Planning Application Status

PL2018203




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2018203
WOODLAND OAKS
Rezoning with no Preliminary Development Plan
Rezoning with no Preliminary Development Plan
Void
11/16/2018
HUFF CARL E & ALTHEA J
Locations
Contacts
HUFF CARL E & ALTHEA J, Address:656 SE BAYBERRY LN #101  
CONSTRUCTION ENGINEERING SERVICES, Address:16810 E 40 HWY, Phone:(816) 478-2323  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review Corrections 12/04/2018 11/30/2018
Hector Soto Jr.
Legal Description
Corrective Action Required
11/30/2018

Please submit an electronic copy of the legal description. Microsoft Word document or selectable text PDF are the preferred file formats. The legal description can be emailed to the planner's email address above.
Traffic Review No Comments 12/04/2018 11/29/2018
Michael Park
Engineering Review Corrections 12/04/2018 11/20/2018
Gene Williams, P.E.
Corrective Action Required
11/20/2018

A downstream receiving sanitary sewer analysis is required to be performed to determine whether the downstream system is capable of managing the increased sanitary sewer flows from this development. A “big picture” evaluation shall be done for the entire sanitary sewer system subwatershed. Evaluation of the system to the South Prairie Lee pump station will be required. These items were discussed during the February pre-application meeting.
Corrective Action Required
11/20/2018

Gravity lines shall be used to the extent practical, with the possibility that certain lots be served by individual grinder pumps and private lines, connected to a public gravity line. The submitted plan shows 9 of the 21 lots with no indication of how they will be sewered. There is a concern these lots may not be sewerable based on the limited information provided. A more detailed layout of the proposed sanitary sewer lines (with profile views) is required.
Corrective Action Required
11/20/2018

A sanitary sewer stub should be provided to the large acreage property to the west, in a suitable location based on topography.
Corrective Action Required
11/20/2018

Water line placement, even though District #13, would be reviewed by the City for general layout. No information has been provided for water service to any of the proposed lots.
Corrective Action Required
11/20/2018

The stormwater detention study that was submitted did not follow the current standard (i.e., we no longer use the pre-development peak flow rate versus post-development peak flow rate), and it did not include 40-hour extended detention for the water quality element. The report did not include any exhibits, figures or discussion of the pre-developed condition versus the post-developed condition. Without this information, detention criteria cannot be established to establish allowable release rates. A revised report shall be submitted. A brochure has been attached with general guidance for a stormwater report.
Fire Review No Comments 12/04/2018 11/16/2018
Jim Eden
Fees
Paid Fees Amount Paid Owing Date Paid
Rezoning (without Preliminary Development Plan) fee $700.00 $700.00 Paid 11/16/2018
Legal Notice Publishing Charge $165.00 $165.00 Paid 11/16/2018
Legal Notice Publishing Charge $165.00 $165.00 Paid 11/16/2018
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
11/16/2018 Receipt Receipt for transaction: 2018-007264
11/16/2018 Letter Routing Sheet
11/16/2018 Drawing Rezoning Map
12/03/2018 Letter Applicant Letter - Dev. Apps (DRCP)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: