Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
No Comments
|
05/20/2024
|
05/20/2024
|
|
Gene Williams, P.E.
|
|
|
Engineering Review
|
No Comments
|
03/05/2024
|
03/05/2024
|
|
Gene Williams, P.E.
|
|
|
Engineering Review
|
Corrections
|
12/12/2023
|
12/12/2023
|
|
Gene Williams, P.E.
|
|
|
Traffic Review
|
No Comments
|
12/12/2023
|
11/29/2023
|
|
Daniel Fernandez
|
|
|
Engineering Review
|
Corrections
|
11/01/2023
|
11/02/2023
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
It does not appear there was any consideration to lowering the storm lines on the street and stormwater plans. This has an impact on the water main, as you are showing the installation of water main beneath storm lines which is not preferred and presents a long-term maintenance issue to Water Utilities. One of the storm lines is a private line, and is shown over the top of the public water main which is not allowed. Please review the street and stormwater plans, and determine how to eliminate the conflicts with the water and storm lines so the water main can be installed over the top of the storm line.
|
|
Corrective Action Required
Additional fire hydrant(s) are appear to be warranted. Fire hydrants shall be provided every 500 feet on public water mains. Please evaluate and revise as appropriate. Ensure the fire hydrants are not located within 20 feet of a intersection curb return radius.
|
|
Corrective Action Required
Deflecting the C900 pipe by 1 degree at each joint produces an approximate 1200 foot radius of curvature. It appears the deflection near station 5+00, 6+25, and 8+75 is less than 1200 feet radius of curvature, and therefore, bends should be installed to eliminate any stress in the line. Please evaluate the locations of bends, and revise as appropriate.
|
|
Corrective Action Required
The steel casing pipe is not necessary at Strother Rd. if the 8 inch line can be bored without the casing carrier pipe. If possible, please delete the casing carrier pipe.
|
|
Corrective Action Required
The new valve at the 16 inch line should be specified as a gate valve.
|
|
Corrective Action Required
Off-site easements may be required across "Lakewood Business Center on I-470 Plat Q Lot 29A." Have you researched this area to determine what easements are needed to install the water main? This shall be required prior to formal approval of the plans.
|
|
|
Engineering Review
|
Corrections
|
07/14/2023
|
07/17/2023
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Why are there two (2) cover sheets for this project?
|
|
Corrective Action Required
Please rename the plans "Wilshire Hills 4th Plat - Water Line Extension" or equivalent language.
|
|
Corrective Action Required
Extend the proposed water main south along the proposed road and connect the 16-inch water main on the south side of Strother Road. An 8-inch main should be large enough if any new building has a similar fire flow requirement as the Phase 3 building.
|
|
Corrective Action Required
Add DR18 to the note in the profile to say “8” C-900 DR18 PVC.
|
|
Corrective Action Required
Add the vertical fitting bend angle to the profile, 45 degree bends are typical.
|
|
Corrective Action Required
Label the easement between Sta. 0+00 and Sta. 3+43. State 10’ proposed easement if that is the case.
|
|
Corrective Action Required
A trenching and backfill detail was missing from the plans. Please develop a trenching and backfill detail based on the Design and Construction Manual (the City does not currently have a standard detail for this), and ensure there is a minimum of 12 inches aggregate on top of pipe in accordance with newer rules from Jul. 2020.
|
|
|
Traffic Review
|
No Comments
|
07/14/2023
|
07/14/2023
|
|
Erin Ralovo
|
|
|