Review Type |
Outcome |
Est. Completion Date |
Completed |
Alarm Plan Review
|
Released for Construction
|
|
11/29/2018
|
|
Joe Dir
|
|
Miscellaneous Correction
Riser diagram / NFPA symbols
ACTION REQUIRED: Alarm system riser diagram and the NFPA symbol legend need to include the WP horn/strobe and the W-horn strobe, and NAC symbols and definition.
|
|
Miscellaneous Correction
NAC panel
ACTION REQUIRED: Plans show NAC circuits but no NAC panel .
Plans need to show the NAC panel locations.
|
|
Misc
Manual pull stations
ACTION REQUIRED: Eliminate all but one manual pull station from all buildings including the clubhouse. The one manual pull station is to be mounted by the FAC.
|
|
Miscellaneous Correction
Battery Caclulations
ACTION REQUIRED: Battery Calculations need to include the size and number of batteries to be installed in each buildings FAC and NAC panels.
|
|
Miscellaneous Correction
FAA location
ACTION REQUIRED: Relocate the FAA from the corridor to the Front entry vestibule.
|
|
Miscellaneous Correction
Strobe notification devices
ACTION REQUIRED: Replace the horn and horn/strobe notification devices with STROBE only notification in the following areas.
Clubhouse: restrooms, dogwash room, massage room and breakroom
|
|
Miscellaneous Correction
Smoke detection
ACTION REQUIRED: Plans need to show smoke detection in the following areas.
Sheet FA1-16 Type V bldg. 2nd floor hallways
Sheet FA1-18 Type VI bldg. 2nd floor hallways
Elevator lobbys and hoistways/pits
Reference material:
Elevator emergency operation, Area smoke Detection IFC 2012 sec. 907.2.13.1.1 907.3.3
Elevator lobbys - reference IFC 2012 sec. 907.2.13.1.1 NFPA 72 sec. 21.3.5
Elevator hoistways - reference IFC 2012 sec 907.2.13.1.1 NFPA 72 sec. 21.3.6, 21.3.7, 21.3.8
|
|
Miscellaneous Correction
Manufacturers specs.
ACTION REQUIRED:Provide manufactures specs for the following:
smoke dampers,
carbon monoxide detectors to be installed in the garages.
strobe only notification devices for the restrooms and other rooms specified
|
|
Installation acceptance testing
Corrective Action Required
2012 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
ACTION REQUIRED:
Acceptance testing of the Fire Alarm System in each building will required prior to the final occupancy inspection of each building. Contact the Fire Department to schedule testing. (816)969-1300
|
|
Miscellaneous Correction
Corrective Action Required
Plan Sheet FA1.26
ACTION REQUIRED: Clubhouse Terrace Level - All addressable manual pull stations need to be removed from plan sheet FA1.26 Clubhouse terrace level.
After a phone conversation with the (P.E.) Rich Beardmore a decision was made that the manual pull stations will be (X) marked off the plan sheets by the plan reviewer and a note added to plan sheets FA1.26 not to install the addressable manual pull stations on the terrace level of the clubhouse.
|
|
|
Alarm Plan Review
|
Rejected
|
|
11/20/2018
|
|
Joe Dir
|
|
Miscellaneous Correction
Corrective Action Required
Riser diagram / NFPA symbols
ACTION REQUIRED: Alarm system riser diagram and the NFPA symbol legend need to include the WP horn/strobe and the W-horn strobe, and NAC symbols and definition.
|
|
Miscellaneous Correction
Corrective Action Required
NAC panel
ACTION REQUIRED: Plans show NAC circuits but no NAC panel .
Plans need to show the NAC panel locations.
|
|
Misc
Corrective Action Required
Manual pull stations
ACTION REQUIRED: Eliminate all but one manual pull station from all buildings including the clubhouse. The one manual pull station is to be mounted by the FAC.
|
|
Miscellaneous Correction
Corrective Action Required
Battery Caclulations
ACTION REQUIRED: Battery Calculations need to include the size and number of batteries to be installed in each buildings FAC and NAC panels.
|
|
Miscellaneous Correction
Corrective Action Required
FAA location
ACTION REQUIRED: Relocate the FAA from the corridor to the Front entry vestibule.
|
|
Miscellaneous Correction
Corrective Action Required
Strobe notification devices
ACTION REQUIRED: Replace the horn and horn/strobe notification devices with STROBE only notification in the following areas.
Clubhouse: restrooms, dogwash room, massage room and breakroom
|
|
Miscellaneous Correction
Corrective Action Required
Smoke detection
ACTION REQUIRED: Plans need to show smoke detection in the following areas.
Sheet FA1-16 Type V bldg. 2nd floor hallways
Sheet FA1-18 Type VI bldg. 2nd floor hallways
Elevator lobbys and hoistways/pits
Reference material:
Elevator emergency operation, Area smoke Detection IFC 2012 sec. 907.2.13.1.1 907.3.3
Elevator lobbys - reference IFC 2012 sec. 907.2.13.1.1 NFPA 72 sec. 21.3.5
Elevator hoistways - reference IFC 2012 sec 907.2.13.1.1 NFPA 72 sec. 21.3.6, 21.3.7, 21.3.8
|
|
Miscellaneous Correction
Corrective Action Required
Manufacturers specs.
ACTION REQUIRED:Provide manufactures specs for the following:
smoke dampers,
carbon monoxide detectors to be installed in the garages.
strobe only notification devices for the restrooms and other rooms specified
|
|
|
Licensed Contractors
|
Approved
|
03/16/2018
|
03/16/2018
|
|
Joe Frogge
|
|
|