Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
09/07/2018
|
09/07/2018
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 12 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact the Field Engineering Inspector at (816) 969-1200 at least 48 hours prior to the onset of construction.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $1,567.69 (which is calculated as 3% of the total infrastructure cost), must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
|
|
|
Planning Review
|
No Comments
|
09/07/2018
|
09/07/2018
|
|
Hector Soto Jr.
|
|
|
Building Codes Review
|
Approved with Conditions
|
09/07/2018
|
09/07/2018
|
|
Joe Frogge
|
|
Corrective Action Required
A construction permit will be required for the new lighting.
Action required: Comment is for informational purposes.
|
|
|
Traffic Review
|
No Comments
|
09/07/2018
|
09/06/2018
|
|
Michael Park
|
|
|
Fire Review
|
No Comments
|
09/07/2018
|
08/30/2018
|
|
Jim Eden
|
|
|
Planning Review
|
No Comments
|
08/10/2018
|
08/10/2018
|
|
Hector Soto Jr.
|
|
|
Building Codes Review
|
Approved with Conditions
|
08/10/2018
|
08/10/2018
|
|
Joe Frogge
|
|
Corrective Action Required
A building permit is required for all work associated with site lighting.
Action required: Comment is for informational purposes.
|
|
|
Traffic Review
|
No Comments
|
08/10/2018
|
08/09/2018
|
|
Michael Park
|
|
|
Fire Review
|
No Comments
|
08/10/2018
|
08/08/2018
|
|
Jim Eden
|
|
|
Engineering Review
|
Corrections
|
08/10/2018
|
08/08/2018
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Article 12 of the UDO requires 5.5 or 6.5 inches of asphalt and 6" of granular base course with either geogrid or 6" of stabilized subgrade. The plans meet the asphalt 6" granular base course requirements. However, the base course is shown on 6" compated subgrade in both pavement sections in the plans. This does not meet the UDO requirement of either geogrid or 6" stabilized subgrade. Please revise.
|
|
Corrective Action Required
Extend silt fence to the north and west to capture any sediment from the north parking area.
|
|
Corrective Action Required
Engineer’s Estimate of Probable Construction Costs:
• Items 6, 9, 10, 13 may be removed from the estimate as those items are not included in the fee calculation.
• Add an item for either geogrid or stabilized subgrade, with a quantity greater than the asphalt quantity to account for the extension beyond the curb and gutter.
|
|
|
Planning Review
|
Corrections
|
07/30/2018
|
07/30/2018
|
|
Victoria Nelson
|
|
Corrective Action Required
C.1. Legal Description. A legal description which accurately describes the limits of the property. The description that you show on the FDP is for the entire area. Please revise so that the description is addressing the Lot only.
|
|
Corrective Action Required
C.3. Floodplain.
Please cite and date the year of the floodplain description (FIRM Panel) that you have shown in the FDP.
|
|
Corrective Action Required
C.5. Streets. Please label the Right-of-Way and the private drive. Please show width of each.
|
|
Corrective Action Required
C.6. Sidewalks. Please label and show the width of the sidewalks along Rosemary and Blue Parkway.
|
|
Corrective Action Required
Property Boundary. Label the property line bearings and dimensions for the boundaries of Lot 1.
|
|
Corrective Action Required
C.7. Easements.
Please label the utility easements on sheets 104 and 105.
|
|
Corrective Action Required
C.20. Right-of-Way.
All existing adjacent public street right-of-ways with centerline location need to be labeled and have dimensions.
|
|
Corrective Action Required
C.25. Oil & Gas Wells.
Please add a note and show if there are any active or non-active oil & gas wells within the area and be sure to cite the source of the information. The Missouri Department of Natural Resources maintains a database of oil & gas wells that can be cited.
|
|
Corrective Action Required
Site Data Table needed on sheet 104.
Please include:
Lot Description-Lot 1...
Lot Area-
Existing Building Area-
Floor Area Ratio (FAR)-
Required Parking Spaces-
Existing Parking Spaces-
Proposed Parking Spaces-
Total Parking Spaces-
Existing Impervious Coverage-
Total Impervious Coverage (existing and propsed)
|
|
|
Engineering Review
|
Corrections
|
07/30/2018
|
07/25/2018
|
|
Sue Pyles, P.E.
|
|
Miscellaneous Correction
Corrective Action Required
Sheet 109: The pavement sections do not meet the requirements of Article 12 of the Unified Development Ordinance for pavement thickness and base requirements. Please revise.
|
|
Corrective Action Required
Submit an Engineer's Estimate of Probable Construction Costs.
|
|
|
Building Codes Review
|
Approved with Conditions
|
07/30/2018
|
07/24/2018
|
|
Joe Frogge
|
|
Corrective Action Required
A building permit is required for all work associated with site lighting.
Action required: Comment is for informational purposes.
|
|
|
Fire Review
|
No Comments
|
07/30/2018
|
07/24/2018
|
|
Jim Eden
|
|
|
Traffic Review
|
No Comments
|
07/30/2018
|
07/23/2018
|
|
Michael Park
|
|
|