Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Footing Inspection - Commercial
|
Partial
|
|
3/22/2019
|
03/22/2019
|
|
Misc
Corrective Action Required
|
Foundation Inspection - Commercial
|
Passed
|
|
3/26/2019
|
03/26/2019
|
Footing Inspection - Commercial
|
Partial
|
3/27/2019 (3:00)
|
3/28/2019
|
03/28/2019
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
4/17/2019
|
4/17/2019
|
04/17/2019
|
|
Misc
Corrective Action Required
|
Sewer Service Inspection
|
Passed
|
4/26/2019
|
4/26/2019
|
04/26/2019
|
|
Misc
|
Footing Inspection - Commercial
|
Passed
|
6/13/2019 (2:00)
|
6/13/2019
|
06/13/2019
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
11/13/2019
|
11/13/2019
|
11/13/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
|
11/14/2019
|
11/14/2019
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
All Rough Inspection - Commercial
|
Passed
|
11/19/2019
|
11/19/2019
|
11/19/2019
|
|
SECOND FLOOR
|
|
FIRST FLOOR
|
|
LOWER LEVEL
|
Rated Assembly Inspection
|
Partial
|
|
11/19/2019
|
12/04/2019
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Not Ready
|
|
12/4/2019
|
12/04/2019
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/5/2019
|
12/5/2019
|
12/05/2019
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/31/2019
|
12/31/2019
|
12/31/2019
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
1/6/2020
|
1/6/2020
|
01/06/2020
|
|
LOWER LEVEL
Corrective Action Required
|
|
FIRST FLOOR
|
|
SECOND FLOOR
|
Electrical Service Inspection
|
Passed
|
1/6/2020
|
1/6/2020
|
01/06/2020
|
Rated Assembly Inspection
|
Passed
|
1/10/2020
|
1/10/2020
|
01/10/2020
|
|
LOWER LEVEL
|
Water Service Inspection
|
Passed
|
|
|
01/24/2020
|
Sewer Service Inspection
|
Passed
|
|
|
01/24/2020
|
Rated Assembly Inspection
|
Partial
|
1/24/2020
|
1/24/2020
|
01/24/2020
|
|
Misc
|
Sprinkler - Hydrostatic Test
|
Failed
|
|
4/1/2020
|
04/01/2020
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
4/7/2020
|
04/07/2020
|
Piers/Caissons Inspection - Commercial
|
Partial
|
4/17/2020 (8:00)
|
4/17/2020
|
04/17/2020
|
|
Misc
|
Alarm Test
|
Passed
|
|
4/28/2020
|
04/28/2020
|
Sprinkler - Flow Test
|
Passed
|
|
4/28/2020
|
04/28/2020
|
Occupancy Inspection - Fire
|
Failed
|
|
5/20/2020
|
05/20/2020
|
Occupancy Inspection - Fire
|
Passed
|
|
5/20/2020
|
05/20/2020
|
Rated Assembly Inspection
|
Passed
|
|
5/20/2020
|
05/20/2020
|
|
Misc
|
Occupancy Inspection - Codes Commercial
|
Failed
|
5/20/2020
|
5/20/2020
|
05/20/2020
|
|
Misc
Corrective Action Required
|
Rough Plumbing Inspection - Commercial
|
Passed
|
|
5/22/2020
|
05/22/2020
|
Rough Mechanical Inspection - Commercial
|
Passed
|
|
5/22/2020
|
05/22/2020
|
Rough Electrical Inspection - Commercial
|
Passed
|
|
5/22/2020
|
05/22/2020
|
Piers/Caissons Inspection - Commercial
|
Passed
|
|
5/22/2020
|
05/22/2020
|
Occupancy Inspection - Engineering
|
Passed
|
|
|
05/22/2020
|
Occupancy Inspection - Codes Commercial
|
Temporary C of O
|
|
5/22/2020
|
05/22/2020
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Planning
|
Passed
|
|
|
10/30/2020
|
Occupancy Inspection - Planning
|
Passed
|
|
|
10/30/2020
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
|
10/30/2020
|
|
Misc
|