Permit Application Status

PRCOM20151608


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20151608
Building Permit - Commercial
Final Completion
SAINT LUKES EAST HOSPITAL
ALTERATION COMMERCIAL
INTERIOR ALTERATIONS FOR EXISTING TENANT
07/20/2015
08/27/2015
09/10/2015
Locations
Contacts
TURNER CONSTRUCTION COMPANY, Address:1220 WASHINGTON STE 1000, Phone:(816) 283-0555  
P1 CONSTRUCTION LLC, Address:13605 W 96TH TERR, Phone:(913) 529-5000  
SHAW ELECTRIC COMPANY, Address:3600 FULLER, Phone:(816) 921-0033  
P1 CONSTRUCTION LLC, Address:13605 W 96TH TERR, Phone:(913) 529-5000  
GUY GRONBERG ARCHITECTS, Address:113 SE 3RD ST, Phone:(816) 524-0878  
SAINT LUKES EAST HOSPITAL, Address:901 E 104TH ST MAILSTOP 900N  
Reviews
Review Type Outcome Est. Completion Date Completed
Alarm Plan Review Released for Construction 12/31/2015
Joe Dir
Sprinkler Plan Review Released for Construction 12/31/2015
Joe Dir
Fire Plan Review Approved with Conditions 07/29/2015
Joe Frogge
Misc
Corrective Action Required
07/29/2015

Any or all electrical outlets and switches connected to the Generator power will need to be tested for proper connection to generator circuits if moved or altered during the rennovation process. For information purposes
IFGC - Inspection, testing and maintenance - alarm and extinguishing systems 901.6
Corrective Action Required
07/29/2015

2006 IFC 901.6- Inspection, testing and maintenance. Fire detection, alarm and extinguishing systems shall be maintained in an operative condition at all times, and shall be replaced or repaired where defective. Not required fire protection systems and equipment shall be inspected, tested and maintained or removed. All alarm notification and activation devices to remain in full operation during the demolation and rennovation construction. For information purposes
Alarm testing.
Corrective Action Required
07/29/2015

2006 IFC 904.4.2- Alarm testing. Notification appliances, connections to fire alarm systems, and connections to approved supervising stations shall be tested in accordance with this section and Section 907 to verify proper operation. Testing of the alarm system in the rennovation area will be required if any of the alarm devices are relocated, disconnected or altered during the rennovation process. For information purposes.
Licensed Contractors Approved 07/30/2015 07/29/2015
Joe Frogge
LC - MEP Subs
Resolved
07/29/2015

No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Excerpt from Sec. 7-130, Lees Summit Code of Ordinances. Action required: MEP subcontractors are required to be listed on permit. Provide company names of MEP contractors.
Fire Plan Review Approved with Conditions 07/30/2015 07/27/2015
Joe Dir
Misc
Corrective Action Required
07/27/2015

Any or all electrical outlets and switches connected to the Generator power will need to be tested for proper connection to generator circuits if moved or altered during the rennovation process. For information purposes
IFGC - Inspection, testing and maintenance - alarm and extinguishing systems 901.6
Corrective Action Required
07/27/2015

2006 IFC 901.6- Inspection, testing and maintenance. Fire detection, alarm and extinguishing systems shall be maintained in an operative condition at all times, and shall be replaced or repaired where defective. Not required fire protection systems and equipment shall be inspected, tested and maintained or removed. All alarm notification and activation devices to remain in full operation during the demolation and rennovation construction. For information purposes
Alarm testing.
Corrective Action Required
07/27/2015

2006 IFC 904.4.2- Alarm testing. Notification appliances, connections to fire alarm systems, and connections to approved supervising stations shall be tested in accordance with this section and Section 907 to verify proper operation. Testing of the alarm system in the rennovation area will be required if any of the alarm devices are relocated, disconnected or altered during the rennovation process. For information purposes.
Building Plan Review Approved 07/30/2015 07/22/2015
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Alteration to Commercial $329.90 $329.90 Paid 08/27/2015
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Miscellaneous Inspection Partial 9/2/2015 9/2/2015 at 12:00 AM 09/02/2015
Misc
Partial Correction
09/02/2015
COURTESY WALK-THROUGH AND INSPECTION DISCUSSION WITH JOHN OF TURNER CONSTRUCTION.
In-wall Inspection Passed 9/9/2015 9/9/2015 at 12:00 AM 09/09/2015
Alarm Test Passed 09/11/2015
Final Inspection - Commercial Partial 9/11/2015 9/11/2015 at 12:00 AM 09/11/2015
Misc
Partial Correction
09/11/2015
FOLLOWING FIRST PHASE RENOVATED & MODIFIED SPACES ARE OK FOR USE AND OCCUPANCY: 3D335; 345; 349; 353; 354; 356; 357; 358;
Occupancy Inspection - Fire Passed 9/17/2015 at 12:00 AM 09/17/2015
Final Inspection - Commercial Passed 9/17/2015 at 12:00 AM 09/17/2015
Misc
Resolved
09/17/2015
FOLLOWING FIRST PHASE RENOVATED & MODIFIED SPACES ARE OK FOR USE AND OCCUPANCY: 3D335; 345; 349; 353; 354; 356; 357; 358;
Documents & Images
Date Uploaded File Type Document Name
07/27/2015 Letter Fire Building Plan Review
07/29/2015 Letter Codes Plan Review Conditions
08/27/2015 Letter Codes Building Permit
08/27/2015 Receipt Receipt for transaction: 2015-005059
09/02/2015 Letter Inspection Summary
09/09/2015 Letter Inspection Summary
09/11/2015 Letter Inspection Summary
09/17/2015 Letter Inspection Summary
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home