Summary
PL2011074
SAINT LUKES EAST ER ADDITION #2
Commercial Final Development Plan
Commercial Final Development Plan
Approved
06/14/2011
SAINT LUKES EAST HOSPITAL
Locations
Contacts
SAINT LUKES EAST HOSPITAL, Address:100 NW SAINT LUKES BOULEVARD  
ACI BOLAND, Address:11229 NALL, SUITE 140  
SHAFER KLINE & WARREN INC, Address:11250 CORPORATE AVE, Phone:(913) 888-7800  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review No Comments 08/03/2011 08/04/2011
Gene Williams, P.E.
Planning Review No Comments 08/03/2011 08/03/2011
Planning Admin
Traffic Review No Comments 08/03/2011 08/01/2011
Michael Park
Fire Review Complete 08/03/2011 07/29/2011
Jim Eden
Code Statement
Corrective Action Required
07/29/2011

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Planning Review Corrections 06/28/2011 06/30/2011
Hector Soto Jr.
Planning Correction
Corrective Action Required
06/30/2011

UTILITY EASEMENTS. The proposed expansion is shown to be built over two overlapping 10' wide utility easements. No structures are allowed to encroach into any utility easements.
Fire Review Complete 06/28/2011 06/28/2011
Jim Eden
Code Statement
Corrective Action Required
06/28/2011

Fire Department-All building and life safety issues shall comply with the 2006 International Fire Code and local amendments as adopted by the City of Lee’s Summit.
Engineering Review Corrections 06/28/2011 06/28/2011
Gene Williams, P.E.
Corrective Action Required
06/28/2011

Building footprint appears to be encroaching upon a utility easement as evident from the plat. Buildings and permanent structures cannot encroach upon utility easements.
Corrective Action Required
06/28/2011

Sheet C5.0 shows a detail of the sanitary sewer connection using vitrified clay pipe which is no longer allowed in the City of Lee's Summit.
Corrective Action Required
06/28/2011

A sealed Engineer’s Opinion of Probable Construction Costs should accompany your final submittal copies. Public Works’ review and inspection fee is based on that cost. The following items, both materials and installation, should be included in the itemized estimate • Any water line larger than 2” in diameter, valves, hydrants, and backflow preventer with vault, if outside the building • All storm water piping 6” or larger, structures, and detention/retention facilities • All grading for detention/retention ponds • All sanitary sewer manholes and piping between manholes, including private mains • The connection of the building sewer stub to the public main • All public infrastructure, both onsite and offsite • All private street construction, excluding parking lots, drive approaches and sidewalks • All erosion control devices
Traffic Review No Comments 06/28/2011 06/17/2011
Michael Park
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $600.00 $600.00 Paid 06/14/2011
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
06/14/2011 Letter Admin Route Sheet FDP
06/30/2011 Letter Applicant Letter (FDP)
07/27/2011 Letter Admin Re-Route FDP
08/04/2011 Letter Approval Letter (Administrative)
08/04/2011 Fee Worksheet.xlsx
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents