Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Plan Review
|
Approved with Conditions
|
07/30/2019
|
07/25/2019
|
|
Joe Frogge
|
|
License Tax Application
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
|
|
Miscellaneous Correction
Northern room is not identified.
Action required: Identify use of all rooms.
|
|
Code analysis required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update code analysis with occupant loads.
|
|
Misc
Corrective Action Required
Paint booth and paint rooms shown as future work.
Action required: Comment is for informational purposes. No aspects of paint booth or paint room have been reviewed. Installation of either will require complete, engineered designs and be constructed under a permit.
7/25/19 - acknowledged
|
|
Miscellaneous Correction
2018 IBC 2902.3.1 Access. The route to the public toilet facilities required by Section 2902.3 shall not pass through kitchens, storage rooms or closets. Access to the required facilities shall be from within the building or from the exterior of the building. All routes shall comply with the accessibility requirements of this code. The public shall have access to the required toilet facilities at all times that the building is occupied.
Action required: Comment is for informational purposes. Modification to design may be required dependent on use of northern space.
7/25/19 - no CMR required - approved based on both sides of building being S1
|
|
Miscellaneous Correction
2018 IBC 1203.1 Equipment and systems. Interior spaces intended for human occupancy shall be provided with active or passive space heating systems capable of maintaining an indoor temperature of not less than 68degF at a point 3 feet above the floor on the design heating day. (see code for exceptions)
Action required: Provide complete mechanical design. (shell permit only shows one unit heater installed in northern space and no cooling in either space)
7/25/19 - all mechanical (heat only) performed under shell permit
|
|
Miscellaneous Correction
2018 IMC 403.2 Outdoor air required. The minimum outdoor airflow rate shall be determined in accordance with Section 403.3. (see code for exception)
Action required: Revise drawings to show outside air calculations as well as method of delivery.
7/25/19 - Fenestration well exceeds 4% which qualifies as naturally ventilated
|
|
Miscellaneous Correction
Corrective Action Required
2018 IMC 502.14 Motor vehicle operation. In areas where motor vehicles operate, mechanical ventilation shall be provided in accordance with Section 403. Additionally, areas in which stationary motor vehicles are operated shall be provided with a source capture system that connects directly to the motor vehicle exhaust systems. Such system shall be engineered by a registered design professional or shall be factory-built equipment designed and sized for the purpose. (see code for exceptions)
Action required: Provide exhaust system design.
7/25/19 - Existing source capture system to be reused. Field verify.
|
|
Miscellaneous Correction
2018 IPC 1003.1 Where required. Interceptors and separators shall be provided to prevent the discharge of oil, grease, sand and other substances harmful or hazardous to the public sewer, the private sewage system or the sewage treatment plant or processes.
Action required: Provide sand/oil separation or detailed business plan from tenant that describes how these discharges are avoided.
7/25/19 - all fluids are captured by drain pans
|
|
|
Licensed Contractors
|
Approved
|
07/30/2019
|
07/25/2019
|
|
Joe Frogge
|
|
LC - General Contractor
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
7/25/19 - Tracy D approved to waive gc
|
|
LC - MEP Subs
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (Electrician ok, plumber required if sand/oil separator is added, HVAC contractor required.
7/25/19 - no mechanical or plumbing work to be performed
|
|
|
Fire Plan Review
|
Approved with Conditions
|
07/30/2019
|
07/23/2019
|
|
Michael Weissenbach
|
|
Material safety and data sheets
Corrective Action Required
2018 IFC 407.2- Material Safety Data Sheets. Material Safety Data Sheets (MSDS) for all hazardous materials shall be readily available on the premises.
(Informational Purposes)
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
(Action Required)
Any modifications to the alarm system will require three sets of stamped shop drawings.
|
|
Hazardous material identification
Corrective Action Required
2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 2703.5.
(Informational Purposes)
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
(Action Required)
Any modifications to the fire sprinkler system will require three sets of shop drawings.
|
|
|
Building Plan Review
|
Rejected
|
07/19/2019
|
07/15/2019
|
|
Joe Frogge
|
|
License Tax Application
Corrective Action Required
A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit.
Action required: Comment is for informational purposes.
|
|
Miscellaneous Correction
Corrective Action Required
Northern room is not identified.
Action required: Identify use of all rooms.
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update code analysis with occupant loads.
|
|
Misc
Corrective Action Required
Paint booth and paint rooms shown as future work.
Action required: Comment is for informational purposes. No aspects of paint booth or paint room have been reviewed. Installation of either will require complete, engineered designs and be constructed under a permit.
|
|
Miscellaneous Correction
Corrective Action Required
2018 IBC 2902.3.1 Access. The route to the public toilet facilities required by Section 2902.3 shall not pass through kitchens, storage rooms or closets. Access to the required facilities shall be from within the building or from the exterior of the building. All routes shall comply with the accessibility requirements of this code. The public shall have access to the required toilet facilities at all times that the building is occupied.
Action required: Comment is for informational purposes. Modification to design may be required dependent on use of northern space.
|
|
Miscellaneous Correction
Corrective Action Required
2018 IBC 1203.1 Equipment and systems. Interior spaces intended for human occupancy shall be provided with active or passive space heating systems capable of maintaining an indoor temperature of not less than 68degF at a point 3 feet above the floor on the design heating day. (see code for exceptions)
Action required: Provide complete mechanical design. (shell permit only shows one unit heater installed in northern space and no cooling in either space)
|
|
Miscellaneous Correction
Corrective Action Required
2018 IMC 403.2 Outdoor air required. The minimum outdoor airflow rate shall be determined in accordance with Section 403.3. (see code for exception)
Action required: Revise drawings to show outside air calculations as well as method of delivery.
|
|
Miscellaneous Correction
Corrective Action Required
2018 IMC 502.14 Motor vehicle operation. In areas where motor vehicles operate, mechanical ventilation shall be provided in accordance with Section 403. Additionally, areas in which stationary motor vehicles are operated shall be provided with a source capture system that connects directly to the motor vehicle exhaust systems. Such system shall be engineered by a registered design professional or shall be factory-built equipment designed and sized for the purpose. (see code for exceptions)
Action required: Provide exhaust system design.
|
|
Miscellaneous Correction
Corrective Action Required
2018 IPC 1003.1 Where required. Interceptors and separators shall be provided to prevent the discharge of oil, grease, sand and other substances harmful or hazardous to the public sewer, the private sewage system or the sewage treatment plant or processes.
Action required: Provide sand/oil separation or detailed business plan from tenant that describes how these discharges are avoided.
|
|
|
Licensed Contractors
|
Rejected
|
07/23/2019
|
07/15/2019
|
|
Joe Frogge
|
|
LC - General Contractor
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances.
Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
|
|
LC - MEP Subs
Corrective Action Required
Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt)
No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (Electrician ok, plumber required if sand/oil separator is added, HVAC contractor required.
|
|
|
Fire Plan Review
|
Approved with Conditions
|
07/19/2019
|
07/10/2019
|
|
Michael Weissenbach
|
|
Material safety and data sheets
Corrective Action Required
2018 IFC 407.2- Material Safety Data Sheets. Material Safety Data Sheets (MSDS) for all hazardous materials shall be readily available on the premises.
(Informational Purposes)
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
(Action Required)
Any modifications to the alarm system will require three sets of stamped shop drawings.
|
|
Hazardous material identification
Corrective Action Required
2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 2703.5.
(Informational Purposes)
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
(Action Required)
Any modifications to the fire sprinkler system will require three sets of shop drawings.
|
|
|