Summary
PL2014005
GREEN LANTERN CAR WASH
Commercial Preliminary Development Plan
Commercial Preliminary Development Plan
Approved
01/17/2014
CROSS PROPERTIES LLC
Locations
Contacts
CROSS PROPERTIES LLC, Address:700 NW BLUE PKWY  
GASTINGER WALKER HARDEN ARCHITECTS, Address:817 WYANDOTTE  
OLSSON ASSOCIATES, Address:1251 NW BRIARCLIFF PKWY, STE. 50, Phone:(816) 361-1177  
BLUE BEACON INTERNATIONAL, INC., Address:500 GRAVES BLVD, Phone:(785) 825-2221  
CWW ENTERPRISES LLC, Address:500 GRAVES BLVD  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 03/04/2014 03/04/2014
Gene Williams, P.E.
Corrective Action Required
03/04/2014

INSERT STANDARD COMMENT 1 CONCERNING ALL ENGINEERING PLANS
Corrective Action Required
03/04/2014

INSERT STANDARD COMMENT 3 CONCERNING FEES
Corrective Action Required
03/04/2014

Corrective Action Required
03/04/2014

INSERT STANDARD COMMENT 6 CONCERNING LAND DISTURBANCE
Corrective Action Required
03/04/2014

INSERT STANDARD COMMENT 11 CONCERNING PAVEMENT
Corrective Action Required
03/04/2014

INSERT STANDARD COMMENT 12 CONCERNING CUT AND FILL
Planning Review Approved with Conditions 03/04/2014 03/03/2014
Jennifer Thompson
Traffic Review No Comments 03/04/2014 02/25/2014
Michael Park
Fire Review Approved with Conditions 03/04/2014 02/25/2014
Jim Eden
Code Statement
Corrective Action Required
02/25/2014

Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Engineering Review Corrections 01/31/2014 01/31/2014
Gene Williams, P.E.
Corrective Action Required
01/31/2014

The north fire hydrant (private) will need to be moved to meet the Fire Department requirements for spacing and hose length and also to meet the recommendation that the entrance be moved to align with the commercial entrance to the north.
Corrective Action Required
01/31/2014

The north fire hydrant (private) will need a backflow vault and backflow prevention assembly. The most logical location would be on the applicants property and within the island to the northeast. A gate valve must be provided prior to the backflow prevention assembly.
Corrective Action Required
01/31/2014

The south fire hydrant (public) should be moved in accordance with the Fire Department's comments, and will be considered public.
Corrective Action Required
01/31/2014

The south fire hydrant and water line will need to be located within a public easement. Please dedicate an easement on the minor plat for these features. The portion of the water line located on property not owned by the applicant will need a public easement recorded by separate document. Standard forms with approved language for the easement dedication are available upon request, or the applicant may choose to contact the City of Lee's Summit Right-of-Way Agent (Curt Powelson) at 816-969-1800.
Corrective Action Required
01/31/2014

A separate set of engineering plans will be required for the public water line and public fire hydrant (i.e., the south fire hydrant and water line).
Corrective Action Required
01/31/2014

A private easement will be required for the north fire line where it intersects the private drive.
Corrective Action Required
01/31/2014

Missouri Department of Transportation (MoDOT) will need to review the storm drainage plan, and in particular the flumes which direct stormwater onto their right of way.
Corrective Action Required
01/31/2014

A private easement to connect the storm drain to the private storm drainage system within the private street will need to be obtained.
Corrective Action Required
01/31/2014

The sanitary sewer connection cannot be direct-connected to the existing manhole as shown. A wye must be cut-in a minimum of four (4) feet from the outside of the manhole.
Corrective Action Required
01/31/2014

Please clean up (i.e., smooth-out) the contour line shown on Sheet C0.01 which is located directly beneath the 62.31' dimension.
Corrective Action Required
01/31/2014

If the building will be sprinklered, a backflow assembly and vault will be necessary near the water main since the building is greater than fifty (50) feet from the building. A private easement will be necessary for this fire line where it crosses adjacent property.
Traffic Review Corrections 01/31/2014 01/29/2014
Michael Park
Corrective Action Required
01/29/2014

The driveway should be moved approximately 30 feet to the west. This would align the driveway with access to the adjacent property towards the north, improve the entering traffic circulation/more direct manuever to the wash lanes, and create more space on the common drive for vehicles to stack at the intersection.
Fire Review Corrections 01/31/2014 01/28/2014
Jim Eden
Code Statement
Corrective Action Required
01/27/2014

Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Misc.
Resolved
02/25/2014

The plans indicate a fire protection main coming into the building, will it be sprinklered?
Misc.
Resolved
02/25/2014

Recommend locating the new south fire hydrant on the east side of the driveway if other utilities will allow it. There is limited access to the hydrant in its proposed location.
Imposed Loads
Corrective Action Required
01/27/2014

Fire Department- IFC 503.2.3 Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Planning Review Corrections 01/31/2014 01/27/2014
Jennifer Thompson
Corrective Action Required
01/27/2014

This property is not platted. A minor plat application shall be submitted, reviewed, and recorded prior to the issuance of a building permit.
Corrective Action Required
01/27/2014

After discussing with Mr. Don Boos, it has been noted the chain link fence is to be removed. Please revise the fencing note on the plans. Removal of the fence and planting of the landscaping could require a permit from MoDOT, please contact Steve Holloway, Traffic Specialist in State Right-of-way permitting to confirm.
Corrective Action Required
01/30/2014

Is there an executed access agreement for the drive entry area? If so please provide a copy of this. Also, during the platting process this will need to be reflected on the plat along with the coordination of other easements necessary for existing and or proposed utilities for this property.
Corrective Action Required
01/30/2014

Provide an elevation for the detached canopy structure.
Corrective Action Required
01/30/2014

Provide a detail for the pavement areas/curbs. Please refer to Article 12. Parking Section 12.120 (Unified Development Ordinance) for surface and curbing requirements.
Corrective Action Required
01/30/2014

Provide an accessible sign detail. Every accessible parking space required shall be identified by a sign, mounted on a pole or other structure, located between thirty-six (36) inches and sixty (60) inches above the ground, measured from the bottom of the sign, at the head of the parking space. All identifying signs shall be twelve (12) inches wide by eighteen (18) inches in height and meet the requirements set forth in the Manual on Uniform Traffic Control Devices. The R7-8 is the sign type for Lee's Summit, it has a white background with a green border.
Corrective Action Required
01/30/2014

Provide a trash enclosure detail. Each trash enclosure shall be constructed of masonry walls with a steel gate painted to be compatible with the color of the masonry walls and building it is to serve.
Corrective Action Required
01/30/2014

The street tree landscaping requirements have not been met for the Hwy 50 frontage and the Chipman Road frontage. Approximately 14 additional trees are required along the Highway 50 frontage and approximately 4 additional trees are required along the Chipman Road frontage. The additional trees along Highway 50 should be placed to "fill in" the area in the middle of the lot where no landscaping is currently shown.
Corrective Action Required
01/31/2014

If possible, submit all proposed sign renderings for this site. It appears that approximately 4-5 wall signs are proposed. That exceeds the number of signs staff can administratively approve. However, through this Preliminary Development Plan process the additional signs can be approved. Also, is a monument sign proposed? If so, please indicate the location on the site plan and provide a spec sheet.
Corrective Action Required
01/31/2014

A modification to the parking setback will be needed for the south, west, and north property lines. The ordinance requires the following for parking setbacks from the respective property line: North (front): 6-feet South (rear): 20-feet East (side): 6 feet West (side): 6 feet Please provide a narrative statement that explains the need for a modification of the applicable regulation. The applicable regulation can be found in Section 12.120 Parking Lot Design (Unified Development Ordinance).
Fire Review Approved with Conditions 01/31/2014 01/23/2014
Jim Eden
Code Statement
Corrective Action Required
01/23/2014

Fire Department- All building and life safety issues shall comply with the 2012 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Misc.
Corrective Action Required
01/23/2014

The plans indicate a fire protection main coming into the building, will it be sprinklered?
Misc.
Corrective Action Required
01/23/2014

Recommend locating the new south fire hydrant on the east side of the driveway if other utilities will allow it. There is limited access to the hydrant in its proposed location.
Imposed Loads
Corrective Action Required
01/23/2014

Fire Department- IFC 503.2.3 Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fees
Paid Fees Amount Paid Owing Date Paid
Commercial Preliminary Development Plan fee $1,800.00 $1,800.00 Paid 01/17/2014
$1,800.00
Legal Notice Publishing Charge $165.00 $165.00 Paid 01/17/2014
$165.00
Legal Notice Publishing Charge $165.00 $165.00 Paid 01/17/2014
$165.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 03/11/2014 05:00 PM Council Chambers 03/11/2014 05:00 PM
Public Hearing Review
Pending
03/11/2014
City Council Ordinance 04/03/2014 06:15 PM Council Chambers 04/03/2014 06:15 PM
Public Hearing Review
Pending
04/17/2014
City Council Public Hearing 04/03/2014 06:15 PM Council Chambers 04/03/2014 06:15 PM
Public Hearing Review
Pending
04/03/2014
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home

*PLEASE NOTE - You must be logged in with your registered user account to view any documents related to your Planning Application