Summary
PL2012137
LEES SUMMIT MEDICAL CENTER MODULAR BUILDINGS
Commercial Final Development Plan
Commercial Final Development Plan
Expired
10/26/2012
MIDWEST DIVISION LSH LLC
Application requires a SUP for modular buildings. This was never pursued by the applicant. This application has now expired.
Locations
Contacts
MIDWEST DIVISION LSH LLC, Address:PO BOX 1504  
LEE'S SUMMIT MEDICAL CENTER, Address:2100 SE BLUE PKWY, Phone:(816) 282-5000  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Corrections 11/09/2012 11/09/2012
Gene Williams, P.E.
Corrective Action Required
11/09/2012

There is insufficient information on the provided sketch to determine where the new modular unit will be constructed. Please provide a site plan with reference points to property lines, and please include the location of easements, public water lines, public sanitary sewer lines, and other items which would have a bearing on this project.
Corrective Action Required
11/09/2012

The location of the proposed modular unit must be a minimum distance from public sanitary sewers and public water lines as outlined in the Design and Construction Manual. Please ensure that the modular unit and associated canopies are the minimum distance required.
Planning Review Corrections 11/09/2012 11/07/2012
Hector Soto Jr.
Corrective Action Required
11/07/2012

APPROVAL PROCESS. As discussed in the pre-application meeting held on 9/12/12, the use of modular buildings on the hospital property is not a permitted use and can only be allowed if a special use permit (SUP) is approved by the City Council. Submittal and approval of a separate SUP application by Council is required before staff can approve a final development plan for the modular building on the site. The SUP process takes 2-3 months to complete from the time of application. Staff cannot move forward on the final development plan unless City Council approves the SUP.
Corrective Action Required
11/07/2012

SITE PLAN. Provide a detailed site plan showing the proposed modular building relative to the surrounding development (e.g., hospital building, parking lot, access drives, etc.).
Corrective Action Required
11/08/2012

ELEVATIONS. Provide elevations and specifications for the proposed modular building. The elevations and/or specifications shall call out the builidng materials and colors.
Fire Review Corrections 11/09/2012 11/02/2012
Jim Eden
Code Statement
Corrective Action Required
11/02/2012

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Misc.
Corrective Action Required
11/02/2012

There is insufficient information to do a complete review of this project. Provide a detailed site plan for the project. Provide dimensions and show existing and proposed structures/infra-structure.
Traffic Review No Comments 11/09/2012 10/31/2012
Michael Park
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 10/26/2012
$600.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
10/26/2012 Letter Routing Sheet - FDP
11/09/2012 Letter Applicant Letter - FDP (DFDP)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home