Planning Application Status

PL2013068




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2013068
SUMMIT CENTER PAD SITE BUILDING
Commercial Preliminary Development Plan
Commercial Preliminary Development Plan
Approved
05/17/2013
CURRY REAL ESTATE
Locations
Contacts
CURRY REAL ESTATE, Address:2700 Kendallwood Pkwy, Suite 208, Phone:(816) 414-5234  
SCHAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
SCHARHAG ARCHITECTS, Address:310 ARMOUR RD #202, Phone:(816) 221-9297  
CURRY REAL ESTATE, Address:2700 Kendallwood Pkwy, Suite 208, Phone:(816) 414-5234  
DACUR INVESTMENT COMPANY INC, Address:2700 KENDALLWOOD PKWY # 208  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 07/02/2013 07/02/2013
Gene Williams, P.E.
Corrective Action Required
07/02/2013

The location of the trash enclosure should be moved slightly to the west to completely remove it's footprint from the existing utility easement.
Corrective Action Required
07/02/2013

All Engineering Plan Review and Inspection Fees shall be paid prior to the issuance of any infrastructure permits or the start of construction.
Corrective Action Required
07/02/2013

A Land Disturbance Permit shall be obtained from the Public Works Department if ground breaking is desired to take place prior to the issuance of a building permit or prior to the approval of the Final Development Plan.
Corrective Action Required
07/02/2013

Any cut or fill operations at the project site, which cause public water lines, public sanitary sewer lines, or public storm sewer lines to exceed their maximum or minimum depth of cover requirements shall be mitigated by relocating the City utility either vertically or horizontally to meet the specifications contained within the City's Design and Construction Manual.
Planning Review Approved with Conditions 07/02/2013 06/28/2013
Chris Hughey
See attached PC Letter. CHRIS HUGHEY 06/28/2013 4:16 PM
Fire Review Complete 07/02/2013 06/26/2013
Jim Eden
Code Statement
Corrective Action Required
06/26/2013

Fire Department- All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Traffic Review No Comments 07/02/2013 06/25/2013
Michael Park
Engineering Review Corrections 05/31/2013 05/31/2013
Gene Williams, P.E.
Corrective Action Required
05/31/2013

Please show all existing easements on all plan sheets. At least one (1) known public easement exists for the sanitary sewer. This will help to determine whether encroachments exist.
Corrective Action Required
05/31/2013

Are the existing flumes for stormwater in satisfactory condition? The adjacent property will be updating and installing new flume gutter sections for their project, and it will be beneficial to look at the existing condition of these facilities to determine whether this is necessary.
Corrective Action Required
05/31/2013

Sheet C4: Sanitary service should have a cut-in wye rather than a tee.
Corrective Action Required
05/31/2013

Sheet C4: Please be aware that the location of the water meter may change based on landscaping (i.e., trees, shrubs, etc.). The water meter should be placed in a readily-accessible area.
Corrective Action Required
05/31/2013

Sheet C4: All easements must be shown on the Preliminary Development Plan. Please see previous comment concerning the location and description of easements.
Corrective Action Required
05/31/2013

Are there any plans to coordinate the construction activities with the adjacent development (i.e., Freddy's)? It would appear that the driveway may be an issue that could be coordinated between the two parties.
Corrective Action Required
05/31/2013

Please provide a statement in your response to comments which addresses stormwater post-development release rates not being applicable due to the exception granted by the Design and Construction Manual (i.e., Section 5601.3A(2).
Planning Review Corrections 05/31/2013 05/30/2013
Chris Hughey
Corrective Action Required
05/29/2013

Landscaping. On Sheet L-1 correct note #4 to specify all deciduous tree plantings shall have a minimum caliper of 3 inches and all evergreen trees shall have a minimum height of 8 feet at the time of planting.
Corrective Action Required
05/30/2013

Landscaping. Submit a letter or other documentation from MoDOT of the acceptance of shrubbery in the MoDOT right-of-way for Oldham Pkwy.
Corrective Action Required
05/30/2013

Landscaping. Correct the open space tree requirement calculations. This should fallow the same methods used for the open space shrubbery calculations (47,404/5,000). 10 open space trees will be required.
Corrective Action Required
05/30/2013

Landscaping. The new painted parking lot islands need to be converted in to standard curbed parking lot islands with landscaping material and sod. Please note the impervious surface calculations will need to be updated to account for this additional pervious area.
Corrective Action Required
05/30/2013

Landscaping. The parking lot screening shrubs follow a calculation of 12 shrubs per 40 linear feet of parking lot frontage. Also, please note street frontage shrubs are included within this calculation and not in addition to it.
Corrective Action Required
05/30/2013

Sheet A2. Show and label the roof top or ground mounted mechanical units on the building elevations and site plan. Please note roof top units will be required to be screened by the buildings parapet wall equal to the height of the units and ground mounted units shall be screened by landscaping material or screening wall equal to the height of the units.
Corrective Action Required
05/30/2013

Sheet SL1 - Lighting. All new parking lot pole lights shall use LED light fixtures. Please correct the AS1 specification sheet and note on Sheet SL1.
Corrective Action Required
05/30/2013

Accessible Parking Space signage. Provide a detail of the accessible parking space signage. Please note sign model number R7-8 shall be used.
Corrective Action Required
05/30/2013

Parking. Staff would like to verify that enough parking spaces will be provided for the entire center. Please submit a list of current tenants with approximate gross square footages.
Corrective Action Required
05/30/2013

Parking. Provide a detail/section of the proposed parking lot thickness construction. Please note parking lot construction methods shall comply with the standards in Article 12 of the UDO or the residential road design in the Design and Construction Manual.
Corrective Action Required
05/31/2013

Parking. Based on the center's parking needs the parking lot spaces shown behind the main building will likely be required to be added to meet necessary parking calculations. In addition, several of the existing rear parking spaces will need to be re-striped due to fading paint.
Corrective Action Required
05/31/2013

Driveway relocation. Please verify the landscaping trees added by the recently approved "Freddy's Steakburgers and Frozen Custard" development along the south side of the driveway islands will not be removed with the driveway realignment.
Corrective Action Required
05/31/2013

Photometrics. Add footcandle measurements (photometrics) to he Site Lighting Plan (sheet SL1).
Traffic Review Corrections 05/31/2013 05/30/2013
Michael Park
Corrective Action Required
05/30/2013

To accommodate separate left-turn and right-turn egress from the driveway onto Oldham Pkwy, can the driveway be widened to at least 37' (Back of Curb to Back of Curb), 40' preferred total width (BOC-BOC).
Corrective Action Required
05/30/2013

Increase the driveway curb radii at the intersection of Oldham Pkwy to better accommodate right-turn traffic (e.g. truck movements).
Fire Review Complete 05/31/2013 05/24/2013
Jim Eden
Code Statement
Corrective Action Required
05/24/2013

Fire Department- All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Commercial Preliminary Development Plan fee $2,400.00 $2,400.00 Paid 05/17/2013
$2,400.00
9110076-Legal Notice Publishing Charge $165.00 $165.00 Paid 05/17/2013
$165.00
9110076-Legal Notice Publishing Charge $165.00 $165.00 Paid 05/17/2013
$165.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Planning Commission Meeting 07/09/2013 05:00 PM Council Chambers 07/09/2013 05:00 PM
Public Hearing Review
Approved
07/09/2013
City Council Public Hearing 08/01/2013 06:15 PM Council Chambers 08/01/2013 06:15 PM
Public Hearing Review
Pending
08/01/2013
City Council Ordinance 08/15/2013 06:15 PM Council Chambers 08/15/2013 06:15 PM
Public Hearing Review
Pending
07/25/2013
Documents & Images
Date Uploaded File Type Document Name
05/17/2013 Letter Routing Sheet
05/31/2013 Letter Applicant Letter - Dev. Apps (DRCP)
06/18/2013 Letter Resubmittal Routing Sheet
07/01/2013 Letter TIA
07/05/2013 Letter PC Letter
08/02/2013 Letter CC PH LTR
08/02/2013 Letter CC ORD LTR
08/02/2013 Ordinance ORDINANCE
08/09/2013 Ordinance Ord. #7348
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home