Permit Application Status

PRCOM20170409


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20170409
Building Permit - Commercial
Certificate of Occupancy
M150 ECHELON LAND DEV LLC
NEW MULTI-FAMILY
NEW 3 STORY APARTMENT BUILDING FOUNDATION/UNDERSLAB PERMTIT - PRCOM20181437 *NOT TO BE ISSUED UNTIL FIRE DEPARTMENT RELEASES PERMIT
02/16/2017
08/07/2018
10/29/2020
Locations
Contacts
LUKE DRAILY CONSTRUCTION INC, Address:75 NW BUSINESS PARK LANE, Phone:(816) 459-8531  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
ELECTRICAL ENTERPRISES INC, Address:PO BOX 127, Phone:(785) 242-7971  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
NSPJ ARCHITECTS, Address:3515 W 75TH ST, SUITE 201, Phone:(913) 831-1415 Ext:278  
KANSAS CITY TESTING & ENGINEERING, Address:1308 ADAMS STREET, Phone:(913) 321-8100  
M150 ECHELON LAND DEV LLC, Address:120 SE 30TH ST  
GRIFFIN RILEY PROPERTY GROUP, Address:21 SE 29TH TER, Phone:(816) 366-7900  
CITY OF LEE'S SUMMIT MISSOURI, Address:220 SE GREEN ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved 03/06/2017 04/12/2018
Joe Frogge
Building Plan Review Approved 06/14/2018 04/12/2018
Joe Frogge
Licensed Contractors Approved 06/14/2018 04/12/2018
Joe Frogge
Special Inspections Review Approved 02/05/2018
Joe Frogge
Final Development Plan Review Approved 03/06/2017 02/05/2018
Joe Frogge
Alarm Plan Review Released for Construction 05/24/2017
Joe Dir
Sprinkler Plan Review Released for Construction 05/24/2017
Joe Dir
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Multi-Family $12,578.78 $12,578.78 Paid 12/20/2017
8331507-Sewer Connection Fee $3,000.00 $3,000.00 Paid 12/20/2017
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 9/24/2018 (3:00) 9/24/2018 09/24/2018
Misc
Corrective Action Required
09/24/2018
North 6 interior grade beams approved
Sprinkler - Hydrostatic Test Passed 4/4/2019 04/04/2019
Electrical Service Inspection Partial 5/6/2019 5/6/2019 05/06/2019
Misc
Partial Correction
05/06/2019
TEMP POWER APPROVED
All Rough Inspection - Commercial Failed 7/3/2019 7/3/2019 07/03/2019
Misc
Corrective Action Required
07/03/2019
307-Back to back low voltage, verify distance with box manufacture and UL. 306-hold down screw north wall kit. Verify with 3rd party inspector. 308-10’ Fire stop party walls. 309-4” DWV fire collar-party wall. 311-South bathroom sub floor no backing under plywood. 310- 10’ Fire stopping at party walls.
Above Ceiling Inspection Passed 7/3/2019 7/3/2019 07/03/2019
All Rough Inspection - Commercial Failed 7/10/2019 7/10/2019 07/10/2019
Misc
Corrective Action Required
07/03/2019
309 - 10’ Fire stop party walls. 310- 10’ Fire stopping at party walls.
All Rough Inspection - Commercial Passed 7/11/2019 7/11/2019 07/11/2019
Misc
Resolved
07/11/2019
All Rough Inspection - Commercial Failed 7/11/2019 7/11/2019 07/11/2019
Misc
Corrective Action Required
07/11/2019
First floor -Fire block party walls in garage per code -fire block party wall separating room 107 and 105 -outlets in same wall opening in room 107- fire puddy on outlet boxes -fire block party walls separating rooms on the south side 1st floor Second floor -Fire puddy for outlet boxes in wall separating rooms 210 and 211 -tie down room 211 south side just inside bedroom on left side -fire block penetration on ride side of bedroom room 211 south side -fire puddy outlets dividing room 209 and 211 -support strap for duct cut in main room, room 208. Properly support -fire puddy all outlets in double wall per code, 2nd floor mostly south side
All Rough Inspection - Commercial Failed 7/22/2019 7/22/2019 07/22/2019
Misc
Corrective Action Required
07/22/2019
Tie down in room 211 south side just inside bedroom on left side Fire block penetration on floor in room 211, right side of bedroom Support strap for duct work cut in room 208, needs to be properly supported
All Rough Inspection - Commercial Partial 8/6/2019 8/6/2019 08/06/2019
Misc
Informational
08/06/2019
Second floor all rough approved
Rated Assembly Inspection Partial 8/13/2019 08/13/2019
Misc
Corrective Action Required
08/13/2019
First layer of Sheetrock on ceiling on 3rd floor, and stair towers in building 7 approved to continue work.
All Rough Inspection - Commercial Partial 8/15/2019 8/15/2019 08/15/2019
Misc
Informational
08/15/2019
1st floor all rough approved on building 7, ok to insulate
Rated Assembly Inspection Failed 8/20/2019 8/20/2019 08/20/2019
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/20/2019
First layer of Sheetrock on ceiling on 3rd floor, and stair towers in building 7 approved to continue work.
Misc
Corrective Action Required
08/20/2019
2nd layer of ceiling on the 3rd floor layers not off set from 1st 24" as per UL listing.
Rated Assembly Inspection Failed 8/23/2019 8/23/2019 08/23/2019
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/20/2019
First layer of Sheetrock on ceiling on 3rd floor, and stair towers in building 7 approved to continue work.
Misc
Corrective Action Required
08/20/2019
2nd layer of ceiling on the 3rd floor layers not off set from 1st 24" as per UL listing, *****inspection performed on 8/23/19. Still need to fix all ceiling layers on 3rd floor, north and south side along with north and south stair towers. Leave a piece of sheet rock off of ceilings in order to verify spacing for next inspection. Only 1 layer on stair towers.
Rated Assembly Inspection Failed 8/26/2019 8/26/2019 08/26/2019
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/23/2019
First layer of Sheetrock on ceiling on 3rd floor, and stair towers in building 7 approved to continue work.
Misc
Corrective Action Required
08/23/2019
2nd layer of ceiling on the 3rd floor layers not off set from 1st 24" as per UL listing, *****inspection performed on 8/26/19 north and south stair towers need to be re done, leave off piece of sheet rock for next inspection. Sheet rock seam outside of room 304 is too close from 1st layer to 2nd layer.
Rated Assembly Inspection Partial 8/28/2019 8/28/2019 08/28/2019
THE FOLLOWING AREAS ARE APPROVED
Resolved
08/28/2019
First layer of Sheetrock on ceiling on 3rd floor, and stair towers in building 7 approved to continue work.
Misc
Resolved
08/28/2019
SECOND FLOOR
Corrective Action Required
08/28/2019
2ND FLOOR WALLS & CEILINGS
FIRST FLOOR
Corrective Action Required
08/28/2019
THIRD FLOOR
Corrective Action Required
08/28/2019
CEILINGS AND WALLS OK 3RD LAYER OF STAIR TOWERS.
Rated Assembly Inspection Failed 9/3/2019 9/3/2019 09/03/2019
SECOND FLOOR
Corrective Action Required
08/28/2019
2ND FLOOR WALLS & CEILINGS
FIRST FLOOR
Corrective Action Required
08/28/2019
First floor main rooms and garages walls and ceilings **room 109 needs sheet rock installed behind bath tub ** all thread coming through ceiling in garage, 2nd garage from the far north end ** all sheet rock seams need to be gone over in every room, bathroom, closet, etc. on screws being too close to seams and not being code compliant, all rooms units and garages on 1st floor. With screws being too close to the seams, the fasteners are over spaced. **ok to tape the ceilings in rooms and garages but not the walls
THIRD FLOOR
Resolved
09/03/2019
Rated Assembly Inspection Failed 9/5/2019 9/5/2019 09/05/2019
SECOND FLOOR
Corrective Action Required
09/03/2019
2ND FLOOR WALLS & CEILINGS
FIRST FLOOR
Corrective Action Required
09/03/2019
First floor main rooms and garages walls and ceilings **room 109 needs sheet rock installed behind bath tub ** all thread coming through ceiling in garage, 2nd garage from the far north end ** all sheet rock seams need to be gone over in every room, bathroom, closet, etc. on screws being too close to seams and not being code compliant, all rooms units and garages on 1st floor. With screws being too close to the seams, the fasteners are over spaced. **ok to tape the ceilings in rooms and garages but not the walls
THIRD FLOOR
Corrective Action Required
09/05/2019
Third floor stair tower ceilings failed. Need to install hat channel per UL listing on plans
Rated Assembly Inspection Partial 9/9/2019 9/9/2019 09/09/2019
SECOND FLOOR
Corrective Action Required
09/05/2019
2ND FLOOR WALLS & CEILINGS
FIRST FLOOR
Corrective Action Required
09/05/2019
First floor main rooms and garages walls and ceilings **ok to tape Everything except hallway walls on 1st floor, need to be redone to match plans (type B) walls
THIRD FLOOR
Resolved
09/09/2019
Third floor stair tower ceilings approved for 4th layer of sheet rock
Rated Assembly Inspection Partial 9/11/2019 9/11/2019 09/11/2019
SECOND FLOOR
Corrective Action Required
09/09/2019
2ND FLOOR WALLS & CEILINGS
FIRST FLOOR
Informational
09/11/2019
All first floor is approved to mud and tape
Rated Assembly Inspection Partial 9/16/2019 9/16/2019 09/16/2019
SECOND FLOOR
Resolved
09/16/2019
THIRD FLOOR
Informational
09/16/2019
4th layer in stair tower ceilings are approved
Underground Electrical Inspection - Commercial Partial 9/16/2019 9/16/2019 09/16/2019
Misc
Partial Correction
09/16/2019
All light pole bases on west side of property approved except the light pole base on the south side entrance off of cheddington is approved.
Electrical Service Inspection Failed 11/13/2019 11/13/2019 11/13/2019
Misc
Corrective Action Required
11/13/2019
Install grounding electrode conductor sized for the service to the ufer ground
Electrical Service Inspection Passed 12/6/2019 12/6/2019 12/06/2019
Misc
Resolved
12/06/2019
Alarm Test Failed 3/4/2020 03/04/2020
Sprinkler - Flow Test Passed 3/4/2020 03/04/2020
Alarm Test Passed 3/17/2020 03/17/2020
Rated Assembly Inspection Passed 03/19/2020
SECOND FLOOR
Informational
09/16/2019
Stair towers 4th layer of sheet rock is approved
Rough Mechanical Inspection - Commercial Passed 03/19/2020
Rough Plumbing Inspection - Commercial Passed 03/19/2020
In-wall Inspection Passed 03/19/2020
All Rough Inspection - Commercial Passed 03/19/2020
Misc
Informational
08/15/2019
1st floor all rough approved on building 7, ok to insulate
Final Mechanical Inspection Passed 03/19/2020
Final Electrical Inspection - Commercial Passed 03/19/2020
Final Plumbing Inspection - Commercial Passed 03/19/2020
Occupancy Inspection - Codes Commercial Failed 3/19/2020 3/19/2020 03/25/2020
Resolved
03/26/2020
Occupancy Inspection - Water Utilities Passed 3/19/2020 03/25/2020
Occupancy Inspection - Planning Passed 3/19/2020 03/25/2020
Occupancy Inspection - Engineering Passed 3/19/2020 03/25/2020
Occupancy Inspection - Codes Commercial Temporary C of O 3/26/2020 03/26/2020
Occupancy Inspection - Codes Commercial Full C of O 10/29/2020
Occupancy Inspection - Fire Passed 3/19/2020 10/29/2020
Documents & Images
Date Uploaded File Type Document Name
05/22/2017 Permit Map
12/20/2017 Receipt Receipt for transaction: 2017-007716
08/07/2018 Letter Codes Building Permit
09/24/2018 Letter Inspection Summary
05/06/2019 Letter INSPECTION SUMMARY
07/03/2019 Letter INSPECTION SUMMARY
07/03/2019 Letter INSPECTION SUMMARY
07/10/2019 Letter INSPECTION SUMMARY
07/11/2019 Letter INSPECTION SUMMARY
07/11/2019 Letter INSPECTION SUMMARY
07/22/2019 Letter INSPECTION SUMMARY
08/06/2019 Letter INSPECTION SUMMARY
08/13/2019 Letter INSPECTION SUMMARY
08/15/2019 Letter INSPECTION SUMMARY
08/20/2019 Letter INSPECTION SUMMARY
08/23/2019 Letter INSPECTION SUMMARY
08/26/2019 Letter INSPECTION SUMMARY
08/28/2019 Letter INSPECTION SUMMARY
09/03/2019 Letter INSPECTION SUMMARY
09/05/2019 Letter INSPECTION SUMMARY
09/09/2019 Letter INSPECTION SUMMARY
09/11/2019 Letter INSPECTION SUMMARY
09/16/2019 Letter INSPECTION SUMMARY
09/16/2019 Letter INSPECTION SUMMARY
11/13/2019 Letter INSPECTION SUMMARY
12/06/2019 Letter INSPECTION SUMMARY
03/17/2020 Letter INSPECTION SUMMARY
03/26/2020 Letter Codes Temporary Certificate of Occupancy
08/03/2020 Letter DS Building Permit
10/29/2020 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home