Permit Application Status

PRCOM20251410


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20251410
Building Permit - Commercial
Issued
NEW MULTI-FAMILY
THE REUNION AT BLACKWELL - BUILDING 22, TYPE C -PLEX PLAN REVIEW COMPLETED UNDER PRCOM20250089
04/09/2025
06/30/2025
Locations
Contacts
Avital Homes, LLC, Address:7500 W 151st Street, #23100, Phone:(816) 914-7128  
RED DOG ELECTRIC SERVICES, Address:PO BOX 1, Phone:(913) 208-4816  
APEX HEATING & AIR CONDITIONING INC, Address:1202 NW EAGLE RIDGE BLVD, Phone:(816) 228-2739  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
COLLINS WEBB ARCHITECTURE LLC, Address:307 SW MARKET ST, Unit A, Phone:(816) 249-2270  
Doug Jenson - Avital Homes, Phone:(816) 266-0685  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 09/15/2025 09/15/2025
Joe Frogge
Final Development Plan Review Approved 04/14/2025 03/31/2025
Mike Weisenborn
Building Plan Review Approved with Conditions 04/14/2025 03/31/2025
Mike Weisenborn
Miscellaneous Correction
Resolved
06/20/2025

Foundation and underlsab plumbing only released at this time. Substantial completion on the sanitary and water before private connections can be made. Full access and live hydrants required prior to release of vertical construction.
Licensed Contractors Approved 04/14/2025 03/31/2025
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Water Tap Fee $10,595.00 $10,595.00 Paid 06/30/2025
Water Meter Fee $1,066.76 $1,066.76 Paid 06/30/2025
Sanitary Sewer Development Fee $6,101.00 $6,101.00 Paid 06/30/2025
Valuation Fee for New 3 or 4 Family $4,451.71 $4,451.71 Paid 06/30/2025
Residential Excise Tax Fee $2,480.64 $2,480.64 Paid 06/30/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$225.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Piers/Caissons Inspection - Commercial Pending
Above Ceiling Inspection Pending
Erosion Control Inspection Pending
Misc
Corrective Action Required
10/10/2025
No further inspections until erosion control is in compliance
Misc
Corrective Action Required
10/10/2025
Erosion control not in compliance -dirt and rock in street -silt fence downed around lot -lot access shall be maintained to allow parking and unloading that prevents tracking of mud and materials onto street
Footing Inspection - Commercial Partial 9/12/2025 9/12/2025 09/12/2025
Misc
Informational
09/12/2025
Footing okay to pour.
Erosion Control Inspection Failed 9/12/2025 9/12/2025 09/12/2025
Misc
Corrective Action Required
09/12/2025
No further inspections until erosion control is in compliance
Footing Inspection - Commercial Partial 9/17/2025 09/17/2025
Misc
Informational
09/12/2025
Footing okay to pour. Stem walls okay to pour
Sewer Service Inspection Passed 9/30/2025 9/30/2025 09/30/2025
Misc
Informational
09/30/2025
9-30-25 Dustin A, 6 inch Sewer service is tied to existing 6 inch stub. Tracer wire is attached . Pass
Underslab Plumbing Inspection - Commercial Passed 10/8/2025 10/8/2025 10/08/2025
Footing Inspection - Commercial Failed 10/10/2025 10/10/2025 10/10/2025
Misc
Informational
09/17/2025
Footing okay to pour. Stem walls okay to pour
Misc
Corrective Action Required
10/10/2025
Inspection denied see erosion control
Erosion Control Inspection Failed 10/10/2025 10/10/2025 10/10/2025
Misc
Corrective Action Required
09/12/2025
No further inspections until erosion control is in compliance
Misc
Corrective Action Required
10/10/2025
Erosion control not in compliance -dirt and rock in street -silt fence downed around lot -lot access shall be maintained to allow parking and unloading that prevents tracking of mud and materials onto street
Footing Inspection - Commercial Passed 10/14/2025 10/14/2025 10/14/2025
Misc
Resolved
10/14/2025
Footing okay to pour. Stem walls okay to pour
Misc
Resolved
10/14/2025
Inspection denied see erosion control
Water Service Inspection Passed 10/17/2025
Misc
Informational
10/17/2025
10-17-25 Dustin A, water service and tap is installed to city specs.
Rated Assembly Inspection Failed 12/10/2025 12/10/2025 12/10/2025
Misc
Corrective Action Required
12/10/2025
Could not locate address 614 (If 616-620 is address incorrectly repair erosion control before calling for reinspection )
Rated Assembly Inspection Not Ready 12/11/2025 12/11/2025 12/11/2025
Misc
Corrective Action Required
12/10/2025
Could not locate address 614 (If 616-620 is address incorrectly repair erosion control before calling for reinspection ) Still no gravel entry in place
Rated Assembly Inspection Partial 12/12/2025 12/12/2025 12/12/2025
Misc
Resolved
12/12/2025
Could not locate address 614 (If 616-620 is address incorrectly repair erosion control before calling for reinspection ) Still no gravel entry in place
Misc
Informational
12/12/2025
Exterior nailing inspected
Rated Assembly Inspection Partial 1/23/2026 1/23/2026 01/23/2026
Misc
Informational
12/12/2025
Exterior nailing inspected
All Rough Inspection - Commercial Not Ready 2/17/2026 2/17/2026 02/17/2026
Misc
Corrective Action Required
02/17/2026
-Remove all insulation in separation wall for inspection
Electrical Service Inspection Passed 2/17/2026 2/17/2026 02/17/2026
All Rough Inspection - Commercial Failed 2/19/2026 2/19/2026 02/19/2026
Misc
Resolved
02/19/2026
-Remove all insulation in separation wall for inspection
Misc
Corrective Action Required
02/19/2026
Throughout -Remove all Sheetrock stacked against walls for inspection -missing putty packs throughout -multiple putty packs throughout installed improperly -complete HVAC in attic space -missing truss bracing on multiple trusses. 1st checked was B1A -Truss G1 plans call for bracing 1/S061 614 -fireblock top of exterior wall for hvac line set -seal gaps in 10’ fireblock in separation wall 618 -fireblock block wall space to ceiling space rear wall -complete hvac in attic space -fireblock top of furr out wall back side of laundry 620 -seal top plate penetration in foyer -protect dryer vent at top plate -complete electrical in rear bedroom 622 -protect dryer vent at top plate to code
All Rough Inspection - Commercial Passed 2/23/2026 2/23/2026 02/23/2026
Misc
Resolved
02/23/2026
Throughout -Remove all Sheetrock stacked against walls for inspection -missing putty packs throughout -multiple putty packs throughout installed improperly -complete HVAC in attic space -missing truss bracing on multiple trusses. 1st checked was B1A -Truss G1 plans call for bracing 1/S061 614 -fireblock top of exterior wall for hvac line set -seal gaps in 10’ fireblock in separation wall 618 -fireblock block wall space to ceiling space rear wall -complete hvac in attic space -fireblock top of furr out wall back side of laundry 620 -seal top plate penetration in foyer -protect dryer vent at top plate -complete electrical in rear bedroom 622 -protect dryer vent at top plate to code
Rated Assembly Inspection Partial 3/6/2026 3/6/2026 03/06/2026
Misc
Resolved
03/06/2026
Exterior nailing inspected
Misc
Informational
03/06/2026
The following areas inspected 1st layer sheet rock on separation walls
Rated Assembly Inspection Partial 3/13/2026 3/13/2026 03/13/2026
Misc
Informational
03/06/2026
The following areas inspected 1st layer sheet rock on separation walls 2nd layer screw pattern attic only
Rated Assembly Inspection Not Ready 3/23/2026 3/23/2026 03/23/2026
Misc
Informational
03/13/2026
The following areas inspected 1st layer sheet rock on separation walls 2nd layer screw pattern attic only
Misc
Corrective Action Required
03/23/2026
Fire caulk all penetrations
Rated Assembly Inspection Partial 3/25/2026 3/25/2026 03/25/2026
Misc
Informational
03/23/2026
The following areas inspected 1st layer sheet rock on separation walls 2nd layer screw pattern attic only 2nd layer in attic space mud, tape and fire caulk
Misc
Resolved
03/25/2026
Fire caulk all penetrations
Rated Assembly Inspection Passed 3/31/2026 3/31/2026 03/31/2026
Misc
Resolved
03/31/2026
The following areas inspected 1st layer sheet rock on separation walls 2nd layer screw pattern attic only 2nd layer in attic space mud, tape and fire caulk
Documents & Images
Date Uploaded File Type Document Name
06/30/2025 Receipt Receipt for transaction:2025-005063
06/30/2025 Letter DS Building Permit
03/31/2025 Approved Plans Approved plans V1
03/06/2025 Approved Plans Approved plans V2
09/12/2025 Plans Approved Struct Revisions
09/12/2025 Letter INSPECTION SUMMARY
09/12/2025 Letter INSPECTION SUMMARY
09/17/2025 Letter INSPECTION SUMMARY
09/30/2025 Letter INSPECTION SUMMARY
10/08/2025 Letter INSPECTION SUMMARY
10/10/2025 Letter INSPECTION SUMMARY
10/10/2025 Letter INSPECTION SUMMARY
10/14/2025 Letter INSPECTION SUMMARY
10/17/2025 Letter INSPECTION SUMMARY
10/17/2025 Approved Plans Approved Bldg C Trusses
10/17/2025 Approved Plans Building C truss Seals All C buildngs_STAND REVIEWED
11/05/2025 Approved Plans Approved G111
11/12/2025 Approved Plans Approved Truss repair
11/17/2025 Approved Plans Truss repair doc
12/08/2025 Approved Plans Approved E200 revision
12/10/2025 Letter INSPECTION SUMMARY
12/11/2025 Letter INSPECTION SUMMARY
12/12/2025 Letter INSPECTION SUMMARY
01/23/2026 Letter INSPECTION SUMMARY
02/09/2026 Approved Plans REUNION GRADING PLA
02/17/2026 Letter INSPECTION SUMMARY
02/17/2026 Letter INSPECTION SUMMARY
02/19/2026 Letter INSPECTION SUMMARY
02/23/2026 Letter INSPECTION SUMMARY
03/06/2026 Letter INSPECTION SUMMARY
03/13/2026 Letter INSPECTION SUMMARY
03/23/2026 Letter INSPECTION SUMMARY
03/25/2026 Letter INSPECTION SUMMARY
03/31/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home