Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
12/02/2022
|
12/02/2022
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)). These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $4,252.13
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
Corrective Action Required
Review of the waiver is currently under review by the City Engineer. It is anticipated the waiver shall be approved. If not, it may be possible that detention shall be requred or other measures for the new improvements. If this occurs, a revision to the Final Development Plan shall be required.
|
|
|
Building Codes Review
|
No Comments
|
12/02/2022
|
12/01/2022
|
|
Joe Frogge
|
|
Miscellaneous Correction
Water service backflow to be inside building.
11/17/22 - still shown in yard on C500-B
11/23/22 - profile on C800-B still references exterior backflow and there is no information about meter.
|
|
Miscellaneous Correction
Specify size, type, and location of water meter.
11/17/22 - not found in plans
11/23/22 - Not found in plans
|
|
|
Traffic Review
|
No Comments
|
12/02/2022
|
11/23/2022
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
12/02/2022
|
11/23/2022
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Knox Locks
Corrective Action Required
IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official.
A Knox padlock sall be provided on the gate if not already there.
|
|
|
Planning Review
|
No Comments
|
12/02/2022
|
11/23/2022
|
|
Mike Weisenborn
|
|
|
Building Codes Review
|
Corrections
|
11/18/2022
|
11/21/2022
|
|
Joe Frogge
|
|
Miscellaneous Correction
Sanitary connection at manhole not allowed.
|
|
Miscellaneous Correction
Corrective Action Required
Water service backflow to be inside building.
11/17/22 - still shown in yard on C500-B
|
|
Miscellaneous Correction
Corrective Action Required
Specify size, type, and location of water meter.
11/17/22 - not found in plans
|
|
|
Engineering Review
|
Corrections
|
11/18/2022
|
11/18/2022
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
The Design Criteria Modification Request should be combined into one (1) single pdf file with: 1) the template form, 2) the summary discussion (sealed), and 3) exhibits. Please combine these into one (1) single pdf file.
|
|
Corrective Action Required
The 6 inch fire line appears to be connected to a private water line. Does this private water main connect to the public 12 inch main along Douglas St. with a backflow vault and backflow assembly? If not, a backflow vault and backflow assembly may be required near the 12 inch main near Douglas St. Please review and revise the drawings as necessary, as it appears there is no backflow vault near the 12 inch public main near Douglas St. If required by Water Utilities, this backflow vault and backflow assembly should be located outside of right of way and outside any public easements. Please see the Design and Construction Manual for more specific requirements for fire lines and backflow vaults, or contact me for further discussion.
|
|
Corrective Action Required
A 2 inch domestic service line is shown connecting to what appears to be a private water main. It also shows an in-line backflow vault and backflow preventor, which should be shown within the building and not outside the building. Backflow vaults installed outside a building are generally limited to private fire lines rather than domestic water service lines. Please show the location of the water meter, including sizing information, near the public water main along Douglas St. (i.e., the 12 inch line near Douglas St.). No backflow vault is desired or required for a domestic service line, so please eliminate the backflow vault from the domestic line. Please revise as appropriate.
|
|
Corrective Action Required
A two (2) inch domestic water service line is shown, but it is questionable whether this size line is appropriate for the building shown. Are you intending on installing a 2 inch meter? It would appear a 5/8 inch meter would be sufficient in this instance, and it would appear a 2 inch line would not be required. Please review and revise as appropriate.
|
|
Corrective Action Required
Please show the location of the water meter and the size of the water meter. It should be located near the public 12 inch line near Douglas St., and within right of way or an easement and in an area readily-accessible to Water Utilities staff. If no easement is located in the area of the water meter, a separately-recorded water line easement may be dedicated.
|
|
Corrective Action Required
It appears a water meter already exists near the private fire hydrant. Is there a reason why an additional water meter is being proposed? It may be possible to install a tee after the existing water meter, and utilize the existing water meter to service the new building. Please evaluate and revise as appropriate.
|
|
Corrective Action Required
There were references to W(R) on the plan sheets (i.e., Water Line "Record"). What does this term refer to? We are seeing no such water line in our records. Please evaluate and revise as appropriate.
|
|
Corrective Action Required
Due to the apparent confusion regarding water lines and fire lines, please contact me for further information. Alternatively, please consult the Design and Construction Manual "Water Mains" for further information regarding fire lines, domestic service lines, backflow vaults and backflow assemblies, etc.
|
|
Corrective Action Required
Please revise the cost estimate as appropriate after making the revisions to the plans.
|
|
|
Planning Review
|
No Comments
|
11/18/2022
|
11/17/2022
|
|
Hector Soto Jr.
|
|
|
Traffic Review
|
No Comments
|
11/18/2022
|
11/11/2022
|
|
Scott Ready
|
|
|
Fire Review
|
Approved with Conditions
|
11/18/2022
|
11/11/2022
|
|
Scott Ready
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Knox Locks
Corrective Action Required
IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official.
A Knox padlock sall be provided on the gate if not already there.
|
|
|
Engineering Review
|
Corrections
|
11/04/2022
|
11/04/2022
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
The waiver request is not a construction modification request, but rather, a design modification request. Please resubmit the correct form.
|
|
Corrective Action Required
Please include the project number on the design modification form. It is project number PL2022374.
|
|
Corrective Action Required
Please ensure the other waiver requests for Lee's Summit West High School and the main Lee's Summit High School include the correct form for the waiver. It is not a Construction Modification Request, but rather, a Design Criteria Modification Request. This form shall be sent separately.
|
|
Corrective Action Required
The plan package included Lee's Summit West High School improvements. Please eliminate these from the application package, and only include those pertaining to Lee's Summit North High School.
|
|
Corrective Action Required
Normally, a general overview sheet is included to show where the improvements are being proposed. I could not find such a general layout sheet. Please provide a general layout sheet of the campus.
|
|
Corrective Action Required
No further review was conducted, pending receipt of a plan package that can be reviewed from the perspective of: 1) one project (i.e., Lee's Summit North High School), and 2) an overview sheet showing where the proposed building is located in relation to other buildings. At present, I cannot determine where the building addition is being proposed with certainty.
|
|
|
Traffic Review
|
No Comments
|
11/04/2022
|
11/04/2022
|
|
Brad Cooley, P.E., RSPI
|
|
|
Fire Review
|
Approved with Conditions
|
11/04/2022
|
11/02/2022
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Knox Locks
Corrective Action Required
IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official.
A Knox padlock sall be provided on the gate if not already there.
|
|
|
Planning Review
|
Corrections
|
11/04/2022
|
11/01/2022
|
|
Hector Soto Jr.
|
|
Corrective Action Required
SITE DATA TABLE (Sheet C100-B).
- Correct the listed property zoning from PO to R-1 (Single-family Residential).
- Fill in the setback information for Front (30' per plat); Rear (30'); and side (30').
- Provide building square footage for the existing school; the proposed robotics building; and total (existing + proposed).
- List the number of existing classrooms; the number of proposed classrooms (from the addition); and total classrooms (existing + proposed).
- List the number of existing parking parking spaces and the number of required parking spaces. The number of required parking spaces for a high school is calculated at a rate of 6 spaces per total classrooms.
|
|
Corrective Action Required
ROOF-TOP UNITS. In order to comply with City ordinances, all RTUs shall be fully screened from view by raising building parapet heights at least equal to the height of the units being screened.
|
|
Corrective Action Required
EXTERIOR MATERIALS. Label the proposed exterior building material colors.
|
|
Corrective Action Required
LIGHTING. Identify which light fixture(s) listed on the fixture schedule on Sheet E700 will be used on the building exterior. All exterior lighting fixtures shall comply with UDO Sections 8.220 and 8.260.
|
|
|
Building Codes Review
|
Corrections
|
11/04/2022
|
10/26/2022
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Sanitary connection at manhole not allowed.
|
|
Miscellaneous Correction
Corrective Action Required
Water service backflow to be inside building.
|
|
Miscellaneous Correction
Corrective Action Required
Specify size, type, and location of water meter.
|
|
|