Planning Application Status

PL2025209




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2025209
Charlie's Car Wash - outdoor vacuum stations, central vacuum system and off-site parking; 950 NW Chipman Rd.
Commercial Final Development Plan
Commercial Final Development Plan
Approved
08/08/2025
CWW ENTERPRISES LLC
Charlie's Car Wash - outdoor vacuum stations, central vacuum system and off-site parking; 950 NW Chipman Rd.
Locations
Contacts
CWW ENTERPRISES LLC, Address:500 GRAVES BLVD  
DAVID EICKMAN, Address:OLSSON ASSOCIATES, Phone:(816) 361-1177  
Donald Boos, Address:500 Graves Boulevard, Phone:(913) 269-4462  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 09/08/2025 09/10/2025
Sue Pyles, P.E.
DE Contact Field Eng. Inspector
Corrective Action Required
09/10/2025

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE Engineers Estimate
Corrective Action Required
09/10/2025

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
Planning Review No Comments 09/08/2025 09/08/2025
Hector Soto Jr.
Planning Review Corrections 08/26/2025 08/26/2025
Hector Soto Jr.
Corrective Action Required
08/26/2025

FLOODPLAIN. Add a note to the plans regarding the site's location relative to the 100-year floodplain. Cite the FIRM Panel information used to make the determination.
Corrective Action Required
08/26/2025

OIL AND GAS WELLS. Add a note to the plans regarding the presence of any active, inactive or capped oil and/or gas wells on the site. Cite the source of information used to make the determination. MoDNR maintains a well database that can be sourced and cited.
Engineering Review Corrections 08/26/2025 08/26/2025
Sue Pyles, P.E.
Corrective Action Required
08/26/2025

Sheet C1.0: The right-turn arrow immediately south of the proposed vacuum building is shaded as if existing and not impacted throughout the plan set, but is shown as being removed on this sheet. Please clarify and revise as needed.
Corrective Action Required
08/26/2025

Sheet C10.0: Revise asphalt pavement section. KCMMB asphalt is now required, as specified in the Design and Construction Manual LS Section 2205.
Fire Review No Comments 08/26/2025 08/21/2025
Jim Eden
Building Codes Review Approved with Conditions 08/26/2025 08/20/2025
Joe Frogge
Miscellaneous Correction
Corrective Action Required
08/20/2025

MEP plans have been deferred to building submittal.
Miscellaneous Correction
Corrective Action Required
08/20/2025

Architectural review not included in this review.
Traffic Review No Comments 08/26/2025 08/20/2025
Erin Ralovo
Fees
Paid Fees Amount Paid Owing Date Paid
Final Development Plan fee $725.00 $725.00 Paid 08/12/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home

*PLEASE NOTE - You must be logged in with your registered user account to view any documents related to your Planning Application