Planning Application Status

PL2014158




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2014158
KESSLER RIDGE AT NEW LONGVIEW
Residential Preliminary Development Plan
Residential Preliminary Development Plan
Approved
11/21/2014
72 lots (55 lots on the initial phase) Note: Legal notice charged covered in the combined $928 & $1,402 payments.
Locations
Contacts
M-III LONGVIEW LLC, Address:4601 COLLEGE BLVD STE 300, Phone:(816) 561-3796  
LUTJEN INC, Address:1301 BURLINGTON STE 100, Phone:(816) 587-4320  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Corrections 02/03/2015 02/03/2015
Gene Williams, P.E.
DE C&O #01 Eng Plans – FP/PP
Corrective Action Required
02/03/2015

All required engineering plans and studies, including water lines, sanitary sewers, storm drainage, streets and erosion and sediment control shall be submitted along with the final plat and approved prior to the approval of the final plat. All public infrastructure must be substantially complete, prior to the issuance of any building permits.
DE C&O #02 Master Drainage Plan
Corrective Action Required
02/03/2015

A Master Drainage Plan (MDP) shall be submitted and approved in accordance with the City’s Design and Construction Manual for all areas of the development, including all surrounding impacted areas, along with the engineering plans for the development. The MDP shall address drainage level of service issues on an individual lot basis.
DE C&O #03 Eng & Insp Fees
Corrective Action Required
02/03/2015

All Engineering Plan Review and Inspection Fees shall be paid prior to approval of the engineering plans and prior to the issuance of any infrastructure permits or the start of construction (excluding land disturbance permit).
DE C&O #04 Cert FA or Escrow
Corrective Action Required
02/03/2015

All subdivision-related public improvements must have a Certificate of Final Acceptance prior to approval of the final plat, unless security is provided in the manner set forth in the City's Unified Development Ordinance (UDO) Section 16.340. If security is provided, building permits may be issued upon issuance of a Certificate of Substantial Completion of the public infrastructure as outlined in Section 1000 of the City's Design and Construction Manual.
DE C&O #05 As-Graded MDP
Corrective Action Required
02/03/2015

The As-graded Master Drainage Plan shall be submitted to and accepted by the City prior to the issuance of any building permits for the development.
DE C&O #06 Land Disturbance
Corrective Action Required
02/03/2015

A Land Disturbance Permit shall be obtained from the Public Works Department prior to land disturbance activities on the project site.
DE C&O #07 Easements
Corrective Action Required
02/03/2015

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to the issuance of a Certificate of Substantial Completion. A certified copy shall be submitted to the City for verification.
DE C&O #08 Changes to MDP
Corrective Action Required
02/03/2015

A restriction note shall be included on the final plat stating: “Individual lot owner(s) shall not change or obstruct the drainage flow paths on the lots, as shown on the Master Drainage Plan, unless specific application is made and approved by the City Engineer."
DE C&O #12 Cut & Fill
Corrective Action Required
02/03/2015

Any cut and / or fill operations, which cause public infrastructure to exceed the maximum / minimum depths of cover shall be mitigated by relocating the infrastructure vertically and / or horizontally to meet the specifications contained within the City’s Design and Construction Manual.
Corrective Action Required
02/03/2015

The sanitary sewer shown connecting to the existing sanitary sewer at the south end of the detention basin tract shall be re-evaluated at the final design stage. The proposed geometry of the sanitary at this location may not be in the City's best interest for long term maintenance and access.
Corrective Action Required
02/03/2015

The detention basin shown within the 4.26 acre detention tract shall be designed to meet the current APWA Section 5600 standards for comprehensive control, including a water quality element consisting of 40 hour extended detention for the 1.37 inch rain event, or best management practices as defined in Section 5600.
Traffic Review Corrections 02/03/2015 02/03/2015
Michael Park
Corrective Action Required
02/03/2015

Sidewalk is needed along Longview Road. Consider sidewalk along both sides of all streets to blend the TND design and promote a more walkable development.
Fire Review Complete 02/03/2015 01/29/2015
Jim Eden
THE PLANNING COMMISSION FAILED TO MAKE A RECOMMENDATION TO THE CITY COUCIL.
Planning Review Corrections 02/03/2015 01/26/2015
Jennifer Thompson
Fire Review Corrections 12/19/2014 12/17/2014
Jim Eden
Misc.
Corrective Action Required
12/17/2014

The section of road between SW Kessler Drive and SW Edwards Drive needs to named. Do not use Redbuck.
Misc.
Corrective Action Required
12/17/2014

The road between SW Gentry and SW Longview Road with no clear delineation needs to be either all SW Haverford or SW Curry Road.
Planning Review Corrections 12/19/2014 12/12/2014
Jennifer Thompson
Corrective Action Required
12/12/2014

It's the City's understanding the Historic homes located within this property are to remain in place/existing location (not to be relocated).
Legal Description
Corrective Action Required
12/12/2014

Please submit an electronic copy of the legal description. Microsoft Word document or selectable text PDF are the preferred file formats. The legal description can be emailed to the planner's email address above.
Corrective Action Required
12/12/2014

See the attached Single Family Residential Compatibility forms, please complete and submit.
Corrective Action Required
12/12/2014

Provide a statement indicating the location of all oil and gas wells, whether active, inactive or capped, if any, based on available information.
Corrective Action Required
12/16/2014

Provide approximate lot square footages.
Corrective Action Required
12/16/2014

Pavement width with curb?
Corrective Action Required
12/16/2014

The street name is missing on the north/south portion between Kessler (to the north) and Edwards (to the south).
Corrective Action Required
12/16/2014

name of the tracts?
Traffic Review Corrections 12/19/2014 12/10/2014
Michael Park
Corrective Action Required
12/10/2014

Sidewalk needed along Longview Road and Longview Boulevard and Kessler.
Corrective Action Required
12/10/2014

Need to discuss a revised alignment of Kessler and the context of an overall street plan for the remaining property south of 3rd Street and east of Longview Blvd.
Fire Review Corrections 12/05/2014 11/24/2014
Jim Eden
Misc.
Corrective Action Required
11/24/2014

The road between SW Gentry and SW Longview Road with no clear delineation needs to be either all SW Haverford or SW Curry Road.
Misc.
Corrective Action Required
11/24/2014

The section of road between SW Kessler Drive and SW Edwards Drive needs to named. Do not use Redbuck.
Engineering Review Corrections 12/19/2014 02/12/2014
Chris Hughey
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Preliminary Plat fee $928.00 $928.00 Paid 11/21/2014
9110077-Commercial Preliminary Development Plan fee $1,402.00 $1,402.00 Paid 12/04/2014
$2,400.00
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 02/10/2015 05:00 PM Council Chambers 02/10/2015 05:00 PM
Public Hearing Review
Pending
01/13/2015
City Council Ordinance 03/05/2015 06:15 PM Council Chambers 03/05/2015 06:15 PM
Public Hearing Review
Pending
03/05/2015
City Council Public Hearing 03/05/2015 06:15 PM Council Chambers 03/05/2015 06:15 PM
Public Hearing Review
Pending
02/05/2015
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home