| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Engineering Review
|
Approved with Conditions
|
02/25/2015
|
02/25/2015
|
|
|
Gene Williams, P.E.
|
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $1,948.16 (which is based on 3% of the total infrastructure cost plus two (2) water test inspection fees) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
|
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
|
|
|
DE Contact ROW Inspector
Corrective Action Required
Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
|
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
PW Submit Land Disturbance (DELETE)
Corrective Action Required
If land disturbance is desired prior to the issuance of a building permit, please submit a Land Disturbance Permit application and the required attachments to the Erosion Control Specialist. Contact Barton Reese at (816) 969-1800 for land disturbance permitting details.
|
|
|
|
|
Fire Review
|
Approved with Conditions
|
02/25/2015
|
02/24/2015
|
|
|
Jim Eden
|
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
|
|
|
|
|
Planning Review
|
No Comments
|
02/25/2015
|
02/23/2015
|
|
|
Christina Stanton
|
|
|
|
|
Traffic Review
|
No Comments
|
02/25/2015
|
02/20/2015
|
|
|
Michael Park
|
|
|
|
|
Fire Review
|
Approved with Conditions
|
02/09/2015
|
02/09/2015
|
|
|
Jim Eden
|
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code.
|
|
|
Misc.
The fuel for the generator was not specified. If it is diesel, provide tank specifications and amount of fuel to be stored.
|
|
|
|
|
Engineering Review
|
Corrections
|
02/09/2015
|
02/09/2015
|
|
|
Gene Williams, P.E.
|
|
|
Corrective Action Required
Please add a note stating that "...all construction shall follow the City of Lee's Summit Design and Construction Manual as adopted by Ordinance 5813. Where discrepancies exist between these plans and the Design and Construction Manual, the Design and Construction Manual shall prevail."
|
|
|
Corrective Action Required
Sheet C4: A cut-in tee is required for any water connection greater than 2" in diameter. It appears a 2 1/2 inch domestic line is called out, so a tee will need to be cut-in at the location shown.
|
|
|
Corrective Action Required
Sheet C4: Is the proposed 2" water meter within an easement? Please show the location of the easement since public water meters should be contained within a public easement or right of way.
|
|
|
Corrective Action Required
Sheet C4: Please revise Construction Note 4 concerning City of Lee's Summit standards for gas line connections. The City does not have any standards for the connection of gas lines since this is a separate entity.
|
|
|
Corrective Action Required
Sheet C5: Pavement detail for "STD. PAVEMENT" does not meet the Unified Development Ordinance (UDO) Article 12 in terms of pavement thickness. The UDO requires a minimum of 5 inch base course asphaltic concrete with a 2" surface course.
|
|
|
Corrective Action Required
Sheet C5: Pavement detail for "HEAVY DUTY PAVEMENT" does not meet the Unified Development Ordinance (UDO) Article 12 in terms of surface course pavement thickness. The UDO requires a minimum of 6 inch base course asphaltic concrete with a 2" surface course.
|
|
|
Corrective Action Required
Sheet C6: The trench and backfill method shown is no longer allowed for the installation of silt fence. The City requires that the slit method (i.e., machine-laid) be used for all silt fence installation.
|
|
|
Corrective Action Required
Sheet C1: This sheet is entitiled "Demolition Plan", but there are notes which specify "remove and replace". While this is not necessarily an issue, please consider renaming this sheet since there are construction notes which pertain to items not associated with demolition. In addition, the notes should be altered to specify the type of pavement to be replaced. If you wish to keep this sheet the same name, then a separate sheet will need to be prepared showing the location(s) of pavement to be replaced, along with a designation whether it is standard thickness or heavy duty.
|
|
|
Corrective Action Required
An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings. The Engineering Plan Review and Inspection Fee is based on this estimate, and is calculated at 3% of the total, plus a $100 per trip fee for the collection of water samples. Items to include in the itemized estimate include: 1) water lines greater than 2" in diameter, 2) connections to the existing water line greater than 2", 3) sanitary sewer wyes, 4) pavement removal and replacement, including subgrade preparation and/or aggregate base, 5) curb and gutter removal and replacement, 6) erosion and sediment control devices, 7) final restoration of the site, including topsoil, seeding, sodding, fertilizer, mulch, etc.
|
|
|
|
|
Planning Review
|
Approved with Conditions
|
02/09/2015
|
02/02/2015
|
|
|
Christina Stanton
|
|
|
Corrective Action Required
Any landscaping to be removed for this project will be replaced with a silimar planting (for example, deciduous shrubs will be replaced with deciduous shrubs). Provide confirmation what will be removed from where and what and will be replanted where.
|
|
|
|
|
Traffic Review
|
No Comments
|
02/09/2015
|
01/30/2015
|
|
|
Michael Park
|
|
|
|