Planning Application Status

PL2023165




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2023165
Wilshire Hills 4th Plat - Public Water
Engineering Plan Review
Engineering Plan Review
Approved
06/23/2023
JEFFREY E SMITH INV CO LC
Locations
Contacts
JEFFREY E SMITH INV CO LC, Address:PO BOX 7688  
Brian Kimes, Address:JES Dev Co Inc, Phone:(573) 443-2021  
Matthew Kriete, Address:Engineering Surveys & Services, Phone:(573) 449-2646  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review No Comments 05/20/2024 05/20/2024
Gene Williams, P.E.
Engineering Review No Comments 03/05/2024 03/05/2024
Gene Williams, P.E.
Engineering Review Corrections 12/12/2023 12/12/2023
Gene Williams, P.E.
Traffic Review No Comments 12/12/2023 11/29/2023
Daniel Fernandez
Engineering Review Corrections 11/01/2023 11/02/2023
Gene Williams, P.E.
Corrective Action Required
10/27/2023

It does not appear there was any consideration to lowering the storm lines on the street and stormwater plans. This has an impact on the water main, as you are showing the installation of water main beneath storm lines which is not preferred and presents a long-term maintenance issue to Water Utilities. One of the storm lines is a private line, and is shown over the top of the public water main which is not allowed. Please review the street and stormwater plans, and determine how to eliminate the conflicts with the water and storm lines so the water main can be installed over the top of the storm line.
Corrective Action Required
10/27/2023

Additional fire hydrant(s) are appear to be warranted. Fire hydrants shall be provided every 500 feet on public water mains. Please evaluate and revise as appropriate. Ensure the fire hydrants are not located within 20 feet of a intersection curb return radius.
Corrective Action Required
11/02/2023

Deflecting the C900 pipe by 1 degree at each joint produces an approximate 1200 foot radius of curvature. It appears the deflection near station 5+00, 6+25, and 8+75 is less than 1200 feet radius of curvature, and therefore, bends should be installed to eliminate any stress in the line. Please evaluate the locations of bends, and revise as appropriate.
Corrective Action Required
11/02/2023

The steel casing pipe is not necessary at Strother Rd. if the 8 inch line can be bored without the casing carrier pipe. If possible, please delete the casing carrier pipe.
Corrective Action Required
11/02/2023

The new valve at the 16 inch line should be specified as a gate valve.
Corrective Action Required
11/02/2023

Off-site easements may be required across "Lakewood Business Center on I-470 Plat Q Lot 29A." Have you researched this area to determine what easements are needed to install the water main? This shall be required prior to formal approval of the plans.
Engineering Review Corrections 07/14/2023 07/17/2023
Gene Williams, P.E.
Corrective Action Required
07/17/2023

Why are there two (2) cover sheets for this project?
Corrective Action Required
07/17/2023

Please rename the plans "Wilshire Hills 4th Plat - Water Line Extension" or equivalent language.
Corrective Action Required
07/17/2023

Extend the proposed water main south along the proposed road and connect the 16-inch water main on the south side of Strother Road. An 8-inch main should be large enough if any new building has a similar fire flow requirement as the Phase 3 building.
Corrective Action Required
07/17/2023

Add DR18 to the note in the profile to say “8” C-900 DR18 PVC.
Corrective Action Required
07/17/2023

Add the vertical fitting bend angle to the profile, 45 degree bends are typical.
Corrective Action Required
07/17/2023

Label the easement between Sta. 0+00 and Sta. 3+43. State 10’ proposed easement if that is the case.
Corrective Action Required
07/17/2023

A trenching and backfill detail was missing from the plans. Please develop a trenching and backfill detail based on the Design and Construction Manual (the City does not currently have a standard detail for this), and ensure there is a minimum of 12 inches aggregate on top of pipe in accordance with newer rules from Jul. 2020.
Traffic Review No Comments 07/14/2023 07/14/2023
Erin Ralovo
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
07/14/2023 Plans 15925 Utility Extension Plan
07/17/2023 Letter DE-Comment Letter (Engineering Plans)
10/17/2023 Letter Response Letter_Rev0_2023172
10/17/2023 Plans 15925 WATER-PLANS 10-12-23-3
11/02/2023 Letter DE-Comment Letter (Engineering Plans)
11/28/2023 Letter Comment Response Letter 11-28-2023
11/28/2023 Plans 15925 COVER11-28-23
11/28/2023 Plans 15925 ROAD PLANS 11-28-23-2
11/28/2023 Plans 15925 SEWER PLANS 11-28-23-5
11/28/2023 Plans 15925 WATER-PLANS 11-28-23-3
11/28/2023 Plans 15925 GRADING 11-28-23-4
11/29/2023 Engineer Report/Study 15925 Hydraulic Report (Public Improvements) Revised 11-28-2023
12/12/2023 Email EMAIL COMMENTS
02/19/2024 Plans Water Line Extension Plans_PL2023165
02/19/2024 Letter Response Letter_PL2023165
03/05/2024 Email MDNR Letter_PL2023165
03/05/2024 Email Approval with Conditions_PL2023165
03/13/2024 Activity Document SIGNED MDNR CONCURRENCE_PL2023165
04/01/2024 Plans Complete Plan Set_PL2023165
05/13/2024 Engineers Estimate Sealed Cost Estimates_PL2023165
05/20/2024 Engineers Estimate Fee Worksheet WilshireHills Water Public_PL2023165
05/22/2024 Recorded Document Recorded Utility Easement_PL2023165
07/15/2024 Activity Document MDNR Water Line Approval_PL2023165
07/26/2024 Approved Plans Stamped Approved Plans PL2023165
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home