Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
08/05/2019
|
08/12/2019
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $30,527.94
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Planning Review
|
No Comments
|
08/05/2019
|
07/30/2019
|
|
Sue Pyles, P.E.
|
|
|
Engineering Review
|
Corrections
|
07/24/2019
|
07/29/2019
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Revise the Heavy Duty Pavement typical section to meet the City's requirements.
|
|
Corrective Action Required
Submit an Engineer's Estimate of Probable Construction Costs.
|
|
|
Planning Review
|
Corrections
|
07/24/2019
|
07/23/2019
|
|
Jennifer Thompson
|
|
Corrective Action Required
The pavement standards have not been met for the heavy duty asphalt. The 4-inch should be revised to 5-inch. Please refer to the UDO Article 8.620-for required thicknesses.
See engineering comment for further requests.
|
|
|
Fire Review
|
Approved with Conditions
|
07/24/2019
|
07/18/2019
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Building Codes Review
|
No Comments
|
07/24/2019
|
07/18/2019
|
|
Joe Frogge
|
|
|
Traffic Review
|
No Comments
|
07/24/2019
|
07/17/2019
|
|
Michael Park
|
|
|
Planning Review
|
Corrections
|
07/08/2019
|
07/08/2019
|
|
Dawn Bell
|
|
Corrective Action Required
Provide a note in the accessible sign detail referencing the R7-8 sign type. This sign has a white background and green border.
|
|
Corrective Action Required
The pavement standards have not been met. Please refer to the UDO Article 8.620-for required thicknesses. In addition, two types of pavement details (vehicle parking areas and drives and fire lanes and truck access) are required and needs to be references within the plan.
|
|
Corrective Action Required
Label the color of restrooms.
|
|
Corrective Action Required
The landscaping sizes have not been met. Please revise the caliper sizes to 3 inches and the required minimum height of evergreen trees is 8 feet.
|
|
|
Traffic Review
|
No Comments
|
07/08/2019
|
07/08/2019
|
|
Michael Park
|
|
|
|
|
Building Codes Review
|
Corrections
|
07/08/2019
|
07/05/2019
|
|
Joe Frogge
|
|
Corrective Action Required
Inadequate information to complete review.
Provide the following:
- All water and waste pipe materials.
- Size of water meter.
|
|
Corrective Action Required
2 water meters shown.
Action required: Eliminate one of the meters.
|
|
|
Engineering Review
|
Corrections
|
07/08/2019
|
07/05/2019
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
C-6: Site and Utility Plan
Terminate storm sewer line “X” from box 42A to a stub out in lieu of energy dissipation or rip rap outlet where P&R can continue drainage past play area.
|
|
Corrective Action Required
A-1 Restroom plan, section, elevation, detail
Install hose bib on exterior of restroom building for maintenance hook up
Call outs for asphalt color and type (match existing facilities)
Call outs for burnished block color (match existing facilities)
Widen plumbing chase from 2’-0”to 2’8”
Insulation type?
|
|
|
Engineering Review
|
Corrections
|
07/08/2019
|
07/05/2019
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
General:
• A portion of the park improvements, located in the NW corner of the park, are shown as a part of the public street plans. Please include all park related items in this plan set and remove from any other sets.
• Show and label easements throughout the plan set, including Landscape sheets.
|
|
Corrective Action Required
Sheet C-5: It appears that the trees to remain are incorrectly labeled. Please revise.
|
|
Corrective Action Required
Sheet C-6: Please clarify water service line alignment. See Building Codes review comments.
|
|
Corrective Action Required
Sheet C-7: The scale shown, 1”=40’, is incorrect. It appears the scale is 1”=30’, please revise.
|
|
Corrective Action Required
Sheet C-13: The Regular Duty Paving detail does not meet the requirements of UDO Section 8.620. Please revise the detail and do not refer to MoDOT requirements in the notes.
|
|
Corrective Action Required
Sheet L 2.01: Only ornamental tree varieties may be located within public easements. Verify that requirement is being met.
|
|
Corrective Action Required
Sheet’s C-5 & C-6: In addition to the label below the sheet number, please include “For Reference Only” in a central location on each sheet. It should be large enough to be noticed right away.
|
|
|
Fire Review
|
Approved with Conditions
|
07/08/2019
|
07/02/2019
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|