| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Licensed Contractors
|
Approved
|
04/06/2026
|
04/02/2026
|
|
|
Joe Frogge
|
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor. (Dyllan not currently licensed with us)
|
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (P&L Mechanical is not licensed to perform electrical or plumbing.)
|
|
|
|
|
Fire Plan Review
|
Rejected
|
03/25/2026
|
03/26/2026
|
|
|
Craig Hill
|
|
|
Misc
Corrective Action Required
Fire code not provided on plans.
Action Required: Please provide the code reference of the IFC and NFPA edition used.
|
|
|
Miscellaneous Correction
Corrective Action Required
2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply.
1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Aisles.
2. Corridors.
3. Exit access stairways and ramps.
1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Interior exit access stairways and ramps.
2. Interior and exterior exit stairways and ramps.
3. Exit passageways.
4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1.
5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge.
1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas:
1. Electrical equipment rooms.
2. Fire command centers.
3. Fire pump rooms.
4. Generator rooms.
5. Public restrooms with an area greater than 300 square feet.
Action required: Provide emergency lighting at exterior landing of marked exits.
|
|
|
|
|
Building Plan Review
|
Rejected
|
03/25/2026
|
03/24/2026
|
|
|
Joe Frogge
|
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update Code Analysis on sheet A0 to show correct building construction type which is 2B. Also amend the occupancy type to M.
|
|
|
IBC 1209.2 Finish materials
Corrective Action Required
2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4.
2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches.
2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.)
Action required: Specify compliant wall finish materials at toilet and mop sink. If paint is used it must be epoxy based.
|
|
|
IBC 1606.2 Design dead load - structural
Corrective Action Required
2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official.
Action required: Provide engineer’s report to verify that existing ceiling structure will support additional load imposed by furnaces.
|
|
|
IBC 1008.3 Emergency power for illumination - at exit discharge
Corrective Action Required
2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply.
1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Aisles.
2. Corridors.
3. Exit access stairways and ramps.
1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Interior exit access stairways and ramps.
2. Interior and exterior exit stairways and ramps.
3. Exit passageways.
4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1.
5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge.
1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas:
1. Electrical equipment rooms.
2. Fire command centers.
3. Fire pump rooms.
4. Generator rooms.
5. Public restrooms with an area greater than 300 square feet.
Action required: Provide emergency lighting at exterior landing of marked exits.
|
|
|
|
|
Licensed Contractors
|
Rejected
|
03/25/2026
|
03/24/2026
|
|
|
Joe Frogge
|
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor. (Dyllan not currently licensed with us)
|
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (P&L Mechanical is not licensed to perform electrical or plumbing.)
|
|
|
|
|
Fire Plan Review
|
Pending
|
04/06/2026
|
|
|
|
Craig Hill
|
|
|
Misc
Corrective Action Required
Fire code not provided on plans.
Action Required: Please provide the code reference of the IFC and NFPA edition used.
|
|
|
Miscellaneous Correction
Corrective Action Required
2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply.
1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Aisles.
2. Corridors.
3. Exit access stairways and ramps.
1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Interior exit access stairways and ramps.
2. Interior and exterior exit stairways and ramps.
3. Exit passageways.
4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1.
5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge.
1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas:
1. Electrical equipment rooms.
2. Fire command centers.
3. Fire pump rooms.
4. Generator rooms.
5. Public restrooms with an area greater than 300 square feet.
Action required: Provide emergency lighting at exterior landing of marked exits.
|
|
|
|
|
Building Plan Review
|
Pending
|
04/06/2026
|
|
|
|
Joe Frogge
|
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update Code Analysis on sheet A0 to show correct building construction type which is 2B. Also amend the occupancy type to M.
|
|
|
IBC 1209.2 Finish materials
Corrective Action Required
2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4.
2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches.
2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.)
Action required: Specify compliant wall finish materials at toilet and mop sink. If paint is used it must be epoxy based.
|
|
|
IBC 1606.2 Design dead load - structural
Corrective Action Required
2018 IBC 1606.2 Design dead load. For purposes of design, the actual weights of materials of construction and fixed service equipment shall be used. In the absence of definite information, values used shall be subject to the approval of the building official.
Action required: Provide engineer’s report to verify that existing ceiling structure will support additional load imposed by furnaces.
|
|
|
IBC 1008.3 Emergency power for illumination - at exit discharge
Corrective Action Required
2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply.
1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Aisles.
2. Corridors.
3. Exit access stairways and ramps.
1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Interior exit access stairways and ramps.
2. Interior and exterior exit stairways and ramps.
3. Exit passageways.
4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1.
5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge.
1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas:
1. Electrical equipment rooms.
2. Fire command centers.
3. Fire pump rooms.
4. Generator rooms.
5. Public restrooms with an area greater than 300 square feet.
Action required: Provide emergency lighting at exterior landing of marked exits.
|
|
|
|