Summary
PRCOM20151978
Building Permit - Commercial
Final Completion
SUMMIT WOODS SPE LLC
NEW OTHER (COMMERCIAL)
ELECTRIC CAR CHARGING STATIONS
08/26/2015
06/10/2016
08/16/2016
Locations
Contacts
MARK ONE ELECTRIC CO INC, Address:1414 GENESSEE ST, Phone:(816) 842-7023  
SUMMIT WOODS SPE LLC, Address:PO BOX 2148  
WAL-MART REAL ESTATE BUSINESS TRUST, Address:PO BOX 8050  
Reviews
Review Type Outcome Est. Completion Date Completed
Public Works Review Approved 09/09/2015 06/10/2016
Dawn Bell
PW-Misc
Corrective Action Required
06/10/2016

It is the responsibility of the contractor to acquire all (private/public) existing utility locations prior to construction. It is the responsibility of the contractor to restore any damaged or broken utility/infrastructure to original or better condition.
Misc
Corrective Action Required
06/10/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Public Works Review Rejected 09/10/2015 09/02/2015
Joe Frogge
Building Plan Review Approved 09/10/2015 08/26/2015
Joe Frogge
Licensed Contractors Approved 09/10/2015 08/26/2015
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Other $36.74 $36.74 Paid 06/10/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Electrical Inspection - Commercial Passed 6/30/2016 6/30/2016 06/30/2016
Final Electrical Inspection - Commercial Not Ready 7/8/2016 7/8/2016 07/08/2016
Misc
Corrective Action Required
07/08/2016
ELECTRICAL SERVICE INSPECTION HAS NOT BEEN REQUESTED OR PERFORMED. ACCESS TO PEDESTAL INTERNALS REQUIRED.
Electrical Service Inspection Passed 8/16/2016 08/16/2016
Final Electrical Inspection - Commercial Passed 8/16/2016 08/16/2016
Misc
Corrective Action Required
07/08/2016
ELECTRICAL SERVICE INSPECTION HAS NOT BEEN REQUESTED OR PERFORMED. ACCESS TO PEDESTAL INTERNALS REQUIRED.
Investigation Inspection Complete 8/16/2016 08/16/2016
Documents & Images
Date Uploaded File Type Document Name
06/10/2016 Letter Codes Building Permit
06/10/2016 Receipt Receipt for transaction: 2016-003565
06/10/2016 Letter Codes Plan Review Conditions
06/30/2016 Letter Inspection Summary
08/16/2016 Letter Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home