Review Type |
Outcome |
Est. Completion Date |
Completed |
Fire Review
|
Corrections
|
01/29/2019
|
02/01/2019
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Action required: Confirm the lane in the parking lot will be heavy duty concrete. What is shown is different than the detail.
|
|
|
Engineering Review
|
Corrections
|
12/12/2018
|
12/12/2018
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Submit:
• Engineer’s Estimate of Probable Construction Costs
• SWPPP
|
|
Corrective Action Required
Sheet 1: Revise the Sheet 4 name in the Index to match the name shown on Sheet 4.
|
|
Corrective Action Required
Sheet 3:
• Show the detention basin and label the 100-year WSE on this sheet and throughout the plan set.
• Revise Note #3 to refer to Development Engineering Inspections.
• The chain link fence is shown but the retaining wall shown in the Preliminary Development Plan is not included in this plan set. Remove the fence and any references to the wall on this sheet and throughout the plan set.
|
|
Corrective Action Required
Sheet 4:
• How will erosion be prevented at the trench drain outlet to the detention basin? Is the intent to have an end section at this location?
• Pipe must have a continuous slope from structure to structure. Please revise the detention basin outlet pipe accordingly.
• Show and label the overflow spillway length and location, along with provided freeboard to top of embankment. Verify the design volume can pass over the spillway in case of a clogged outlet.
• Include detention basin outlet structure information and construction details in the plan set.
• Revise the reference from “Highway Department Standards” to “City Standards” in the Grading and Drainage notes.
• Include storm sewer calculations and storm sewer profiles, including HGL, in the plan set.
|
|
Corrective Action Required
Sheet 6: Label areas for each Drainage Area.
|
|
Corrective Action Required
Sheet 7:
• Label areas for each Drainage Area.
• The leader for the 100-year WSE is not pointing to the correct location.
• Clarify the riprap information. Is the D50=6” or is that the riprap depth? Include both for proper construction.
|
|
Corrective Action Required
Sheet 8:
• The existing water main has been extended to the south property line of this lot. Relocate the fire hydrant to the end of the extended water main.
• Provide a utility easement meeting current requirements for the extended public water main from the public right-of-way through the fire hydrant. Show and label the easement throughout the plan set. Please submit the easement for review.
• A Backflow Prevention Device is required for the fire protection line. Since the building is more than 50’ from the public water main, it will be required to be in a vault placed according to Section 6900 of the Design and Construction manual.
• The line weights and number of lines overlapping make it very difficult to see the water lines connecting to the building. Please include an enlargement of the area on this sheet.
|
|
Corrective Action Required
Sheets 10-13:
• There is a detail for 6” x 18” concrete curb. Please clarify where is that curb is located.
• There is a grate inlet specified in the plans, but no standard detail for it.
• Is the junction box at the SE corner of the site existing or proposed? If proposed, include the standard detail.
• Remove the duplicate Curb & Gutter detail.
|
|
Corrective Action Required
Final Storm Water Drainage Report:
• More clearly define the discharge from the additional impervious area added by this project.
• Update the checklist inclusion item 21 to reflect the final submittal.
• Clarify the detention pond outlet, is there a structure proposed?
• The plans indicate the use of filtering devices prior to discharge into the detention basin as a water quality measure in lieu of 40-hour extended detention for the water quality storm. As this is not standard, please expand upon the use of these, providing the reason for their use and how they will meet the intent of Section 5600.
|
|
|
Traffic Review
|
No Comments
|
12/12/2018
|
12/11/2018
|
|
Michael Park
|
|
|
Planning Review
|
Corrections
|
12/12/2018
|
12/11/2018
|
|
Shannon McGuire
|
|
Corrective Action Required
Please label the width of the proposed ADA aisle.
|
|
Corrective Action Required
Please provide the location, height, intensity and type of outside lighting fixtures for buildings and parking lots.
|
|
Corrective Action Required
Please provide a photometric diagram indicating the foot candle levels throughout the site and at the property lines.
|
|
Corrective Action Required
Please provide the manufacturer’s specification sheets for proposed exterior lighting to include both parking lot pole mounted and wall mounted fixtures. The specification sheets shall indicate the exact fixture to be used.
|
|
Corrective Action Required
Is any ground mounted equipment being proposed? If so please provide the location, size, and type of material to be used in all screening of ground mounted mechanical equipment.
|
|
Corrective Action Required
Please provide the manufacturer’s specification sheets for proposed mechanical equipment to be used (ground and/or roof).
|
|
Corrective Action Required
Please provide the location, size, and type of material of all proposed monument or freestanding signs.
|
|
Corrective Action Required
Please provide elevations of all sides of proposed buildings including notation indicating building materials to be used on exteriors and roofs. Please include the location, size and materials to be used in all screening of rooftop mechanical equipment. A dashed line indicating the roof line and rooftop mechanical equipment shall be included.
|
|
Corrective Action Required
Please provide a floor plan showing dimensions and areas of all floors within proposed buildings and structures.
|
|
Corrective Action Required
The PDP plans that were approved showed a retaining wall. Has this been removed from the proposed project? If the wall has been removed, staff would like to see the chain-link fence on the north and east side of the building removed as well. If the applicant wished to keep the fence as proposed please provide details for it.
|
|
Corrective Action Required
The correct address for this project is 150 NE Tudor Rd. Please update the plans accordingly.
|
|
|
Building Codes Review
|
Corrections
|
12/12/2018
|
12/10/2018
|
|
Joe Frogge
|
|
Corrective Action Required
Provide blow-up or otherwise clarify domestic and fire entrances into building.
|
|
|
Fire Review
|
Corrections
|
|
12/03/2018
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Action required: Confirm the lane in the parking lot will be heavy duty concrete. What is shown is different than the detail.
|
|
|