Summary
PL2016022
TWIN LAKES INSURANCE
Commercial Final Development Plan
Commercial Final Development Plan
Approved
02/16/2016
MARION RIDGE SAFETY STORAGE LLC
Locations
Contacts
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
MARION RIDGE SAFETY STORAGE LLC, Address:1101 C NW PAMELA BLVD  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Review Approved with Conditions 08/29/2016 08/22/2016
Jim Eden
Code Statement
Corrective Action Required
08/22/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only.
Imposed Loads
Corrective Action Required
08/22/2016

IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities. For information only- The design of the concrete fire lanes shall carry the required load of 75,000-pounds.
Traffic Review No Comments 07/20/2016 07/22/2016
Jennifer Thompson
Fire Review Approved with Conditions 07/20/2016 07/22/2016
Jennifer Thompson
Code Statement
Corrective Action Required
07/20/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only.
Planning Review Corrections 07/20/2060 07/22/2016
Jennifer Thompson
Corrective Action Required
07/22/2016

Are any changes to the electrical plan proposed that are related to the revision of the parkign layout? If so, provide two copies of the revised plans and send to Joe Frogge, Commercial Plans Examiner.
Corrective Action Required
07/22/2016

Provide a revised photometric plan illustrating the new parking lot layout and light pole configuration.
Engineering Review Approved with Conditions 07/20/2016 07/20/2016
Gene Williams, P.E.
Planning Review Approved with Conditions 04/18/2016 04/18/2016
Jennifer Thompson
Corrective Action Required
04/18/2016

The cross access easement covering the shared driveway shall be recorded and a copy returned to the City prior to the issuance of a building permit.
Corrective Action Required
04/18/2016

An approved Form 7460 shall be completed and returned to the City prior to the issuance of a building permit.
Corrective Action Required
04/18/2016

A total of 8 trees are required to meet the open yard tree requirement. Seven trees are shown, one additional open yard tree shall be required.
Engineering Review Approved with Conditions 04/18/2016 04/18/2016
Gene Williams, P.E.
DE Engineers Estimate
Corrective Action Required
04/11/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $9,016.66 (which is based on 3% of the total infrastructure cost plus a water test inspection fee) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
DE Contact Field Eng. Inspector
Corrective Action Required
04/11/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
04/11/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Future Repair Work
Corrective Action Required
04/11/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
04/11/2016

If ground breaking is scheduled to take place rior to the issuance of a building permit, please submit a Land Disturbance Permit application and the required attachments to the Erosion Control pecialist.
DE C&O #12 Cut & Fill
Corrective Action Required
04/11/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Fire Review Approved with Conditions 04/18/2016 04/13/2016
Jim Eden
Code Statement
Corrective Action Required
04/11/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only.
Traffic Review No Comments 04/18/2016 04/11/2016
Michael Park
Planning Review Corrections 04/07/2016 04/07/2016
Jennifer Thompson
Corrective Action Required
04/07/2016

A cross access easement covering the shared driveway shall be required. Please provide the exhibit and language for staff review. This will need to be recorded prior to the issuance of a building permit.
Corrective Action Required
04/07/2016

Sign permits shall be obtained prior to any installation of any signs through the department of Planning and Codes Administration.
Corrective Action Required
04/07/2016

The plans are not signed and sealed. All reports and plans shall be signed and sealed by a Professional Engineer registered in the State of Missouri.
Corrective Action Required
04/07/2016

For any property within two miles of the airport, a Form 7460 shall be completed and submitted to the FAA, and comments received back prior to any construction.
Corrective Action Required
04/07/2016

Provide the manufacturer's specification sheets for proposed exterior lighting to include both parking lot pole mounted and wall mounted fixtures. The specification sheets shall indicate the exact fixture to be sued.
Corrective Action Required
04/07/2016

Please clarify if the parking lot pole lighting is 20-feet in height or is the base increase this height? Also, more clearly label the wattage for the pole lighting.
Corrective Action Required
04/07/2016

Is any wall-pak lighting proposed? Please provide this information.
Corrective Action Required
04/07/2016

The site data table indicates the full-build out will total 14,500 sq. ft. However the building addition is labeled as 1,200 sq.ft. When this is added to the phase 1 sq.ftg. the total is 13,600 sq. ft., please clarify.
Corrective Action Required
04/07/2016

If ground mounted units are not proposed, than what kind of mechanical units are proposed?
Corrective Action Required
04/07/2016

Provide a brief statement indicating the longevity of the foam build outs and the stucco finish system on felt.
Corrective Action Required
04/07/2016

Staff is fine with using the existing trees along I-470 to meet the landscaping requirements for this street frontage. However, if and or when these trees die or are removed, additional landscaping shall be required meeting Article 14 of the UDO.
Corrective Action Required
04/07/2016

The open yard tree requirement has not been met. The calculation for this doesn't include the square footage for the parking area. A total of 8 trees are required to meet this requirement. Four trees are shown. Please revise the table and label four more trees.
Engineering Review Approved with Conditions 04/07/2016 04/07/2016
Gene Williams, P.E.
DE Engineers Estimate
Corrective Action Required
04/07/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $9,016.66 (which is based on 3% of the total infrastructure cost plus a water test inspection fee) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department
DE Contact Field Eng. Inspector
Corrective Action Required
04/07/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
04/07/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Future Repair Work
Corrective Action Required
04/07/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
04/07/2016

If ground breaking is scheduled to take place rior to the issuance of a building permit, please submit a Land Disturbance Permit application and the required attachments to the Erosion Control pecialist.
DE C&O #12 Cut & Fill
Corrective Action Required
04/07/2016

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Traffic Review No Comments 04/07/2016 04/06/2016
Michael Park
Fire Review Approved with Conditions 04/07/2016 04/04/2016
Jim Eden
Code Statement
Corrective Action Required
03/31/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only.
Dumpsters
Resolved
04/04/2016

IFC 304.3.3- Dumpsters and containers with an individual capacity of 1.5 cubic yards [40.5 cubic feet (1.15 m3)] or more shall not be stored in buildings or placed within 5 feet (1524 mm) of combustible walls, openings or combustible roof eave lines. A dumpster enclosure was not shown. For information only.
Knox Locks
Resolved
04/04/2016

IFC 506.1 -Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official.506.1.1 Locks.An approved lock shall be installed on gates or similar barriers when required by the fire code official. A Knox box will be required above the FDC.
Imposed Loads
Resolved
04/04/2016

IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Engineering Review Corrections 03/01/2016 03/01/2016
Gene Williams, P.E.
Corrective Action Required
03/01/2016

A detail is required for the curb inlet to grated inlet conversion. Elevations will be required to ensure this grated inlet is located within the sump of the new driveway.
Corrective Action Required
03/01/2016

Please add a note specifying the removal of the "abandoned asphalt drive".
Corrective Action Required
03/01/2016

An 8" KCMMB approach is needed for the new commercial entrance. The extent should be at a minimum from the sawcut to the right of way line.
Corrective Action Required
03/01/2016

A profile view of the storm lines was not provided. Please provide profile views of the storm lines, along with the hydraulic grade line for the design storm.
Corrective Action Required
03/01/2016

Sidewalk and associated ADA-accessible ramps were not shown. Please ensure there are adequate details on the plans concerning ADA-accessible ramp and the required "flat spot" across the commercial entrance where the cross slope will not exceed 1.50% (2.00% maximum). The width should not be less than 4.0 feet (i.e., it can be reduced to 4 feet for the driveway only). Provide a note stating that truncated domes are not to be installed at the commercial entrance.
Corrective Action Required
03/01/2016

Sheet C.400: Please show the location of all existing easements. It appears the backflow vault is located within the limits of the easement.
Corrective Action Required
03/01/2016

A gate valve is needed just prior to the backflow vault.
Corrective Action Required
03/01/2016

Is the sanitary sewer lateral already existing? If not, please provide notes stating this will be a cut-in wye connection, and the new lateral must be bored beneath McBaine Dr.
Corrective Action Required
03/01/2016

Provide sufficient details concerning the grated inlet construction in relation to the ADA-accessible ramp. The top(s) of the grated inlet would need to be relatively flat, and then the driveway would need to rise to meet the ADA-accessible portion of the driveway. It may be necessary to include a cross section view of the commercial entrance, grated inlet, ADA-accessible ramp, and the how this ties into the proposed parking lot.
Corrective Action Required
03/01/2016

A typical section view of the parking lot paving must be provided in graphical format (i.e., a typical section view) as opposed to notes on the plans. Please see the new Unified Development Ordinance (UDO) Article 12 rules concerning pavement thickness, base, and subgrade stabilization/geogrid.
Corrective Action Required
03/01/2016

Will there be a separate irrigation meter? If so, please show the location.
Corrective Action Required
03/01/2016

Please specify a cut-in tee for the new private fire line.
Corrective Action Required
03/01/2016

An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. The Engineering Plan Review and Inspection Fee is based on this estimate, and calculated at 3% of the total, plus a per trip fee for the observation and collection of water samples. Items to include in the estimate are: 1) stormwater lines greater than 6 inches, 2) stormwater structures and retrofits, 3) water lines greater than 2 inches, 4) backflow vault and backflow assembly, 5) valves, tees, bends, elbows, 6) thrust blocks, straddle blocks, and tie downs, 7) valve boxes and covers, 8) sanitary sewer connection to the main, 9) boring beneath McBaine Dr., 10) removal of abandoned drive, 11) grading to establish proper drainage, 12) grading for parking lot, 13) estimated quantity of poor subgrade to remove and replace, 14) compaction of parking lot, 15) pavement, 16) aggregate for parking lot, including the area one (1) foot beyond the back of curb, 17) subgrade stablization or geogrid, including the area one (1) foot beyond the back of curb, 18) curb and gutter, 19) KCMMB drive approach, 20) sawcut for approach, 21) remvoval of existing curb and gutter for new entrance, 22) public sidewalk, 23) ADA-accessible ramps, 24) erosion and sediment control devices and measures, 25) final restoration, including sodding, seeding, fertilizer, mulch, and topsoil.
Planning Review Corrections 03/01/2016 02/26/2016
Jennifer Thompson
Corrective Action Required
02/26/2016

A cross access easement covering the shared driveway shall be required. Please provide the exhibit and language for staff review. This will need to be recorded pior to the issuance of a building permit.
Corrective Action Required
02/26/2016

A 5-foot sidewalk is required along the McBaine Drive frontage. Please label the plans accordingly.
Corrective Action Required
02/29/2016

Label the driveway width. A minimum 24-feet width (excluding curb & gutter) is required.
Corrective Action Required
02/29/2016

Provide the location, size and type of material of all proposed monument or freestanding signs. Sign permits shall be obtained prior to installation of any signs through the Department of Planning and Codes Administration. All proposed signs must comply with the sign requirements of Article 13 of the UDO.
Corrective Action Required
02/29/2016

Label the existing 15-foot utility easement along the McBaine frontage property line.
Corrective Action Required
02/29/2016

Provide a pavement detail for the parking lot. Please reference Article 12, Section 12.120, of the Unified Development Ordinance.
Corrective Action Required
03/01/2016

All reports and plans shall be signed and sealed by a Professional Engineer registered in the State of Missouri.
Corrective Action Required
03/01/2016

Provide the location, height, intensity and type of outside lighting fixtures for buildings and parking lots.
Corrective Action Required
03/01/2016

Provide a photometric diagram indicating the foot candle levels throughout the site and at the property lines.
Corrective Action Required
03/01/2016

Provide the manufacturer's specification sheets for proposed exterior lighting to include both parking lot pole mounted and wall mounted fixtures. The specification sheets shall indicate the exact fixture to be used.
Corrective Action Required
03/01/2016

Provide the location of the ground mounted units. Also, indicate the location, size and type of material to b used in all screening of ground mounted mechanical equipment.
Corrective Action Required
03/01/2016

Provide an accessible sign detail and note the R7-8 sign type.
Corrective Action Required
03/01/2016

For any property within two miles of the airport, a Form 7460 shall be completed and submitted to the FAA, and comments received back prior to any construction.
Corrective Action Required
03/01/2016

On Sheet A200, revise the north elevation to wrap the stone veneer around the building, similar to how it's shown for the south elevation. The east elevation is missing vertical architectural features. Additional vertical detail is needed for the east elevation.
Corrective Action Required
03/01/2016

Revise the Landscape worksheet on Sheet L.100 for the open yard shrubs and trees requirements. The calculation for this doesn't include the square footage for the parking area. The open yard shrub requirement is 16 shrubs required and the open yard tree requirement is 8 trees required. Parking area can only be omitted from this calculation for schools, churches and similar large public uses, not office/commercial.
Corrective Action Required
03/01/2016

Clarify the landscape symbol for the skyrocket juniper. It seems the symbol is being treated as a shrub on the landscape plan. Depending on what this symbol is representing will determine if landscape requirements are met. For example, if this symbol represents a tree then the open yard tree requirement has been met. However, then the parking lot screening would be deficient of shrubs.
Corrective Action Required
03/02/2016

Break out the site data table to show the building area, impervious area, floor area ratio and required parking spaces by phase 1 and full build out.
Corrective Action Required
03/02/2016

Street trees and shrubs are required along the I-470 frontage. Please include this information in the landscape worksheet and revise the landscape sheet accordingly.
Corrective Action Required
03/02/2016

Provide a CG-1 curb detail and indicate the proposed curbing for the site will be the CG-1 curbing.
Traffic Review Corrections 03/01/2016 02/23/2016
Michael Park
Corrective Action Required
02/23/2016

Add sidewalk along the adjacent roadway.
Fire Review Approved with Conditions 03/01/2016 02/23/2016
Jim Eden
Code Statement
Corrective Action Required
02/23/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
Dumpsters
Corrective Action Required
02/23/2016

IFC 304.3.3- Dumpsters and containers with an individual capacity of 1.5 cubic yards [40.5 cubic feet (1.15 m3)] or more shall not be stored in buildings or placed within 5 feet (1524 mm) of combustible walls, openings or combustible roof eave lines. A dumpster enclosure was not shown. For information only.
Knox Locks
Corrective Action Required
02/23/2016

IFC 506.1 -Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official.506.1.1 Locks.An approved lock shall be installed on gates or similar barriers when required by the fire code official. A Knox box will be required above the FDC.
Imposed Loads
Corrective Action Required
02/23/2016

IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 02/16/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
02/16/2016 Receipt Receipt for transaction: 2016-000375
02/16/2016 Letter Routing Sheet - FDP
03/06/2016 Letter Applicant Letter - FDP (DFDP)
03/31/2016 Letter Resubmittal Routing Sheet - FDP
04/07/2016 Fee WorksheetUpdated
04/07/2016 Letter Applicant Letter - FDP (DFDP)
04/11/2016 Letter Resubmittal Routing Sheet - FDP
04/28/2016 Letter Applicant Letter - FDP (DFDP)
07/13/2016 Letter Resubmittal Routing Sheet - FDP
08/17/2016 Letter Resubmittal Routing Sheet - FDP
08/29/2016 C.101 - ADA DETAIL
08/29/2016 C.001 - COVER
08/29/2016 C.202 - DRAINAGE AREAS
08/29/2016 C.050 - ESC PHASE 1 PLAN
08/29/2016 C.051 - ESC PHASE 2 PLAN
08/29/2016 C.052 - ESC PHASE 3 PLAN
08/29/2016 C.200 - GRADING PLAN
08/29/2016 L.100 - LANDSCAPE PLAN
08/29/2016 C.100 - SITE PLAN
08/29/2016 C.201 - SPOT ELEVATIONS
08/29/2016 C.300 - STORM PLAN GENERAL LAYOUT
08/29/2016 C.301 - STORM PLAN PLAN AND PROFILE
01/16/2017 Letter Applicant Letter - FDP (DFDP)
01/16/2017 Letter Applicant Letter - FDP (DFDP)
10/30/2017 Activity Document Fee WorksheetUpdated
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home