Planning Application Status

PL2023172




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2023172
Wilshire Hills 4th Plat - Mass Grading and ESC
Engineering Plan Review
Engineering Plan Review
Approved
06/27/2023
JEFFREY E SMITH INV CO LC
Locations
Contacts
JEFFREY E SMITH INV CO LC, Address:PO BOX 7688  
ENGINEERING SURVEYS & SERVICES, Address:1113 FAY ST, Phone:(573) 449-2646  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 05/02/2024 05/02/2024
Gene Williams, P.E.
Engineering Review Corrections 04/12/2024
Gene Williams, P.E.
Corrective Action Required
04/12/2024

Please see comments related to the street and stormwater, and in particular, the detention basin and stormwater report. Additional revisions to the detention basin grading and outlet structure may be necessary, and thus this plan cannot be approved until the former is approvable.
Engineering Review Corrections 03/05/2024 03/05/2024
Gene Williams, P.E.
Corrective Action Required
03/05/2024

Please see comments on the Street, Stormwater and Detention Basin plans. It appears detention to limit the peak discharge for the 2, 10, and 100 year events shall be necessary based on the results of the stormwater study. As such, the detention basin design will be changing. Please revise as appropriate.
Engineering Review Approved with Conditions 12/12/2023 12/12/2023
Gene Williams, P.E.
Engineering Review Corrections 11/01/2023 11/02/2023
Gene Williams, P.E.
Corrective Action Required
11/02/2023

Please see comments related to the stormwater detention and stream buffer aspects of the project. Both of these issues have the potential to change the plans significantly.
Corrective Action Required
11/02/2023

Sediment Basin: Please be aware any skimmers shall include a site-specific design with sizing information shown on the plans.
Engineering Review Corrections 07/14/2023 07/17/2023
Gene Williams, P.E.
Corrective Action Required
07/17/2023

Turf reinforcement mat is required in all swales and along the sides of detention basins. Please revise as appropriate.
Corrective Action Required
07/17/2023

It was our understanding the detention basin/retention basin was going to be utilized for temporary sediment basin. If so, are skimmers going to be installed? If so, a site-specific design is required for the skimmers. Please evaluate and revise if appropriate.
Hearings

There are no hearings for this planning application.

Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home