Review Type |
Outcome |
Est. Completion Date |
Completed |
Traffic Review
|
Approved with Conditions
|
05/05/2015
|
05/07/2015
|
|
Michael Park
|
|
Corrective Action Required
Submit Revised Traffic Study that addresses prior comments.
|
|
Corrective Action Required
See TIA for conditions of approval
|
|
|
Planning Review
|
No Comments
|
05/05/2015
|
05/05/2015
|
|
Christina Stanton
|
|
|
Engineering Review
|
Approved with Conditions
|
05/05/2015
|
05/05/2015
|
|
Gene Williams, P.E.
|
|
DE C&O #01 Eng Plans – FDP/PDP
Corrective Action Required
All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with any Final Development Plan. Engineering plans for public infrastructure shall be submitted under a separate submittal package. All public infrastructure must be substantially complete, prior to the issuance of any certificates of occupancy.
|
|
DE C&O #03 Eng & Insp Fees
Corrective Action Required
All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the engineering plans, and prior to the approval of the Final Development Plan, and prior to the issuance of any infrastructure permits or the start of construction (excluding land disturbance permit).
|
|
DE C&O #06 Land Disturbance
Corrective Action Required
A Land Disturbance Permit shall be obtained from the Public Works Department prior to any ground-breaking activities on the site.
|
|
DE C&O #12 Cut & Fill
Corrective Action Required
Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
|
|
Corrective Action Required
Additional fire hydrants shall be required to meet the 300 foot rule to any point on a building. In addition, the maximum distance between any two fire hydrants shall not exceed 500 feet, and fire hydrants on adjacent streets cannot be used to satisfy the 500 foot maximum distance requirement. Please refer to additional comments provided by the Fire Department.
|
|
Corrective Action Required
Applicant will be required to provide documentation that the United States Army Corps of Engineers (USACE) requirements, if applicable, have been met for the project.
|
|
Corrective Action Required
With the exception of street crossings and the reinforced box culvert shown on the plan, all other storm sewer systems shown within the interior of the lots shall be considered private.
|
|
|
Fire Review
|
Corrections
|
04/03/2015
|
04/23/2015
|
|
Jim Eden
|
|
Hydrants
Corrective Action Required
IFC 507.5.1- Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Additional hydrants are needed to meet the 300' rule for LOT 6, and several of the other buildings. The spacing of hydrants shall be in accordance with IFC Appendix C Table 105.1 .
Hydrants are also needed along Ward.Where streets are provided with median dividers which cannot be crossed by fire fighters pulling hose lines, or where arterial streets are provided with four or more traffic lanes and have a traffic count of more than 30,000 vehicles per day, hydrant spacing shall average 500 feet on each side of the street and be arranged on an alternating basis up to a fire-flow requirement of 7,000 gallons per minute and 400 feet for higher fire-flow requirements.
Provide a revised hydrant plan.
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
|
|
FDC
Corrective Action Required
IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
Provide the proposed location of the FDC and a fire hydrant on building being provided with automatic sprinkler systems.
|
|
Misc.
Corrective Action Required
D105.1 Where required.
Where the vertical distance between the grade plane and the highest roof surface exceeds 30 feet (9144 mm), approved aerial fire apparatus access roads shall be provided. For purposes of this section, the highest roof surface shall be determined by measurement to the eave of a pitched roof, the intersection of the roof to the exterior wall, or the top of parapet walls, whichever is greater.
D105.2 Width.
Aerial fire apparatus access roads shall have a minimum unobstructed width of 26 feet (7925 mm), exclusive of shoulders, in the immediate vicinity of the building or portion thereof.
D105.3 Proximity to building.
At least one of the required access routes meeting this condition shall be located within a minimum of 15 feet (4572 mm) and a maximum of 30 feet (9144 mm) from the building, and shall be positioned parallel to one entire side of the building. The side of the building on which the aerial fire apparatus access road is positioned shall be approved by the fire code official.
Provide 26 foot fire lanes where appropriate.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3- Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
|
|
|
Traffic Review
|
Corrections
|
04/03/2015
|
04/03/2015
|
|
Michael Park
|
|
Corrective Action Required
Consider a driveway connection between Building 7 (east side parking lot) and Lot 6 (parking lot/drive aisle).
|
|
Corrective Action Required
Access easements needed along the north/west property line/shared driveway and shared private driveways throughout the development.
|
|
Corrective Action Required
A brief review of the traffic study did not reveal any issues or comments that would impact the PDP. A more detailed review of the traffic study will be completed and associated comments coordinated directly with the applicant and their engineer(s) in the next couple weeks. PDP related off-site improvements and phasing of such improvements will be listed in the staff recommendations for PDP approval and require an agreement.
|
|
|
Engineering Review
|
Corrections
|
04/03/2015
|
04/03/2015
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
The "Sewer Demand Report" dated March 19, 2015 does not appear to follow the City of Lee's Summit criteria for a sanitary sewer analysis. For instance, peak inflow was assumed to be zero. The Design and Construction Manual does not allow for this assumption to be made. In addition, it did not appear that the downstream connection was taken into account, including the hydraulic grade line at the connection point. The hydraulic grade line of the existing downstream system into which the sewer discharges should be taken into account, and calculations should be shown which demonstrate a freely-flowing system with sanitary sewer flows below the top of the pipe, and the hydraulic grade line at the connection point being above the hydraulic grade line of the receiving sewer.
|
|
Corrective Action Required
The "peaking factor" used in the "Sewer Demand Report" dated March 19, 2015 is not necessary. Please refer to comment #1, and use the peak inflow calculation rather than a "peaking factor".
|
|
Corrective Action Required
It appears that considerable amounts of fill will be placed on the northwest portion of the project site. Will the area listed as "Future Development" also include fill? The reason this question is asked are the existence of two (2) access points to the "Future Development", and it is unclear how this will be achieved with the placement of fill in this area.
|
|
Corrective Action Required
Landscape Plan: Please show the locatons of all existing and proposed City-owned utilities (i.e., water, sanitary sewer, and stormwater), and the location of all private water lines, private fire lines, private sanitary sewers, private storm sewers and structures, and private fire line backflow vaults. City-owned utilities should be a minimum of five (5) feet from any tree, as measured from the mature tree trunk to the outside of the City-owned utility (i.e., outside of the pipe, manhole, or structure).
|
|
Corrective Action Required
Please add a note to the Preliminary Development Plan stating that all pavement thickness and base will follow the Unified Development Ordinance (UDO) Article 12.
|
|
Corrective Action Required
Utility Plan C102: Please label the private storm lines (i.e., all interior storm lines) as "private". This would include the extended box culvert.
|
|
Corrective Action Required
Utility Plan C102: Please show and label the locations of all proposed easements.
|
|
Corrective Action Required
Utility Plan C102: A 12" sanitary sewer line is shown in the northeast portion of the site. It is unclear how this new sanitary sewer line can be installed and still meet the maximum fifteen (15) feet depth of cover requirement contained within the Design and Construction Manual. This is based on a review of the grading plan.
|
|
Corrective Action Required
Utility Plan C102: Please move the private box culvert outside of the right of way and easements, with the exception of street crossings.
|
|
Corrective Action Required
Please be aware of the following requirements concerning sanitary sewer lines: 1) maximum depth of fifteen (15) feet as measured from the top of rim to the top of pipe, and 2) minimum of fifteen (15) feet distance from any proposed permanent building, structure, or retaining wall. It appears these requirements will not be met.
|
|
Corrective Action Required
Utility Plan C102: It appears the public sanitary sewer should be extended to the northwest plat boundary in accordance with the Design and Construction Manual.
|
|
Corrective Action Required
Utility Plan C102: Please be aware that the maximum depth of cover for water lines is seven (7) feet, and the minimum depth of cover is 42 inches.
|
|
Corrective Action Required
Please be aware that retaining walls, if proposed, cannot cross easements.
|
|
Corrective Action Required
Utility Plan C102: A 12" sanitary sewer main is shown extending to Main St along the north property line of Lot 5. Is the intent of this public main to connect the existing sanitary sewer from the west? If so, please indicate on the plan sheet, and please ensure that the maximum depth of cover is not exceeded. There appears to be considerable amounts of fill placed in the vicinity of this location, and it is possible that the proposed sanitary sewer will exceed the maximum depth of cover.
|
|
Corrective Action Required
Please be aware that separate engineering plans will be required for all public improvements, including street, stormwater, sanitary sewers, waterlines, and erosion and sediment control.
|
|
Corrective Action Required
Please be aware that all United States Army Corps of Engineers (USACE) requirements, if any, should be met for the project. Approvals from the USACE should be forwarded to the City.
|
|
Corrective Action Required
Please show sidewalk along the east side of Main Street.
|
|
|
Fire Review
|
Corrections
|
04/03/2015
|
03/27/2015
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
For information only.
|
|
Hydrants
Corrective Action Required
IFC 507.5.1- Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Additional hydrants are needed to meet the 300' rule for the majority of the buildings. Hydrants are also needed along Ward.
IFC App C Table 105.1 .
Where streets are provided with median dividers which cannot be crossed by fire fighters pulling hose lines, or where arterial streets are provided with four or more traffic lanes and have a traffic count of more than 30,000 vehicles per day, hydrant spacing shall average 500 feet on each side of the street and be arranged on an alternating basis up to a fire-flow requirement of 7,000 gallons per minute and 400 feet for higher fire-flow requirements.
\
Where new water mains are extended along streets where hydrants are not needed for protection of structures or similar fire problems, fire hydrants shall be provided at spacing not to exceed 1,000 feet to provide for transportation hazards.
Provide a revised hydrant plan.
|
|
FDC
Corrective Action Required
IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
Show the location of the fire main, FDC, and additional supply hydrant (if needed) for the buildings required to be provided with an automatic sprinkler system by IFC 903.2 and local amendments.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3- Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
For information only
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
For information only.
|
|
|
Planning Review
|
Corrections
|
04/03/2015
|
03/27/2015
|
|
Christina Stanton
|
|
Legal Description
Corrective Action Required
Please submit an electronic copy of the legal description. Microsoft Word document or selectable text PDF are the preferred file formats. The legal description can be emailed to the planner's email address above.
|
|
Corrective Action Required
Add the distances and bearings from the legal description to the map.
|
|
Corrective Action Required
Lots 5 and 6 are flipped on the Plat.
|
|
Corrective Action Required
Staff recommends adjusting the lot line between lots 4 & 5 and maintaining shared access for these lots from both Ward Road and Innovation Drive.
|
|
Corrective Action Required
Impervious Coverage. The impervious coverage references the Stormwater Report, which mentions a 68% limitation. Is the limitation overall or on a lot-by-lot basis?
|
|
Corrective Action Required
Label the dimensions of the setback lines.
|
|
Corrective Action Required
Parking--General. It appears that the parking counts need to be re-reviewed. While most lots and buildings meet the required parking the only areas I counted the same (or nearly the same) as the proposed number was for Lot 5, Building 6 and Lot 3, Building 2. Lot 4, Building 4 appears to be deficient of the required parking.
|
|
Corrective Action Required
Parking--Hospitality. Is is intended that the hotel/motel will not have a restaurant or lounge open to the public? Under the current parking counts, if this were to change additional parking would be required or a modification would be needed.
|
|
Corrective Action Required
Parking--Educational. Where does the 3/1,000 for educational come from? The Unified Development Ordinance (UDO) has 10/classroom for college/university and 6/classroom for high school. Provide a parking study for an alternate parking plan to support the requested 3/1,000.
|
|
Corrective Action Required
Lighting. Add a note stating that all exterior lighting fixtures, their heights, and intensity shall meet the standards in the UDO. Detailed specifications can be provided at the final development plan (FDP).
|
|
Corrective Action Required
Monument Signs. Article 13 of the UDO allows for 1 freestanding sign per building. Monuments are permitted with up to 96 square feet of structure area; up to 72 of the 96 square feet may be sign face area; a maximum of 12 feet in height and 75 feet between freestanding signs. It would appear that the southernmost monument sign on Lot 4 needs a modification to allow for an additional sign and for being less than 75 feet from another freestanding sign. If any other modifications are needed more specific details will need to be provided
|
|
Corrective Action Required
Landscaping--Street Frontage Trees. Most lots do not appear to be meeting the minimum required street frontage trees, but have excess open yard trees. Ordinance modifications need to be specific. Is a modification being sought to the number of street trees, where, and how many?
|
|
Corrective Action Required
Landscaping--Shrubs. Staff cannot ascertain whether the number of shrubs are met because individual shrubs are not identified on the map, only "shrub massing areas". Either provide a note stating that the number of shrubs shall meet the requirements of the UDO per Sections 14.090.A.3 and B.1 and 14.120.C, or revise the plans to show greater detail and request of modification if needed.
|
|
Corrective Action Required
Landscaping--Plant Size. The UDO requires a minimum of 3 inch caliper for deciduous trees. A modification is needed for 1 1/2 inch caliper ornamental trees.
|
|
Corrective Action Required
Previously Approved Waivers/Modifications. Four waivers/modifications were granted on the previously approved PDP, which was under the 715 zoning ordinance. (1) "A waiver...to allow a sidewalk on only one side of the beltroad where the hike and bike trail runs parallel to the road to link the park and pond areas." Sidewalk shall be required along the east side of Ward Road. Funds for the sidewalk could be escrowed in Phase I and the sidewalk constructed in Phase II, or the installation could be delayed to be installed at the same time as the expansion of Ward Road.
(2) "A waiver...to exclude required berming along the parking lots, where other methods of screening are proposed." Under the current zoning ordinance, the UDO, other methods of screening parking lots are allowed so this modification is no longer needed. (3) "A waiver...to the strict application of the number of shrubs and trees required by the Landscaping and Tree Protection sections of the ordinance, with compliance to the submitted 'Landscape Concept and Open Space Plan' required in lieu therof." Ordinance modifications need to be specific. Will a modification be needed for the number of shrubs? How many?
(4) "A waiver...to the parking stall size, to allow 9' x 18' instead of 9' x 19'." It does not appear that this modifcation is needed based on dimensions provided on Sheet AS100.
|
|
Corrective Action Required
Provide typicals of the other proposed buildings and a trash enclosure.
|
|
Corrective Action Required
Add a note stating that all curbing shall be CG-1 concrete curbing per Section 12.120.F.1.d of the UDO, and pavement shall be per Section 12.120.F.1.a and b.
|
|
Corrective Action Required
Add a note stating that all mechanical equipment shall be screened per the UDO.
|
|
|