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/24/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/24/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/24/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/24/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/24/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/24/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/24/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/24/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/24/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/24/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/24/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/24/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/24/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/24/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/24/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/24/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/24/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
02/24/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
Pavement-Stabilized Subgrade Partial 3/1/2017 03/01/2017
PW-Misc
Informational
02/28/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/01/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
02/28/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
02/28/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
02/28/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/28/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/28/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/28/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/28/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/28/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/28/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/28/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/28/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/28/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/28/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/28/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/28/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/28/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/28/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/28/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/28/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/28/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/28/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/28/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/28/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/28/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/28/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/28/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/28/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/28/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/28/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/28/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/28/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/28/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
02/28/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
02/28/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
02/28/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
02/28/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
02/28/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
02/28/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
02/28/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
02/28/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
02/28/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
02/28/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
02/28/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
02/28/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
02/28/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
02/28/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
02/28/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
02/28/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
02/28/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
02/28/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
02/28/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
02/28/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
02/28/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
02/28/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
02/28/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
02/28/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
02/28/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
02/28/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
02/28/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
02/28/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
02/28/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
02/28/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
Pavement-Stabilized Subgrade Partial 3/2/2017 03/02/2017
PW-Misc
Informational
03/01/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/01/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/01/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/01/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/01/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/01/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/01/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/01/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/01/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/01/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/01/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/01/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/01/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/01/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/01/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/01/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/01/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/01/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/01/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/01/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/01/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/01/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/01/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/01/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/01/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/01/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/01/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/01/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/01/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/01/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/01/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/01/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/01/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/01/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/01/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/01/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/01/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/01/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/01/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/01/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/01/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/01/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/01/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/01/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/01/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/01/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/01/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/01/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/01/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/01/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/01/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/01/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/01/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/01/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/01/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/01/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/01/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/01/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/01/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/01/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/01/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/01/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/01/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/01/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/02/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
Pavement-Stabilized Subgrade Partial 3/3/2017 03/03/2017
PW-Misc
Informational
03/02/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/03/2017
I told the contractor with summit concrete they are going to have to mill the entrance 2" and replace with asphalt.Steve Robbins 03/03/2017 2:49 PM
PW-Misc
Informational
03/02/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/02/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/02/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/02/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/02/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/02/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/02/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/02/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/02/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/02/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/02/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/02/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/02/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/02/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/02/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/02/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/02/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/02/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/02/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/02/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/02/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/02/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/02/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/02/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/02/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/02/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/02/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/02/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/02/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/02/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/02/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/02/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/02/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/02/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/02/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/02/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/02/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/02/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/02/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/02/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/02/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/02/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/02/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/02/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/02/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/02/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/02/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/02/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/02/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/02/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/02/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/02/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/02/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/02/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/02/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/02/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/02/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/02/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/02/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/02/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/02/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/02/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/02/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/02/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
Pavement-Stabilized Subgrade Partial 3/6/2017 03/06/2017
PW-Misc
Informational
03/03/2017
I told the contractor with summit concrete they are going to have to mill the entrance 2" and replace with asphalt.Steve Robbins 03/03/2017 2:49 PM
PW-Misc
Informational
03/03/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/03/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/03/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/03/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/03/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/03/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/03/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/03/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/03/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/03/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/03/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/03/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/03/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/03/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/03/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/03/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/03/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/03/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/03/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/03/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/03/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/03/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/03/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/03/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/03/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/03/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/03/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/03/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/03/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/03/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/03/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/03/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/03/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/03/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/03/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/03/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/03/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/03/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/03/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/03/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/03/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/03/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/03/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/03/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/03/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/03/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/03/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/03/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/03/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/03/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/03/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/03/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/03/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/03/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/03/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/03/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/03/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/03/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/03/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/03/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/03/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/03/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/03/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/03/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/03/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
PW-Misc
Informational
03/06/2017
Summit Concrete is milling 2" off the entrance today and getting ready for ashpalt.Steve Robbins 03/06/2017 9:30 AM
Pavement-Stabilized Subgrade Partial 3/7/2017 03/07/2017
PW-Misc
Informational
03/06/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/07/2017
They are not doing any milling today, they still have a portion going to the east and then they will have finished it all.Steve Robbins 03/07/2017 1:16 PM
PW-Misc
Informational
03/06/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/06/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/06/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/06/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/06/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/06/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/06/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/06/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/06/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/06/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/06/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/06/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/06/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/06/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/06/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/06/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/06/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/06/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/06/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/06/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/06/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/06/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/06/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/06/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/06/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/06/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/06/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/06/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/06/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/06/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/06/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/06/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/06/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/06/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/06/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/06/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/06/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/06/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/06/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/06/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/06/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
PW-Misc
Informational
03/06/2017
I told the contractor with summit concrete they are going to have to mill the entrance 2" and replace with asphalt.Steve Robbins 03/03/2017 2:49 PM
PW-Misc
Informational
03/06/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/06/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/06/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/06/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/06/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/06/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/06/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/06/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/06/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/06/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/06/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/06/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/06/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/06/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/06/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/06/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/06/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/06/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/06/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/06/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/06/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/06/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/06/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/06/2017
Summit Concrete is milling 2" off the entrance today and getting ready for ashpalt.Steve Robbins 03/06/2017 9:30 AM
Pavement-Stabilized Subgrade Partial 3/8/2017 03/08/2017
PW-Misc
Informational
03/07/2017
They are not doing any milling today, they still have a portion going to the east and then they will have finished it all.Steve Robbins 03/07/2017 1:16 PM
PW-Misc
Informational
03/07/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/07/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/07/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/07/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/07/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/07/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/07/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/07/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/07/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/07/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/07/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/07/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/07/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/07/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/07/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/07/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/07/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/07/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/07/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/07/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/07/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/07/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/07/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/07/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/07/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/07/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/07/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/07/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/07/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/07/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/07/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/07/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/07/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/07/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/07/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/07/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/07/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/07/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/07/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/07/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/07/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/07/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
PW-Misc
Informational
03/07/2017
I told the contractor with summit concrete they are going to have to mill the entrance 2" and replace with asphalt.Steve Robbins 03/03/2017 2:49 PM
PW-Misc
Informational
03/07/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/07/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/07/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/07/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/07/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/07/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/07/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/07/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/07/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/07/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/07/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/07/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/07/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/07/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/07/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/07/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/07/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/07/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/07/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/07/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/07/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/07/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/07/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/07/2017
Summit Concrete is milling 2" off the entrance today and getting ready for ashpalt.Steve Robbins 03/06/2017 9:30 AM
PW-Misc
Informational
03/08/2017
Today they finished milling the rest of the entrance up next to the curb. They still have to clean the millings up.Steve Robbins 03/08/2017 3:03 PM
Storm - Pipe Passed 1/6/2017 03/09/2017
PW-Misc
Informational
03/09/2017
All the storm pipe has been installed, and all the swales by the end of the parking lot, along with the rip rap has been installed.Steve Robbins 03/09/2017 3:29 PM
Pavement-Stabilized Subgrade Partial 3/9/2017 03/09/2017
PW-Misc
Informational
03/08/2017
They are not doing any milling today, they still have a portion going to the east and then they will have finished it all.Steve Robbins 03/07/2017 1:16 PM
PW-Misc
Informational
03/09/2017
Today they cleaned up the millings from the entrance that they finished milling yesterday. I am planning on doing a parking lot proofroll in the morning.Steve Robbins 03/09/2017 3:45 PM
PW-Misc
Informational
03/08/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/08/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/08/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/08/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/08/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/08/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/08/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/08/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/08/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/08/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/08/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/08/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/08/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/08/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/08/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/08/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/08/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/08/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/08/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/08/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/08/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/08/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/08/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/08/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/08/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/08/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/08/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/08/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/08/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/08/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/08/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/08/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/08/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/08/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/08/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/08/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/08/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/08/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/08/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/08/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/08/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/08/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
PW-Misc
Informational
03/08/2017
I told the contractor with summit concrete they are going to have to mill the entrance 2" and replace with asphalt.Steve Robbins 03/03/2017 2:49 PM
PW-Misc
Informational
03/08/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/08/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/08/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/08/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/08/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/08/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/08/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/08/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/08/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/08/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/08/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/08/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/08/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/08/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/08/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/08/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/08/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/08/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/08/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/08/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/08/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/08/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/08/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/08/2017
Summit Concrete is milling 2" off the entrance today and getting ready for ashpalt.Steve Robbins 03/06/2017 9:30 AM
PW-Misc
Informational
03/08/2017
Today they finished milling the rest of the entrance up next to the curb. They still have to clean the millings up.Steve Robbins 03/08/2017 3:03 PM
Proof roll parking lot Partial 3/10/2017 03/10/2017
PW-Misc
Informational
12/21/2016
The curbs are installed in the parking lot, they did a proofroll for the parking lot before they started installing type 3 rock and geo-grid. So far the south and east sides of the parking lot have been rocked with geo-grid installed. We probably will not do a proof roll until spring because no ashpalt will be installed this winter.Steve Robbins 12/14/2016 3:53 PM
PW-Misc
Informational
03/10/2017
We did a partial proofroll of the parking lot today, the west side and the entrance off of ashurst. The proofroll on ashurst is good to go, but the parking lot has 3 areas that need to dry out, with the weather coming in this weekend it is ulnlikely they will be able to ashplat on monday.Steve Robbins 03/10/2017 3:40 PM
PW-Misc
Informational
12/21/2016
Today they are grading west side of the parking lot trying to get it ready for geo-grid and rock.Steve Robbins 12/15/2016 2:49 PM
PW-Misc
Informational
12/21/2016
So far all the parking lot has curb, rock and geo -grid installed except for the west side which they are working on today to get in graded so they can put the rock and geo-grid down.Steve Robbins 12/21/2016 10:50 AM
Proof roll parking lot Partial 3/13/2017 03/13/2017
PW-Misc
Informational
03/10/2017
We did a partial proofroll of the parking lot today, the west side and the entrance off of ashurst. The proofroll on ashurst is good to go, but the parking lot has 3 areas that need to dry out, with the weather coming in this weekend it is ulnlikely they will be able to ashplat on monday.Steve Robbins 03/10/2017 3:40 PM
PW-Misc
Informational
03/13/2017
No work in the parking lot today because of weather.Steve Robbins 03/13/2017 4:01 PM
PW-Misc
Informational
03/10/2017
The curbs are installed in the parking lot, they did a proofroll for the parking lot before they started installing type 3 rock and geo-grid. So far the south and east sides of the parking lot have been rocked with geo-grid installed. We probably will not do a proof roll until spring because no ashpalt will be installed this winter.Steve Robbins 12/14/2016 3:53 PM
PW-Misc
Informational
03/10/2017
Today they are grading west side of the parking lot trying to get it ready for geo-grid and rock.Steve Robbins 12/15/2016 2:49 PM
PW-Misc
Informational
03/10/2017
So far all the parking lot has curb, rock and geo -grid installed except for the west side which they are working on today to get in graded so they can put the rock and geo-grid down.Steve Robbins 12/21/2016 10:50 AM
Pavement-Surface Partial 3/17/2017 03/17/2017
PW-Misc
Informational
03/17/2017
Today they intalled base rock on west side of the parking lot, they are letting one section dry out until monday, they are also going to start the base for the street on monday, ashurst.Steve Robbins 03/17/2017 4:10 PM
Proof roll parking lot Passed 3/20/2017 03/20/2017
PW-Misc
Informational
03/13/2017
No work in the parking lot today because of weather.Steve Robbins 03/13/2017 4:01 PM
PW-Misc
Informational
03/13/2017
We did a partial proofroll of the parking lot today, the west side and the entrance off of ashurst. The proofroll on ashurst is good to go, but the parking lot has 3 areas that need to dry out, with the weather coming in this weekend it is ulnlikely they will be able to ashplat on monday.Steve Robbins 03/10/2017 3:40 PM
PW-Misc
Informational
03/13/2017
The curbs are installed in the parking lot, they did a proofroll for the parking lot before they started installing type 3 rock and geo-grid. So far the south and east sides of the parking lot have been rocked with geo-grid installed. We probably will not do a proof roll until spring because no ashpalt will be installed this winter.Steve Robbins 12/14/2016 3:53 PM
PW-Misc
Informational
03/13/2017
Today they are grading west side of the parking lot trying to get it ready for geo-grid and rock.Steve Robbins 12/15/2016 2:49 PM
PW-Misc
Informational
03/13/2017
So far all the parking lot has curb, rock and geo -grid installed except for the west side which they are working on today to get in graded so they can put the rock and geo-grid down.Steve Robbins 12/21/2016 10:50 AM
PW-Misc
Informational
03/20/2017
All of the proofrolls for the parking lot and the public street have passed.Steve Robbins 03/20/2017 3:04 PM
Pavement-Surface Partial 3/20/2017 03/20/2017
PW-Misc
Informational
03/17/2017
Today they intalled base rock on west side of the parking lot, they are letting one section dry out until monday, they are also going to start the base for the street on monday, ashurst.Steve Robbins 03/17/2017 4:10 PM
PW-Misc
Informational
03/20/2017
Today they installed base rock for the street ashurst coming off view high. They are also installing base rock in the parking lot for entrance off ashurst. They will be working their way around the parking lot. The area that has been in question on the west side of the building is still dryin g out, a sprinkler line broke over the weekend and flooded the area again.Steve Robbins 03/20/2017 3:11 PM
Pavement-Surface Passed 3/21/2017 03/21/2017
PW-Misc
Informational
03/20/2017
Today they intalled base rock on west side of the parking lot, they are letting one section dry out until monday, they are also going to start the base for the street on monday, ashurst.Steve Robbins 03/17/2017 4:10 PM
PW-Misc
Informational
03/20/2017
Today they installed base rock for the street ashurst coming off view high. They are also installing base rock in the parking lot for entrance off ashurst. They will be working their way around the parking lot. The area that has been in question on the west side of the building is still dryin g out, a sprinkler line broke over the weekend and flooded the area again.Steve Robbins 03/20/2017 3:11 PM
PW-Misc
Informational
03/21/2017
Today they installed base rock for the rest of the parking lot and in the area in front of the entrance to the buildig where they installed more AB-3. They also installed the base rock for the public street. This morning we did a string line test from curb to curb to make sure they had the proper dept.Steve Robbins 03/21/2017 4:02 PM
Pavement-Proof Roll Passed 3/27/2017 03/27/2017
Corrective Action Required
03/27/2017
PW-Misc
Informational
03/27/2017
The proofroll for the two public streets has passed. I have documented this with the proofroll for the parking lot.Steve Robbins 03/27/2017 7:51 AM
Water Line - Construction Inspection Passed 11/3/2016 03/27/2017
PW-Misc
Informational
10/17/2016
Brice Lawson 10/12/2016 4:30 PM Central Plumbing installed approx. 235' of 8" C900 water line starting at 9+09.25 towards the west.
PW-Misc
Informational
10/17/2016
Brice Lawson 10/13/2016 4:29 PM Central Plumbing installed approx. 165' of 8" C900 water line. They continued where they left off on 10/12 and installed pipe to the T fitting where this line branches to the building.
Curb - Compression Strength Passed 3/27/2017 03/27/2017
Storm - Outlet Structure Passed 3/27/2017 03/27/2017
PW-Misc
Informational
03/27/2017
All storm outlet structures has been installed on this job.Steve Robbins 03/27/2017 8:12 AM
Pavement-Stabilized Subgrade Passed 3/27/2017 03/27/2017
PW-Misc
Informational
03/09/2017
Today they cleaned up the millings from the entrance that they finished milling yesterday. I am planning on doing a parking lot proofroll in the morning.Steve Robbins 03/09/2017 3:45 PM
PW-Misc
Informational
03/27/2017
All the subgrade has been installed and stabilized.Steve Robbins 03/27/2017 8:16 AM
PW-Misc
Informational
03/09/2017
They are not doing any milling today, they still have a portion going to the east and then they will have finished it all.Steve Robbins 03/07/2017 1:16 PM
PW-Misc
Informational
03/09/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/09/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/09/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/09/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/09/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/09/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/09/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/09/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/09/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/09/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/09/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/09/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/09/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/09/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/09/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/09/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/09/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/09/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/09/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/09/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/09/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/09/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/09/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/09/2017
Talked to contractor and they are going to form the entrances for both public streets and pour them on tuesdaylSteve Robbins 02/24/2017 4:17 PM
PW-Misc
Informational
03/09/2017
Today they installed the curbs for the 2 public roads , the one off chipman and the one off viewhigh.Steve Robbins 02/22/2017 4:02 PM
PW-Misc
Informational
03/09/2017
No work in the parking lot was done today, and no work on the public street.Steve Robbins 01/23/2017 2:46 PM
PW-Misc
Informational
03/09/2017
No work was being done on the parking lot today. They still need geo-grid and rock on the west side ot the church parking lot. Steve Robbins 01/19/2017 2:48 PM
PW-Misc
Informational
03/09/2017
There is nothing going on in the parking lot, they still have to put in rock and geo-grid on the west side. They are not working on the public street behind the church, we still need a proofroll for the curbs so they can go in.Steve Robbins 01/12/2017 1:18 PM
PW-Misc
Informational
03/09/2017
Today I talked with Mark and let him know that the 2 entrances on the public streets need to be asphalt with geo-grid and not concrete like the plans show. I talked to gene and kent and they agreed that it should be asphalt, only the entrance to the church should be concrete. Also let them know to use a curb machine for the curbs that are on the public street. They have a run of about 400 ft.Steve Robbins 01/11/2017 3:15 PM
PW-Misc
Informational
03/09/2017
No work on the parking lot or the street is going on today.Steve Robbins 01/09/2017 11:29 AM
PW-Misc
Informational
03/09/2017
No work was done on the subgrade today, they are waiting for warmer weather. I got a complaint on ashurst not being blocked off, the contractor put up a dirt berm in front of the road , a citizen said they were still getting in. We are now going to put up steel fence stakes in front of the street in hopes that will keep the 4-wheelers off the property and not tracking mud on the streets.Steve Robbins 01/04/2017 3:47 PM
PW-Misc
Informational
03/09/2017
Today they are still working on grading for the rock and geo-grid.Steve Robbins 12/30/2016 11:13 AM
PW-Misc
Informational
03/09/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/09/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/09/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/09/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/09/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/09/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/09/2017
They passed their last dirt proofroll , so next week they will install rock and geo-grid on the last section next week.Steve Robbins 02/17/2017 3:36 PM
PW-Misc
Informational
03/09/2017
Today they are installing the geo-grid and rock on the last section of parking lot that had been faliling.Steve Robbins 02/21/2017 1:55 PM
PW-Misc
Informational
03/09/2017
All the curbs for the streets have been put in with a curb machine and the used the granite mix for the curbs.Steve Robbins 02/23/2017 4:32 PM
PW-Misc
Informational
03/09/2017
I talked with the contractor about the entrance and milling off 2" and installing ashpalt, Louis, the contractor thinks it is still good and offered to warranty the work for a longer period of time. I talked with Gene Williams and Mike Andersen and they both said it is not acceptable and they will have to tear it out or do the above stated.Steve Robbins 03/02/2017 4:10 PM
PW-Misc
Informational
03/09/2017
I told the contractor with summit concrete they are going to have to mill the entrance 2" and replace with asphalt.Steve Robbins 03/03/2017 2:49 PM
PW-Misc
Informational
03/09/2017
The entrance that was poured off chipman was determined to be incomplete, it rained last evening and someone wrote there name in the concrete, after talking to Kent we determined they need to mill the top 2 " and put ashphalt on it when they do the surface for the rest of the street.Steve Robbins 03/01/2017 4:26 PM
PW-Misc
Informational
03/09/2017
Today they poured the entrance for the road off chipman rd. The plans showed to put in a concrete entrance and we as a city want ashphalt and geo-grid and type 5, I talked with Gene Williams and he said it would be okay to put in concrete for the entrance because there is a 20" gas line in the way which will not allow us to get the proper amount of ashalt in. They are putting in 6" of rock and 8" of concrete , granite mix.Steve Robbins 02/28/2017 4:13 PM
PW-Misc
Informational
03/09/2017
No work for this site was done in the parking lot or steet today.Steve Robbins 01/26/2017 2:39 PM
PW-Misc
Informational
03/09/2017
No work was done in the parking lot or on the road today.Steve Robbins 01/24/2017 2:25 PM
PW-Misc
Informational
03/09/2017
Today they were working on rock and geo-grid for the west side of the parking lot.Steve Robbins 12/27/2016 3:37 PM
PW-Misc
Informational
03/09/2017
They are still working on the rock and geo-grid for the parking lot. Steve Robbins 12/29/2016 2:03 PM
PW-Misc
Informational
03/09/2017
Yesterday and today not work was done due to the cold and snow.Steve Robbins 01/06/2017 1:52 PM
PW-Misc
Informational
03/09/2017
No work in the parking lot was done, and there is no erosion control problems with mudd in the streets.Steve Robbins 01/20/2017 3:20 PM
PW-Misc
Informational
03/09/2017
No work done today in the parking lot or the street. They are waiting to get a curb machine for the public street and waiting for the parking lot to dry out so they can finish the parking lot with rock and geo-grid.Steve Robbins 01/25/2017 3:22 PM
PW-Misc
Informational
03/09/2017
Today they installed rock and geo-grid on the street going to chipman rd. They installed a few inches of ab-3 and I told them it was okay for now, they are just getting started. They are going to have at least 6-7 inches of ab-5 before they do a proofroll. Steve Robbins 02/07/2017 3:54 PM
PW-Misc
Informational
03/09/2017
Today they were digging up the parking lot in front of the drop off. It still did not pass a dirt proofroll .Steve Robbins 02/16/2017 3:16 PM
PW-Misc
Informational
03/09/2017
They are still trying to pass a proofroll on one section in front of the church before they can put down the AB-3 and geo-grid.Steve Robbins 02/15/2017 3:16 PM
PW-Misc
Informational
03/09/2017
They were not doing any work in the parking lot or the public street today.Steve Robbins 02/14/2017 3:58 PM
PW-Misc
Informational
03/09/2017
They were going to do a dirt proofroll on a section of the parking lot that didnt pass yet. Steve Robbins 02/13/2017 3:19 PM
PW-Misc
Informational
03/09/2017
No work was done in the parking lot or the street. We will do a proofroll for the curbs for the public street next week.Steve Robbins 02/09/2017 11:20 AM
PW-Misc
Informational
03/09/2017
I talked with Gene Williams about the public street that is coming off chipman rd. There is a 20" gas line that goes under the road and after they located the line it was determined that they only had 8-10 " to get the rock, geo-grid and asphalt in. Gene said it would be ok to get rock and 8" of concrete over the gas line if it was ok with the gas company. They are fine with it and thats what they are going to do. None of this work was going on today.Steve Robbins 02/08/2017 3:01 PM
PW-Misc
Informational
03/09/2017
Today they passed the proofroll for the parking lot and the public street. They also put rock and geo-grid in the parking lot.Steve Robbins 02/06/2017 2:51 PM
PW-Misc
Informational
03/09/2017
The did another proofroll on the dirt of the east side of the parking lot and the public street that is going in on chipman, the special inspector did not pass it, they will do it again on monday.Steve Robbins 02/03/2017 3:22 PM
PW-Misc
Informational
03/09/2017
No work in the parking lot or street today.Steve Robbins 02/02/2017 3:50 PM
PW-Misc
Informational
03/09/2017
They did a proofroll on the parking lot that is not rocked and one on the public future street. Part of it failed , they are doing another one tomorrow.Steve Robbins 02/01/2017 3:42 PM
PW-Misc
Informational
03/09/2017
I talked with the super today, they are planning on a proofroll for the rest of the parking lot, if that passes they will beging putting in rock and geo-grid for the remaining parking lot. Then I can get a proofroll for that. They also replaced fence around the storm box that backs up to the houses on ashurst. He said it looks like someone took them down, but Huber replaced it for the safety of the people living there.Steve Robbins 01/31/2017 9:43 AM
PW-Misc
Informational
03/09/2017
No work on the parking lot or public street going on today.Steve Robbins 01/30/2017 12:48 PM
PW-Misc
Informational
03/09/2017
Today they did not do any work in the road or parking lot.Steve Robbins 01/27/2017 2:39 PM
PW-Misc
Informational
03/09/2017
Summit Concrete is milling 2" off the entrance today and getting ready for ashpalt.Steve Robbins 03/06/2017 9:30 AM
PW-Misc
Informational
03/09/2017
Today they finished milling the rest of the entrance up next to the curb. They still have to clean the millings up.Steve Robbins 03/08/2017 3:03 PM
Water Line - Fire Hydrant Passed 10/14/2016 03/28/2017
PW-Misc
Informational
10/13/2016
Brice Lawson 10/12/2016 4:34 PM Central Plumbing installed the fire hydrant assembly at STA.9+09.25.
Corrective Action Required
03/28/2017
PW-Misc
Informational
03/28/2017
The water lines and all fire hydrants have all been installed.Steve Robbins 03/28/2017 3:38 PM
Street - Surface Course Partial 3/29/2017 03/29/2017
PW-Misc
Informational
03/29/2017
It is raining all day today and expecting rain for the rest of the week, so we probably won't get any asphalt this week.Steve Robbins 03/29/2017 1:56 PM
Street - Surface Course Partial 4/3/2017 04/03/2017
PW-Misc
Informational
03/29/2017
It is raining all day today and expecting rain for the rest of the week, so we probably won't get any asphalt this week.Steve Robbins 03/29/2017 1:56 PM
Corrective Action Required
04/03/2017
PW-Misc
Informational
04/03/2017
They are not doing any surface today because of the rain. It will probably be slow for the next few days.Steve Robbins 04/03/2017 3:06 PM
Street - Surface Course Partial 4/7/2017 04/07/2017
PW-Misc
Corrective Action Required
04/03/2017
PW-Misc
Informational
04/07/2017
No work was done on surface due to the rain this week.Steve Robbins 04/07/2017 2:39 PM
Street - Surface Course Partial 4/10/2017 04/11/2017
PW-Misc
Corrective Action Required
04/07/2017
PW-Misc
Informational
04/11/2017
Yesterday on 4/10 they installed surface in the parking lot on the west side. Today they are working on the east side of the parking lot and working there way around the whole lot. The public road on ashurst and the one off chipman has not been suraced yet. I told them to sawcut the road on chipman about a foot beyond the curb into the street because it was chipping away. They agreed.Steve Robbins 04/11/2017 11:26 AM
PW-Misc
Informational
04/07/2017
No work was done on surface due to the rain this week.Steve Robbins 04/07/2017 2:39 PM
Street - Surface Course Partial 4/12/2017 04/12/2017
PW-Misc
Informational
04/11/2017
Yesterday on 4/10 they installed surface in the parking lot on the west side. Today they are working on the east side of the parking lot and working there way around the whole lot. The public road on ashurst and the one off chipman has not been suraced yet. I told them to sawcut the road on chipman about a foot beyond the curb into the street because it was chipping away. They agreed.Steve Robbins 04/11/2017 11:26 AM
PW-Misc
Informational
04/12/2017
All the parking lot and the future public street off chipman has surface installed. They made a sawcut on chipman and tied the asphalt in very nice.Steve Robbins 04/12/2017 3:56 PM They still have to install surface on ashurst.
PW-Misc
Corrective Action Required
04/11/2017
PW-Misc
Informational
04/11/2017
No work was done on surface due to the rain this week.Steve Robbins 04/07/2017 2:39 PM
ESC - (Vegetation/Ground Cover) Partial 4/14/2017 04/14/2017
PW-Misc
Informational
04/14/2017
All the sod has been installed and seed has been planted and is coming up, the majority of the seed is established, It is not 70 percent but it is getting close. All the plants and trees have been planted.Steve Robbins 04/14/2017 9:44 AM
Storm - Inlets Clean Passed 4/14/2017 04/14/2017
PW-Misc
Informational
04/14/2017
The storm inlets are clean and flowing good.Steve Robbins 04/14/2017 1:20 PM
Storm - Swales Passed 4/14/2017 04/14/2017
Erosion Control Inspection Partial 4/14/2017 04/14/2017
PW-Misc
Informational
04/14/2017
The erosion control is still in place because the 70 percent vegetation is not established yet.Steve Robbins 04/14/2017 1:27 PM
Driveway Inspection Passed 4/14/2017 04/14/2017
PW-Misc
Informational
01/19/2017
The driveway entrance on the south end of the church off ashurst has been formed , rocked , copacted and concrete installed.There will be one more driveway entrance on the north side.Steve Robbins 01/19/2017 9:36 AM
PW-Misc
Informational
04/14/2017
Both driveway approaches have been installed and has passed inspections.Steve Robbins 04/14/2017 1:30 PM
Street - Surface Course Passed 4/17/2017 04/17/2017
PW-Misc
Informational
04/12/2017
All the parking lot and the future public street off chipman has surface installed. They made a sawcut on chipman and tied the asphalt in very nice.Steve Robbins 04/12/2017 3:56 PM They still have to install surface on ashurst.
PW-Misc
Informational
04/12/2017
Yesterday on 4/10 they installed surface in the parking lot on the west side. Today they are working on the east side of the parking lot and working there way around the whole lot. The public road on ashurst and the one off chipman has not been suraced yet. I told them to sawcut the road on chipman about a foot beyond the curb into the street because it was chipping away. They agreed.Steve Robbins 04/11/2017 11:26 AM
PW-Misc
Corrective Action Required
04/12/2017
PW-Misc
Informational
04/12/2017
No work was done on surface due to the rain this week.Steve Robbins 04/07/2017 2:39 PM
PW-Misc
Informational
04/17/2017
Today they installed the surface asphlat for ashurst rd. which is the entrance off view high dr. This now completes all the parking lot and the 2 roads that will be public in the future. The only thing left is the work to be done in the row on the kansasity side . That is going to be concrete that connects to asphalt on ashurst.Steve Robbins 04/17/2017 3:30 PM
Erosion Control Inspection Partial 4/26/2017 04/26/2017
PW-Misc
Informational
04/14/2017
The erosion control is still in place because the 70 percent vegetation is not established yet.Steve Robbins 04/14/2017 1:27 PM
PW-Misc
Informational
04/26/2017
The erosion control is stll good. They will put some more seed down to try and fill in the bare spots. The erosion control is doing good.Steve Robbins 04/26/2017 3:40 PM
ESC - (Vegetation/Ground Cover) Partial 4/27/2017 04/26/2017
PW-Misc
Informational
04/14/2017
All the sod has been installed and seed has been planted and is coming up, the majority of the seed is established, It is not 70 percent but it is getting close. All the plants and trees have been planted.Steve Robbins 04/14/2017 9:44 AM
PW-Misc
Informational
04/26/2017
They are going to put more seed down, they do not have 70 percent vegetation yet.Steve Robbins 04/26/2017 3:43 PM
ESC - (Vegetation/Ground Cover) Partial 4/27/2017 04/27/2017
PW-Misc
Informational
04/26/2017
They are going to put more seed down, they do not have 70 percent vegetation yet.Steve Robbins 04/26/2017 3:43 PM
PW-Misc
Informational
04/26/2017
All the sod has been installed and seed has been planted and is coming up, the majority of the seed is established, It is not 70 percent but it is getting close. All the plants and trees have been planted.Steve Robbins 04/14/2017 9:44 AM
PW-Misc
Informational
04/27/2017
I walked the property with Mark today and told him he can take the silt fence down that is on chipman rd, they have over 70 percent vegetation in that area and we talked about some other areas that will need more seed that will be on a punch list at substantial.Steve Robbins 04/27/2017 3:48 PM
Grading/Excavation/Fill Inspection Partial 5/2/2017 05/01/2017
PW-Misc
Informational
08/31/2016
Due to the rain nothing has been going on for the site work. As soon as the weather breaks they will be resuming work on the storm sewer Steve Robbins 08/31/2016 3:18 PM
PW-Misc
Informational
05/01/2017
Kent Monter recieved a complaint from Marlo Knapp about her private drive that you can enter from chipman rd just east of the Summit Church entrance. I went to her house and talked with her and she showed me what her concern is and I took pictures. I showed Kent the pictures of some standing water which looks to be the result of the dirt eroding away. We do not think it is the result of anything summit church has done but I am going to ask them if they have some extra dirt if they can put some in spots where the water is standing.Steve Robbins 05/01/2017 3:05 PM
Install Street and Stop Signs Partial 5/3/2017 05/01/2017
Informational
05/01/2017
The end of road marker signs have been installed on ashurst and all the other signs have been installed except for the stop sign on viewhigh and ashurst. This is in the K.C. ROW as is the entrance that they want to be concrete, Today they formed the entrance for the curb. I talked to Mark from Huber and the contractors and let them know that K.C. had to inspect that ROW. Steve Robbins 05/01/2017 3:10 PM
Grading/Excavation/Fill Inspection Partial 5/8/2017 05/08/2017
PW-Misc
Informational
05/01/2017
Kent Monter recieved a complaint from Marlo Knapp about her private drive that you can enter from chipman rd just east of the Summit Church entrance. I went to her house and talked with her and she showed me what her concern is and I took pictures. I showed Kent the pictures of some standing water which looks to be the result of the dirt eroding away. We do not think it is the result of anything summit church has done but I am going to ask them if they have some extra dirt if they can put some in spots where the water is standing.Steve Robbins 05/01/2017 3:05 PM
PW-Misc
Informational
05/01/2017
Due to the rain nothing has been going on for the site work. As soon as the weather breaks they will be resuming work on the storm sewer Steve Robbins 08/31/2016 3:18 PM
PW-Misc
Informational
05/08/2017
I talked with Mark from Huber and he is going to put some dirt on the side of the driveway of marlo Knapp with has eroded away. Summit Church had nothing to do with this but he is gonna put some dirt there if he has enough left over. They are also doing some grading around the site and trying to get things picked up and getting ready for Substantial .Steve Robbins 05/08/2017 3:18 PM
Grading/Excavation/Fill Inspection Passed 5/10/2017 05/09/2017
PW-Misc
Informational
05/08/2017
Kent Monter recieved a complaint from Marlo Knapp about her private drive that you can enter from chipman rd just east of the Summit Church entrance. I went to her house and talked with her and she showed me what her concern is and I took pictures. I showed Kent the pictures of some standing water which looks to be the result of the dirt eroding away. We do not think it is the result of anything summit church has done but I am going to ask them if they have some extra dirt if they can put some in spots where the water is standing.Steve Robbins 05/01/2017 3:05 PM
PW-Misc
Informational
05/08/2017
Due to the rain nothing has been going on for the site work. As soon as the weather breaks they will be resuming work on the storm sewer Steve Robbins 08/31/2016 3:18 PM
PW-Misc
Informational
05/08/2017
I talked with Mark from Huber and he is going to put some dirt on the side of the driveway of marlo Knapp with has eroded away. Summit Church had nothing to do with this but he is gonna put some dirt there if he has enough left over. They are also doing some grading around the site and trying to get things picked up and getting ready for Substantial .Steve Robbins 05/08/2017 3:18 PM
Erosion Control Inspection Passed 5/31/2017 05/10/2017
PW-Misc
Informational
04/26/2017
The erosion control is still in place because the 70 percent vegetation is not established yet.Steve Robbins 04/14/2017 1:27 PM
PW-Misc
Informational
04/26/2017
The erosion control is stll good. They will put some more seed down to try and fill in the bare spots. The erosion control is doing good.Steve Robbins 04/26/2017 3:40 PM
Install Street and Stop Signs Passed 5/19/2017 05/19/2017
Informational
05/19/2017
The stop sign has been installed on ashurst going to view high. All the signs have been installed. Steve Robbins 05/19/2017 11:38 AM
ESC - (Vegetation/Ground Cover) Passed 10/11/2017 at 7:15 AM 10/11/2017
PW-Misc
Informational
04/27/2017
They are going to put more seed down, they do not have 70 percent vegetation yet.Steve Robbins 04/26/2017 3:43 PM
PW-Misc
Informational
04/27/2017
All the sod has been installed and seed has been planted and is coming up, the majority of the seed is established, It is not 70 percent but it is getting close. All the plants and trees have been planted.Steve Robbins 04/14/2017 9:44 AM
PW-Misc
Informational
04/27/2017
I walked the property with Mark today and told him he can take the silt fence down that is on chipman rd, they have over 70 percent vegetation in that area and we talked about some other areas that will need more seed that will be on a punch list at substantial.Steve Robbins 04/27/2017 3:48 PM
Informational
10/11/2017
The vegetation has been established at 70% or greater and the erosion control silt fence has already been removed.Steve Robbins 10/11/2017 7:15 AM
Documents & Images
Date Uploaded File Type Document Name
05/27/2016 Receipt Receipt for transaction: 2016-003079
06/08/2016 Letter PW-Permit
07/20/2016 Letter PW-Daily Inspection Summary
08/30/2016 Letter PW-Daily Inspection Summary
08/31/2016 Letter PW-Daily Inspection Summary
09/06/2016 Letter PW-Daily Inspection Summary
09/13/2016 Letter PW-Daily Inspection Summary
09/15/2016 Letter PW-Daily Inspection Summary
09/20/2016 Letter PW-Daily Inspection Summary
09/21/2016 Letter PW-Daily Inspection Summary
09/22/2016 Letter PW-Daily Inspection Summary
09/28/2016 Letter PW-Daily Inspection Summary
09/28/2016 Letter PW-Daily Inspection Summary
09/29/2016 Letter PW-Daily Inspection Summary
10/06/2016 Letter PW-Daily Inspection Summary
10/17/2016 Letter Inspection Summary
10/19/2016 Letter PW-Daily Inspection Summary
10/25/2016 Letter Inspection Summary
10/26/2016 Letter PW-Daily Inspection Summary
11/09/2016 Letter PW-Daily Inspection Summary
11/11/2016 Letter PW-Daily Inspection Summary
11/17/2016 Letter PW-Daily Inspection Summary
12/02/2016 Letter Inspection Summary
12/14/2016 Letter PW-Daily Inspection Summary
12/14/2016 Letter PW-Daily Inspection Summary
12/15/2016 Letter PW-Daily Inspection Summary
12/21/2016 Letter PW-Daily Inspection Summary
12/27/2016 Letter PW-Daily Inspection Summary
12/28/2016 Letter PW-Daily Inspection Summary
12/29/2016 Letter PW-Daily Inspection Summary
12/30/2016 Letter PW-Daily Inspection Summary
01/04/2017 Letter PW-Daily Inspection Summary
01/06/2017 Letter PW-Daily Inspection Summary
01/06/2017 Letter PW-Daily Inspection Summary
01/09/2017 Letter PW-Daily Inspection Summary
01/11/2017 Letter PW-Daily Inspection Summary
01/12/2017 Letter PW-Daily Inspection Summary
01/19/2017 Letter PW-Daily Inspection Summary
01/19/2017 Letter PW-Daily Inspection Summary
01/20/2017 Letter PW-Daily Inspection Summary
01/23/2017 Letter PW-Daily Inspection Summary
01/24/2017 Letter PW-Daily Inspection Summary
01/25/2017 Letter PW-Daily Inspection Summary
01/26/2017 Letter PW-Daily Inspection Summary
01/27/2017 Letter PW-Daily Inspection Summary
01/30/2017 Letter PW-Daily Inspection Summary
01/31/2017 Letter PW-Daily Inspection Summary
02/01/2017 Letter PW-Daily Inspection Summary
02/02/2017 Letter PW-Daily Inspection Summary
02/03/2017 Letter PW-Daily Inspection Summary
02/06/2017 Letter PW-Daily Inspection Summary
02/07/2017 Letter PW-Daily Inspection Summary
02/08/2017 Letter PW-Daily Inspection Summary
02/09/2017 Letter PW-Daily Inspection Summary
02/09/2017 Letter PW-Daily Inspection Summary
02/09/2017 Letter PW-Daily Inspection Summary
02/13/2017 Letter PW-Daily Inspection Summary
02/14/2017 Letter PW-Daily Inspection Summary
02/15/2017 Letter PW-Daily Inspection Summary
02/16/2017 Letter PW-Daily Inspection Summary
02/17/2017 Letter PW-Daily Inspection Summary
02/21/2017 Letter PW-Daily Inspection Summary
02/22/2017 Letter PW-Daily Inspection Summary
02/23/2017 Letter PW-Daily Inspection Summary
02/24/2017 Letter PW-Daily Inspection Summary
02/28/2017 Letter PW-Daily Inspection Summary
03/01/2017 Letter PW-Daily Inspection Summary
03/02/2017 Letter PW-Daily Inspection Summary
03/03/2017 Letter PW-Daily Inspection Summary
03/06/2017 Letter PW-Daily Inspection Summary
03/07/2017 Letter PW-Daily Inspection Summary
03/08/2017 Letter PW-Daily Inspection Summary
03/09/2017 Letter PW-Daily Inspection Summary
03/09/2017 Letter PW-Daily Inspection Summary
03/10/2017 Letter PW-Daily Inspection Summary
03/13/2017 Letter PW-Daily Inspection Summary
03/17/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/20/2017 Letter PW-Daily Inspection Summary
03/21/2017 Letter PW-Daily Inspection Summary
03/27/2017 Letter PW-Daily Inspection Summary
03/27/2017 Letter PW-Daily Inspection Summary
03/28/2017 Letter PW-Daily Inspection Summary
03/29/2017 Letter PW-Daily Inspection Summary
04/03/2017 Letter PW-Daily Inspection Summary
04/07/2017 Letter PW-Daily Inspection Summary
04/11/2017 Letter PW-Daily Inspection Summary
04/12/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/14/2017 Letter PW-Daily Inspection Summary
04/17/2017 Letter PW-Daily Inspection Summary
04/26/2017 Letter PW-Daily Inspection Summary
04/26/2017 Letter PW-Daily Inspection Summary
04/27/2017 Letter PW-Daily Inspection Summary
05/01/2017 Letter PW-Daily Inspection Summary
05/08/2017 Letter PW-Daily Inspection Summary
05/09/2017 Letter PW-Certificate of Substantial Completion Single Lot
05/09/2017 Letter PW-Punch List
05/10/2017 Summit Church punch and sub
05/19/2017 Letter PW-Daily Inspection Summary
10/11/2017 Letter DE-Daily Inspection Summary
10/11/2017 Letter DE-Certificate of Final Acceptance (Commercial)
10/11/2017 DOC101117-10112017090420
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home