Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
No Comments
|
01/17/2018
|
01/17/2018
|
|
Sue Pyles, P.E.
|
|
|
Engineering Review
|
Corrections
|
12/22/2017
|
12/27/2017
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Lots 82-83, 96-104, 107 on this plat and Future Lots 1-3 all require 12" Wyes, for a total of 15. Please revise the Engineer's Estimate of Probable Construction Costs accordingly. My previous review comment incorrectly indicated 12.
|
|
|
Engineering Review
|
Corrections
|
10/18/2017
|
10/18/2017
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Label the proposed easemnt along SW Pergola Park Dr, and also label the existing dashed lines in the same area.
|
|
Corrective Action Required
Sanitary Sewer Line 2 at approximate Sta 11+30 does not appear to have adequate horizontal separation of 5' with the adjacent storm sewer structure. Review and revise as needed.
|
|
Corrective Action Required
Doghouse MHs are not allowed. Please revise MH 1-5 accordingly. Revise the estimate, as well. Please excuse my oversight on the previous review.
|
|
Corrective Action Required
Revise the Engineer's Estimate of Probable Construction Costs to Either separate the 8" wyes (12) and 12" wyes (12) or combine to show 24 each. there are 3 existing service lines already in place, so there are 24 total new.
|
|
Corrective Action Required
Revise the Estimate of Quantities on Sheet C202 to match the revised Engineer's Estimate of Probable Construction Costs.
|
|
Corrective Action Required
Please revise the plans to match any revisions to the Final Plat, and coordinate with all public plans for consistency.
|
|
|
Engineering Review
|
Corrections
|
08/15/2017
|
08/10/2017
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Sheet C202: The Sanitary Line Removal quantity shown in the Estimate of Quantities does not appear to include the 8.48 LF at the west end of the removal. Please revise accordingly.
|
|
Corrective Action Required
Sheets 205 & 206: Please revise the first General Note to indicate "cut-in wye" connections for all laterals. Please note that there are laterals on both 8" and 12" mains.
|
|
Corrective Action Required
Sheets 205 & 206: Please verify the appropriate horizontal separation has been provided between the sanitary sewer lines and storm sewer lines & structures and between the sanitary sewer lines and water lines. If necessary, revise as needed to meet the requirements. Please note this does not refer to the area included in the previous email with Gene Williams.
|
|
Corrective Action Required
Please label all manholes shown. Label all existing manholes in the plan set with the City's MH number.
|
|
Corrective Action Required
Please revise the plans to match any revisions to the Final Plat, and coordinate with all public plans for consistency.
|
|
Corrective Action Required
Please verify that all easements are labeled throughout the plan set.
|
|
Corrective Action Required
Sheet C208: The details on this sheet are outdated. Please revise.
|
|
Corrective Action Required
The 12" PVC quantity included in the Engineer's Estimate of Probable Construction Costs appears incorrect. Please revise.
|
|
|