Summary
PL2020285
OSAGE 2ND PLAT - Grading & Site Disturbance
Engineering Plan Review
Engineering Plan Review
Approved
10/01/2020
CLAYTON PROPERTIES GROUP INC
Locations
Contacts
CLAYTON PROPERTIES GROUP INC, Address:120 SE 30TH ST  
OLSSON ASSOCIATES, Address:1301 BURLINGTON, SUITE 100, Phone:(816) 361-1171  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review No Comments 11/20/2020 11/13/2020
Loic Nguinguiri, E.I.
Engineering Review Corrections 11/11/2020 11/11/2020
Loic Nguinguiri, E.I.
Corrective Action Required
11/11/2020

As mentioned on page 5 of 12 of the Missouri DNR permit previously provided to the City through PRLD20200437, please include a brief physical description of the BMPs and BMPs installation/construction procedure(s) in the SWPPP for PL2020285. Make sure to also communicate how each will be maintained throughout the grading process.
Engineering Review Corrections 10/16/2020 10/14/2020
Loic Nguinguiri, E.I.
Corrective Action Required
10/14/2020

Please include a FEMA National Flood Hazard information note.
Corrective Action Required
10/14/2020

Please show location of all oil/gas wells, or indicate none are present, and cite the source.
Corrective Action Required
10/14/2020

Please show a vicinity map with surrounding streets labeled.
Corrective Action Required
10/14/2020

Please relocate overlapping A & C information on the grading sheet, for clarity purposes.
Corrective Action Required
10/14/2020

As shown in ESC-03, J-hooks are required within the ESC plan. Given the silt fence 100’ maximum runs for J-hooks, please locate the needed J-hooks on the plan.
Corrective Action Required
10/14/2020

Please revise the numbers of rock ditch check and curb inlet protection on to sheet C402.
Corrective Action Required
10/14/2020

Please revise staging chart activities to match the proposed work shown on the plan(s) for each project stage. Feel free to remove non-applicable items.
Corrective Action Required
10/14/2020

Please remove non-applicable items from the legend.
Corrective Action Required
10/14/2020

Please provide a SWPPP.
Corrective Action Required
10/14/2020

Please provide an Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet, listing cost estimates for the proposed work shown on the ESC set of plans only.
Corrective Action Required
10/14/2020

Comments on the Street, Stormwater, and Master Drainage Plan are being provided by separate cover. Please ensure the comments on the Street, Stormwater, and Master Drainage Plan are also reflected in the Mass Grading and Erosion and Sediment Control Plans for this project.
Hearings

There are no hearings for this planning application.

Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home