Summary


PRSUBD20251953
Public Infrastructure
In Plan Review
CITY OF LEES SUMMIT
DEVELOPMENT COMPLETE
Sanitary and Water extension for the new TM Aviation Hangar at LXT
05/12/2025
Locations
Contacts
Jason Barker, Address:1627 Main Street, Phone:(816) 381-9047  
Wellner Architects, Inc., Address:1627 Main St, #100, Phone:(816) 221-0017  
CITY OF LEES SUMMIT, Address:220 S MAIN  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review - Sanitary Corrections 05/27/2025 05/13/2025
Gene Williams, P.E.
Engineering Review - Water Corrections 05/27/2025 05/13/2025
Gene Williams, P.E.
Miscellaneous Correction
Corrective Action Required
05/13/2025

Sheet C-115: a. 10 inch public water main should be extended to the west and should eliminate the unneccesary bend to the south and the west as shown on the plans. Ideally, the 10 inch line should be extended within the future parking lot island (i.e., shown as the faint dashed line) far enough so all connections can be made for the hangar building, and the future restaurant building. b. 10 inch main shall be terminated with a fire hydrant, either inline or offset. c. Fire hydrant shown to the northeast of the proposed hangar building shall be public, and shall be connected "straight" to the main rather than introducing unneccessary jogs. d. sanitary sewer is shown too close to fire line and domestic lines. A ten (10) foot minimum distance is required as measured from the outside of the pipe or structure.
Miscellaneous Correction
Corrective Action Required
05/13/2025

Sheet C-119: a. gate valves are shown at two water meter locations. Gate valves are not desired at these locations as the water meters have internal valves. b. a proposed 2 inch by 10 inch tee is proposed. This is not desired. A corporation stop (i.e., a threaded connection to the main) is required. Revise the plan as appropriate for both taps. c. just to be clear, a gate valve IS required on the fire line, immediately prior to the backflow vault. d. MH-2 shows insufficient fall at the 90 degree bend. A minimum 0.50 fall is required. e. what is the invert out elevation for the "existing manhole"? A minimum of 0.50 feet is required at this location due to the 90 degree bend.
Miscellaneous Correction
Corrective Action Required
05/13/2025

Recommend the applicant call me to discuss the revisions to the plans prior to resubmittal. Alternatively, you may wish to send a pdf document showing the proposed revisions for my markup or preliminary review.
Inspections

There are no inspections for this permit application.

Documents & Images
Date Uploaded File Type Document Name
05/05/2025 Plans Public Sanitary and Water Line_Rev 1_PL2025080
05/13/2025 Letter SUBD Comment Letter
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: