Planning Application Status

PL2012025




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2012025
LICATA'S FLOWERS STORM SEWER MODIFICATIONS
Engineering Plan Review
Engineering Plan Review
Approved
03/05/2012
ALDRIDGE SPENCER L & KRISTIN M
Locations
Contacts
Not shown for privacy reasons.
ALDRIDGE SPENCER L & KRISTIN M, Address:3201 SE 3RD ST  
Reviews
Review Type Outcome Est. Completion Date Completed
Eng Plan Resubmittal Decision Approved 01/30/2018
Mike Weisenborn
Engineering Review No Comments 03/23/2012 03/20/2012
Gene Williams, P.E.
Eng Plan Decision Corrections 03/26/2012 03/15/2012
Gene Williams, P.E.
Engineering Review Corrections 03/26/2012 03/15/2012
Gene Williams, P.E.
Corrective Action Required
03/15/2012

The stormwater report consists of a collection of hydrographs with no discussion or conclusions. At a minimum, the report must discuss 1) why the changes are being proposed, 2) total volume of the original underground detention configuration, 3) revised volume of the underground detention configuration, and 4) conclusions concerning the adequacy of the revised design to meet the design standards of existing runoff versus post-development runoff.
Corrective Action Required
03/15/2012

If corrugated metal pipe is being specified for this project, then it will need to be aluminized in accordance with the City's Design and Construction Manual.
Corrective Action Required
03/15/2012

Since this plan is a revision to an existing Final Development Plan, it will need to be a stand-alone plan. It will need to be labeled as such (e.g., sheet 1 of 2, etc., rather than inserting this revised sheet into the existing plan set).
Corrective Action Required
03/15/2012

The title of the plan set must be labeled as "Revision to..." or similar language since this is a stand-alone plan set.
Corrective Action Required
03/15/2012

Standard notes must be included in the plan set concerning 48 notice to inspections, plan set shall meet the requirements of the City of Lee's Summit Design and Construction Manual as adopted by Ordinance 4813, etc.
Corrective Action Required
03/15/2012

A profile must be included with the plan set.
Corrective Action Required
03/15/2012

An Engineers Estimate of Probable Construction Costs must be submitted for the items covered in this revision. These items must include all piping, inlets, flumes, etc.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
03/15/2012 Letter Comment Letter (Engineering Plans)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: