Summary
PL2020048
WOODLAND GLEN 3RD PLAT (WATER LINE)
Engineering Plan Review
Engineering Plan Review
Withdrawn
02/21/2020
ABP FUNDING LLC
This application has been added to the 2nd plat. Mike Weisenborn 04/02/2020 10:54 AM - voided the applicaiton as it was combined with 2nd plat
Locations
Contacts
ABP FUNDING LLC, Address:11040 OAKMONT ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Corrections 03/06/2020 03/06/2020
Sue Pyles, P.E.
Corrective Action Required
03/06/2020

Public infrastructure plans must match the associated plats for location of improvements. When resubmitting, please provide separate plan sets for Woodland Glen 2nd Plat and Woodland Glen 3rd Plat.
Corrective Action Required
03/06/2020

Sheet 1: • Please add the plat number to the project title on this sheet and the title block on all sheets. • Please revise the phone number to 816-969-1200 in General Note 13. • Please remove General Notes 13 & 14, they are not applicable. • Please remove the sanitary sewer portion of Utility Note 4, it is not allowed by MDNR. • Please remove the casing pipe item from the Summary of Quantities table. • Please include a Vicinity Map with nearby streets labeled.
Corrective Action Required
03/06/2020

Sheet 2: City records indicate the water main continues east from SW Winthrop Terrace on the north side of SW Heartwood Drive. Please show this main throughout the plan set.
Corrective Action Required
03/06/2020

Sheet 4: • Label all street names. • Label existing and proposed grade lines in the Profile view. • Include the storm sewer crossing near Sta. 0+20 in the Profile view. • City records indicate the water main continues east from SW Winthrop Terrace on the north side of SW Heartwood Drive. Therefore, Lot 56 can be served by the existing main and the extension to the plat boundary on the south side of SW Heartwood Drive is not required. Please eliminate Line 3.
Corrective Action Required
03/06/2020

Sheet 5: Please remove all standard details not required for this project.
Corrective Action Required
03/06/2020

General: • Submit an Engineer's Estimate of Probable Construction Costs. • Submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
02/21/2020 Letter Routing Sheet
03/06/2020 Letter DE-Comment Letter (Engineering Plans)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home