Permit Application Status

PRCOM20251443


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20251443
Building Permit - Commercial
Issued
NEW OTHER (COMMERCIAL)
REUNION AT BLACKWELL - NEW DETACHED GARAGE
04/10/2025
06/30/2025
08/06/2025
Locations
Contacts
APEX HEATING & AIR CONDITIONING INC, Address:1202 NW EAGLE RIDGE BLVD, Phone:(816) 228-2739  
RED DOG ELECTRIC SERVICES, Address:PO BOX 1, Phone:(913) 208-4816  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
COLLINS WEBB ARCHITECTURE LLC, Address:307 SW MARKET ST, Unit A, Phone:(816) 249-2270  
Avital Homes, LLC, Address:7500 W 151st Street, #23100, Phone:(816) 914-7128  
Doug Jenson - Avital Homes, Phone:(816) 266-0685  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 09/24/2025 09/23/2025
Joe Frogge
Final Development Plan Review Approved 04/24/2025 04/10/2025
Joe Frogge
Fire Plan Review Approved 04/24/2025 04/10/2025
Joe Frogge
Building Plan Review Approved 04/24/2025 04/10/2025
Joe Frogge
Licensed Contractors Approved 04/10/2025 04/10/2025
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Other $181.98 $181.98 Paid 06/30/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Final Inspection - Commercial Pending
Piers/Caissons Inspection - Commercial Pending
Foundation Inspection - Commercial Pending
Footing Inspection - Commercial Pending
Misc
Informational
10/28/2025
Areas approved -Front and rear footings moved and repoured -Stem walls
Underslab Plumbing Inspection - Commercial Pending
Misc
Corrective Action Required
11/19/2025
Plumbing as installed does not match approved plans
Footing Inspection - Commercial Passed 7/18/2025 7/18/2025 07/18/2025
Footing Inspection - Commercial Not Ready 7/25/2025 7/25/2025 07/25/2025
Misc
Corrective Action Required
07/25/2025
-No address posted -no city stamped plans on site
Footing Inspection - Commercial Failed 7/29/2025 7/29/2025 07/29/2025
Misc
Corrective Action Required
07/25/2025
Stem wall poured without inspection, provide 3rd party inspection report
Sewer Service Inspection Partial 7/29/2025 7/29/2025 07/29/2025
Misc
Corrective Action Required
07/29/2025
7-29-25 Dustin A, sewer for clubhouse has passed, there is another sewer attached for a proposed maintenance building . There is no plans for that so plans will need to be submitted before a inspection can be performed.
Footing Inspection - Commercial Partial 10/16/2025 10/16/2025 10/16/2025
Misc
Informational
10/16/2025
Front and rear footings moved and repoured
Footing Inspection - Commercial Partial 10/28/2025 10/28/2025 10/28/2025
Misc
Informational
10/16/2025
Areas approved -Front and rear footings moved and repoured -Stem walls
Sewer Service Inspection Passed 10/31/2025 10/31/2025 10/31/2025
Misc
Resolved
10/31/2025
7-29-25 Dustin A, sewer for clubhouse has passed, there is another sewer attached for a proposed maintenance building . There is no plans for that so plans will need to be submitted before a inspection can be performed.
Underslab Plumbing Inspection - Commercial Failed 11/19/2025 11/19/2025 11/19/2025
Misc
Corrective Action Required
11/19/2025
Plumbing as installed does not match approved plans OK to pour with approved engineer letter
All Rough Inspection - Commercial Failed 1/15/2026 1/15/2026 01/15/2026
Misc
Corrective Action Required
01/15/2026
No plans on site No address posted
All Rough Inspection - Commercial Failed 1/20/2026 1/20/2026 01/20/2026
Misc
Corrective Action Required
01/15/2026
Nail to plans 4” OC edge 12” field
Gas Service Inspection - Commercial Passed 1/28/2026 1/28/2026 01/28/2026
All Rough Inspection - Commercial Passed 1/23/2026 1/23/2026 01/28/2026
Misc
Resolved
01/23/2026
Nail to plans 4” OC edge 12” field
Gas Service Inspection - Commercial Failed 2/12/2026 2/12/2026 02/12/2026
Miscellaneous Correction
Corrective Action Required
02/12/2026
-find the leak and pressure test again
Gas Service Inspection - Commercial Passed 2/19/2026 2/19/2026 02/19/2026
Miscellaneous Correction
Resolved
02/19/2026
-find the leak and pressure test again
All Rough Inspection - Commercial Failed 3/2/2026 3/2/2026 03/02/2026
Misc
Corrective Action Required
03/02/2026
Provide complete set of plans (truss plans) on site for inspection
All Rough Inspection - Commercial Failed 3/4/2026 3/4/2026 03/04/2026
Misc
Resolved
03/04/2026
Provide complete set of plans (truss plans) on site for inspection
Misc
Corrective Action Required
03/04/2026
-complete electrical for panel -anchors shall not be spaced more than 32” to plans -provide attic access
All Rough Inspection - Commercial Failed 3/6/2026 3/6/2026 03/06/2026
Misc
Corrective Action Required
03/04/2026
-secure electrical within 12” of panel -anchors shall not be spaced more than 32” to plans( missing E wall) -protect wires within 6’ of attic access
All Rough Inspection - Commercial Passed 3/13/2026 3/13/2026 03/13/2026
Misc
Resolved
03/13/2026
-secure electrical within 12” of panel -anchors shall not be spaced more than 32” to plans( missing E wall) -protect wires within 6’ of attic access
Documents & Images
Date Uploaded File Type Document Name
06/30/2025 Receipt Receipt for transaction:2025-005065
07/18/2025 Letter INSPECTION SUMMARY
03/31/2025 Approved Plans Approved plans V1
03/06/2025 Approved Plans Approved plans V2
07/25/2025 Letter DS Building Permit
07/25/2025 Letter INSPECTION SUMMARY
07/29/2025 Letter INSPECTION SUMMARY
07/29/2025 Letter INSPECTION SUMMARY
07/29/2025 Letter INSPECTION SUMMARY
09/17/2025 Plans REUNION AT BLACKWELL - NEW DETACHED GARAGE _ REV 1
09/22/2025 Approved Plans Approved garage revisions
10/16/2025 Letter INSPECTION SUMMARY
10/28/2025 Letter INSPECTION SUMMARY
10/31/2025 Letter INSPECTION SUMMARY
11/17/2025 Approved Plans Truss repair doc
11/19/2025 Letter INSPECTION SUMMARY
11/21/2025 Approved Plans Approved trusses - Maintenance
11/25/2025 Approved Plans Approved P101K
01/15/2026 Letter INSPECTION SUMMARY
01/20/2026 Letter INSPECTION SUMMARY
01/28/2026 Letter INSPECTION SUMMARY
02/09/2026 Approved Plans REUNION GRADING PLA
02/12/2026 Letter INSPECTION SUMMARY
02/19/2026 Letter INSPECTION SUMMARY
03/02/2026 Letter INSPECTION SUMMARY
03/02/2026 Letter INSPECTION SUMMARY
03/02/2026 Letter INSPECTION SUMMARY
03/02/2026 Letter INSPECTION SUMMARY
03/04/2026 Letter INSPECTION SUMMARY
03/06/2026 Letter INSPECTION SUMMARY
03/13/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.