Summary
PL2016080
SUMMIT FAIR, PAD 5 - DICK'S
Commercial Final Development Plan
Commercial Final Development Plan
Approved
04/18/2016
RED LEES SUMMIT EAST LLC
Locations
Contacts
OLSSON , Address:7301 W 133RD ST STE 200, Phone:(913) 381-1170  
Not shown for privacy reasons.
RED LEES SUMMIT EAST LLC, Address:1 E WASHINGTON ST STE 300  
Reviews
Review Type Outcome Est. Completion Date Completed
Planning Review No Comments 07/12/2016 07/19/2016
Jennifer Thompson
Engineering Review Approved with Conditions 07/12/2016 07/19/2016
Karen Quackenbush
DE C&O #03 Eng & Insp Fees
Corrective Action Required
07/19/2016

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the engineering plans and prior to the issuance of any infrastructure permits or the start of construction (excluding land disturbance permit).
DE C&O #06 Land Disturbance
Corrective Action Required
07/19/2016

A Land Disturbance Permit shall be obtained from the Public Works Department if ground breaking will take place prior to the issuance of an infrastructure permit or prior to the approval of the Final Development Plan / Engineering Plans.
DE C&O #11 Pavement Thickness
Corrective Action Required
07/19/2016

Private pavement sections shall either follow Article 12 of the UDO or Table LS-2 or LS-3 of the Design & Construction Manual for pavement thickness and base requirements.
DE C&O #12 Cut & Fill
Corrective Action Required
07/19/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
DE Contact Field Eng. Inspector
Corrective Action Required
07/19/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
07/19/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Engineers Estimate
Corrective Action Required
07/19/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $56,911.19 (which is based on 3% of the total infrastructure cost plus a water test inspection fee) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
DE Future Repair Work
Corrective Action Required
07/19/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
07/19/2016

Submit a Land Disturbance Permit application and the required attachments to the Erosion Control Specialist prior to any land disturbance activities that are to occur prior to obtaining a building permit from the Codes Administration Department. Approval of these plans does not constitute approval of the erosion control plan. Contact Barton Reese at (816) 969-1800 for new land disturbance permitting details.
Fire Review Approved with Conditions 07/12/2016 07/12/2016
Jennifer Thompson
Code Statement
Corrective Action Required
07/05/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
Traffic Review No Comments 07/12/2016 07/12/2016
Michael Park
Fire Review Approved with Conditions 06/17/2016 06/16/2016
Jennifer Thompson
Code Statement
Corrective Action Required
06/10/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
Traffic Review Approved with Conditions 06/17/2016 06/16/2016
Michael Park
Corrective Action Required
06/16/2016

Discrepencies in the required and available parking tabulation and comparison between proposed and approved for the overall shopping center (and pad sites) will be addressed by Planning.
Corrective Action Required
06/16/2016

Internal site traffic circulation could be improved with better aligned access, avoidance of skewed intersections, parking lot connectivity and integration of preliminary plans previously approved (partially constructed). Any required changes to the site plan will be proposed by Planning in their comments.
Engineering Review Corrections 06/17/2016 06/14/2016
Karen Quackenbush
Corrective Action Required
06/14/2016

Sheet C003-Given the current location for the southern limit of removal of the existing gas line, it would appear from sheet C301 that the new gas line from the west connects at a point that is north of the removal limit. Please move the limit of the removal of the existing line to the north so that the new line has something to tie to.
Corrective Action Required
06/14/2016

Sheet C202-Please add CB2 in the plan note showing its NE location. Same for CB9. Also for CB8, it would appear that it should say CB7. Please add a plan note for MH#2. On SD-01 you show a station of 11+91. It is unclear what this station is refering to.
Corrective Action Required
06/14/2016

Sheet C202-In looking at the profile for SD-07, it would appear that JB2 could move to the east and line up with the outfall of CB8. Then the starting station for SD-07 could begin at CB8.
Corrective Action Required
06/14/2016

Sheet C203-For profiles SD-03 and SD-04, the graphics do not match the invert elevations on the callouts. Please update.
Corrective Action Required
06/14/2016

Sheet C203-Given the fact that you have plenty of cover over the utilities for SD-03, and the fact that SD-04 from CB2 to MH#1 is both flat and right on top of the existing 12" water line, consider raising SD-03 and the outfall of CB2.
Corrective Action Required
06/14/2016

Sheet C204-For SD-06, the graphics do not match the invert elevations on the callouts. Also, between JB3 and MH#2, the storm crosses the proposed 6" sanitary service pipe shown on C301. It would appear that SD-06 is in conflict with the sevice pipe. Please adjust and show the sanitary pipe in the profile. Also, there are some typos on the callouts for MH#1 and JB3.
Corrective Action Required
06/14/2016

Sheet C204- For SD-08 it would appear that the elevation of 1007.10 for the invert of CB9 should say OUT rather than IN. Also, from the profile of SD-06, it would appear that the INV. IN S elevation for MH#2 should be 1005.97 rather than 1005.77.
Corrective Action Required
06/14/2016

Sheet C204-For SD-10, it would appear that the wye inv should be 1005.28.
Corrective Action Required
06/14/2016

Sheet C301-For the new waterline on the south side of the site, you are showing 5.7 LF of pipe. It would appear that it should be approximately 82 LF.
Corrective Action Required
06/14/2016

Sheet C302-For the profile, it would appear that the horizontal scale should be 1"=30' and that the vertical scale should be 1"=3'. Also, it would appear that the graphic for the 8" PVC just past sta 2+00 is a bit low.
Corrective Action Required
06/14/2016

Sheet C302-Please verify the elevation of SD-06 in the profile. Insure that it matches the elevation on sheet C204.
Corrective Action Required
06/15/2016

An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. The Engineering Plan Review and Inspection Fee is based on this estimate, and calculated at 3% of the total. Items to include in the estimate are: 1) grading to establish proper drainage in accordance with the Master Drainage Plan, 2) grading for roads, 3) estimated removal and replacement of unsuitable subgrade, 4) compaction of road bed, including the areas one (1) foot beyond the back of curb, 5) subgrade stabilization or geogrid, including the area one (1) foot beyond the back of curb, 6) MoDOT Type 5 aggregate, including the area one (1) foot beyond the back of curb, 7) pavement, 8) curb and gutter, 9) underdrains, 10) materials associated with the retaining walls, 11) sidewalks, 12) ADA-accessible ramps, 13) storm lines and storm structures, 14) signs, 15) final restoration, including seeding, sodding, fertilizer, mulch, and topsoil, 16) sanitary sewer line, 17) manholes, 18) trench checks, 19) sanitary sewer laterals and wye connections, 20) water line, 21) valves, 22) fire hydrants, 23) tees, bends, and thrust blocks. Upon review and acceptance of the estimate, the Engineering Plan Review and Inspection Fee will be determined.
Planning Review Corrections 06/17/2016 06/13/2016
Jennifer Thompson
Corrective Action Required
06/13/2016

Provide additional fixture information for all proposed lighting (wall mounted and pole lighting), i.e. photos of the fixtures.
Corrective Action Required
06/13/2016

Provide the location, size and materials to be used in all screening of rooftop/ground mounted mechanical equipment. Provide a dashed line indicating the roof line and rooftop mechanical equipment. Provide the manufacture's specification sheets for all mechanical equipment.
Corrective Action Required
06/13/2016

Architectural drawings were not submitted, please provide.
Corrective Action Required
06/13/2016

Provide a detail of the trash enclosure/dock screen wall.
Corrective Action Required
06/13/2016

The minimum drive aisle widths (at the islands) have not been met. A 24-foot aisle space (excluding curb) shall be maintained. Please reduce the island widths to maintain this distance. This was noted on almost all islands within the proposed parking lot.
Fire Review Approved with Conditions 06/10/2016 06/09/2016
Jim Eden
Code Statement
Corrective Action Required
06/09/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
Engineering Review Corrections 05/02/2016 04/29/2016
Karen Quackenbush
Corrective Action Required
04/29/2016

Sheet C001 - On the east side of the improvements adjacent to NW Blue Pkwy, extend the limits of construction to include the proposed sanitary sewer contruction and the tie-in of the proposed storm sewer into the existing catch basin.
Corrective Action Required
04/29/2016

Sheet C003 - For the sanitary sewer demolition, we do not allow doghouse manholes. Reword note 21 to the following "Contractor to remove existing manhole and xx LF of existing sanitary sewer to allow for connection to new manhole as located on sheet C301." Please determine the length of 8" pvc to be removed.
Corrective Action Required
04/29/2016

Sheet C003 - It seems ok, but please verify that the construction of the new sanitary sewer manhole and 8" pvc as well as the demolition of the existing manhole and pvc stays out of the existing curb along NW Blue Pkwy. If necessary, show removal of existing curb.
Corrective Action Required
04/29/2016

Sheet C003 - Apply the same comment as previous for the sidewalk.
Corrective Action Required
04/29/2016

Sheet C003 - Show curb removal adjacent to the parking lot for the sanitary work.
Corrective Action Required
04/29/2016

Sheet C003 - Show curb removal adjacent to the parking lot for the storm sewer connection\removal at existing catch basin EX CB1.
Corrective Action Required
04/29/2016

Sheet C003 - Extend limits of demolition to accomodate comments 2 - 6.
Corrective Action Required
04/29/2016

Sheet C003 - On the south side of the existing parking lot, you have a water line removal note pointing at the line that has the lighter line weight. It does appear that a portion of the line should be removed\relocated a bit south, due to the fact that it is not located a minimum of 15' from the building. Please indicate the length of removal as necessary.
Corrective Action Required
04/29/2016

Sheet C003 - Please identify the NE for where the existing gas line removal ends on the south side of the site.
Corrective Action Required
04/29/2016

Sheet C101 - On the east side of the site, show limits of new curb and possible new sidewalk near the new SSMH and EX CB1.
Corrective Action Required
04/29/2016

Sheet C201 - It is not completely clear what is going on with the wall on the west side of the building. Please show a blowup of the plan view as well as a section view. In the section view show the sidewalks, wall, wall drain and building. Does the wall step back as show in the detail on sheet C502? How does the sidewalk area between the wall and the building drain?
Corrective Action Required
04/29/2016

Sheet C201 - It appears that the concrete loading dock on the east side of the building sits lower than the adjacent parking lot to the east. How is that area drained? Are you using the straigth trench drain detailed on sheet C501? If so, please add to drainage plan and profiles. It would appear that you could drain into CB9.
Corrective Action Required
04/29/2016

Sheet C202 - SD-04 from CB1 to EX CB1 is shown as 18". On sheet C203 it is shown as 24". Please rectify.
Corrective Action Required
04/29/2016

Sheet C203 - Please follow APWA 5604.5 Inverts and Pipes for the layout of storm sewer networks. There are multiple structures that do not meet the minimum drops.
Corrective Action Required
04/29/2016

Sheet C203 - Please show the 10-yr and 100-yr HGL elevations. If the 100-yr storm event surcharges the system, then there must be an overflow path identified.
Corrective Action Required
04/29/2016

Sheet C203 - In an effort to ensure that the existing system has adequate capacity, please show a small portion of the existing downstream pipe and HGL elevations where the proposed storm sewer ties in.
Corrective Action Required
04/29/2016

Sheet C301 - Where the existing water line goes under SD-04, show 10 feet of casing on both sides (total of 20 feet) per APWA 6901.D
Corrective Action Required
04/29/2016

Sheet C301 - It appears that there is about 11 feet between the south side of the building and the existing water line. Please show limits of new water line and proposed easement.
Corrective Action Required
04/29/2016

Sheet C301 - Show profile of sanitary sewer line. Verify that minimum seperation from building is 15 feet, from water line is 10 feet, that the maximum depth is 15 feet and that the proposed easement is twice as wide as the depth.
Corrective Action Required
04/29/2016

Sheet C301 - On the east side, show the new 8" pvc connecting to the new sanitary sewer manhole.
Corrective Action Required
04/29/2016

Sheet C401 - Please follow Table 12-5 Parking Lot and Paving of the UDO - Article 12. You can use the same pavement section for parking and access drives. Then you can make the heavy duty section for fire and delivery truck lanes.
Corrective Action Required
04/29/2016

Sheet C502 - It does not appear that you are using the double grate inlet anywhere. Consider removing from plan set. Also, if there are any other details you are not using on the other detail sheets, consider removing those.
Corrective Action Required
04/29/2016

Sheet C505 - Update the light and heavy duty pavement sections per comment on sheet C401.
Corrective Action Required
04/29/2016

Sheet C601 - Consider extending the sediment fence on the south side of the site further to the west. Also, on the east side of the site, the fence should "bump" out more to the east so that it's east of the new SSMH and around EX CB1.
Corrective Action Required
04/29/2016

Sheet C601 - Please add reference 6 to all applicable islands.
Planning Review Corrections 05/02/2016 04/29/2016
Jennifer Thompson
Corrective Action Required
04/29/2016

This new development is eliminating 65 or so parking spaces from the center and is not replacing them anywhere in the overall shopping center. We need updated information on the square footage of the center (including proposed building) and an updated parking space count for the center (excluding the spaces to be taken out by the proposed building) to make sure the development is compliant with the parking requirements of the original PDP.
Corrective Action Required
05/02/2016

On Sheet C002, revise comment #17 to reference the City of Lee's Summit, MO.
Corrective Action Required
05/02/2016

On Sheet C401 and C505, update the pavement sections according to the Unified Development Ordinance standards outlined in Table 12-5.
Corrective Action Required
05/02/2016

Provide a land use schedule and include the following: total floor area, land area, number of required and proposed parking spaces, impervious coverage, floor area ratio (FAR)
Corrective Action Required
05/02/2016

Provide additional fixture information for all proposed lighting (wall mounted and pole lighting), i.e. photos of the fixtures. Is any new lighting proposed or is it all existing? Please clarify. The UDO requires LED lighting for all pole mounted lighting.
Corrective Action Required
05/02/2016

A sign permit shall be obtained from the Planning and Codes Administration Department for each sign prior to installation.
Corrective Action Required
05/02/2016

The minor plat application shall be reviewed, approved and recorded with Jackson County Recorder of Deeds Office prior to the issuance of any building permit.
Corrective Action Required
05/02/2016

Architectural drawings were not submitted, please provide. Elevations of all sides of proposed buildings including notation indicating building materials to be used on exteriors and roofs.
Corrective Action Required
05/02/2016

Provide a detail of the trash enclosure/dock screen wall.
Corrective Action Required
05/02/2016

Where is the location of the retaining wall?
Corrective Action Required
05/02/2016

Provide the location, size and materials to be used in all screening of rooftop/ground mounted mechanical equipment. Provide a dashed line indicating the roof line and rooftop mechanical equipment. Provide the manufacture's specification sheets for all mechanical equipment.
Corrective Action Required
05/02/2016

Provide a accessible sign detail for the accessible spaces. Please reference the R7-8 model type within the detail.
Corrective Action Required
05/02/2016

Please note the vertical curbing will be CG-1 concrete curbing as is required around all parking areas and access drives. Also, provide a detail of the CG-1 curbing.
Corrective Action Required
05/02/2016

The aisle width is not met for the easternmost drive aisle. A minimum of 24-feet is needed. Also provide an additional drive aisle dimension at the island for this eastern drive aisle. Additionally, the first 3 north/south parking aisles on the north side of the building don't meet the minimum 24' pavement width (Excluding curb and gutter) between the landscape islands on both ends of the aisles. Also, the new east/west drive aisle at the north end of this site doesn't meet this same 24' pavement requirement.
Corrective Action Required
05/02/2016

Provide the surrounding property information.
Corrective Action Required
05/02/2016

Provide a statement indicating whether oil and/or gas wells are within the subject property.
Corrective Action Required
05/02/2016

Label the right-of way widths for all public streets.
Corrective Action Required
05/02/2016

Provide the dimensions of all required building and parking setbacks.
Corrective Action Required
05/03/2016

Label the existing and proposed easements. Label the platted build lines.
Corrective Action Required
05/03/2016

All head-to-head parking spaces are shown as 18-foot deep. These spaces shall be a minimum 19-foot deep.
Traffic Review Corrections 05/02/2016 04/28/2016
Michael Park
Corrective Action Required
04/28/2016

Has an assessment of parking for the site and the overall center been completed and compared to the UDO requirements and those conditions approved with the PDP? It appears that the project will eliminate about 65 existing parking spaces (not replaced).
Corrective Action Required
04/28/2016

Could the parking and building locations be adjusted to improve traffic flow, shared parking, etc. within the overall center operation (e.g. place the building closer to Blue Parkway)? The changes in parking and driveways may be detrimental to the overall shared parking supply and access to parking. The change in access that is inconsistent with existing conditions and approved plan is mis-aligned with other adjacent driveways and closer to the shopping center principle drive aisle intersection that appears in conflict. There is also an additional access proposed from the main center drive aisle that may generate conflict within the shopping center operations. Additional review and design alternatives should be considered.
Fire Review Approved with Conditions 05/02/2016 04/27/2016
Jim Eden
Code Statement
Corrective Action Required
04/27/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
FDC
Corrective Action Required
04/27/2016

IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official. Action required: Show the location of the FDC.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 04/18/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
04/18/2016 Receipt Receipt for transaction: 2016-001196
04/18/2016 Letter Routing Sheet - FDP
05/10/2016 Letter Applicant Letter - FDP (DFDP)
07/05/2016 Letter Resubmittal Routing Sheet - FDP
07/12/2016 Letter Applicant Letter - FDP (DFDP)
07/12/2016 Letter Applicant Letter - FDP (DFDP)
07/22/2016 Summit Fair Pad 5 Fee Worksheet
01/15/2017 Letter Resubmittal Routing Sheet - FDP
01/15/2017 Letter Applicant Letter - FDP (DFDP)
09/09/2019 Summit Fair - Mixed Use & Apartments
09/09/2019 Summit Fair
09/09/2019 Dicks
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home