Summary


PRSUBD20242255
Public Infrastructure
Issued
CHOYCE LLC
DEVELOPMENT COMPLETE
THE TOWNHOMES OF CHAPEL RIDGE - 3RD PLAT - FULL PUBLIC INFRASTRUCTURE DEVELOPMENT
05/06/2024
10/10/2024
Locations
Contacts
BEEMER CONSTRUCTION COMPANY INC, Address:606 SE CENTRAL DR, Phone:(816) 229-2266  
MATT SCHLICHT, Address:50 SE 30TH ST, Phone:(816) 623-9888  
CHOYCE LLC, Address:PO BOX 847  
BEEMER CONSTRUCTION COMPANY INC, Address:606 SE CENTRAL DR, Phone:(816) 229-2266  
BEEMER CONSTRUCTION COMPANY INC, Address:606 SE CENTRAL DR, Phone:(816) 229-2266  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review - Street and Storm No Comments 12/11/2024 12/04/2024
Sue Pyles, P.E.
Engineering Review - Sanitary No Comments 12/11/2024 12/04/2024
Sue Pyles, P.E.
Engineering Review - Street and Storm No Comments 06/27/2024 06/27/2024
Sue Pyles, P.E.
Miscellaneous Correction
Resolved
06/27/2024

Sheet C.001: • As previously requested, please revise Street & Storm Sewer Note 1 to reflect the 6” aggregate base requirement. • Please revise the main title to match the plat title. • Please revise the title block on this sheet and throughout the plan set to reflect this project.
Miscellaneous Correction
Resolved
06/27/2024

Sheet C.100: Please label both existing end sections in the same manner.
Miscellaneous Correction
Resolved
06/27/2024

Sheet C.200: Please show the proposed contours tie back in to the existing contours.
Miscellaneous Correction
Resolved
06/27/2024

Sheet C.201: Please replace “???” on Lots 30 & 31 rear lot corners.
Engineering Review - Street and Storm Corrections 06/17/2024 06/18/2024
Sue Pyles, P.E.
Miscellaneous Correction
Resolved
06/18/2024

General: • Existing and proposed line types and line weighs aren’t consistent throughout the plan set. Please review and revise. • NEW: The City now requires that CAD drawings be submitted of the approved plans at permit issuance and of the accepted record drawings prior to issuance of a Certificate of Final Acceptance. • Show the existing detention basin and 100-yr WSE boundary, and label the 100-yr WSE elevation on Tract E throughout the plan set. • Please include design details regarding the tract off-street areas. Clarify if the area adjacent to Lot 37 is a parking area, too.
Miscellaneous Correction
Resolved
06/18/2024

Sheet C.001: • Please revise Street & Storm Sewer Note 1 to reference KCMMB asphalt. • Residential streets now require 6” of aggregate base. Please revise Street & Storm Sewer Note 1 and Typical Section accordingly. • Please revise Street & Storm Sewer Note 3 references to remove Junction Box and include Curb Inlet.
Miscellaneous Correction
Resolved
06/18/2024

Sheet C.100: • Please show existing water lines. • Label Tract H on this sheet and throughout the plan set.
Miscellaneous Correction
Resolved
06/18/2024

Sheet C.201: • Please label 100-yr WSE at all storm structures if above grade. • MBOEs are required on lots that include or are adjacent to any stormwater feature that has a 100-yr WSE associated with it.
Miscellaneous Correction
Resolved
06/18/2024

Sheets C.301-C.303: • Please denote all existing pipe of end sections to be removed in Plan views as well as Profile views. • Please relocate overlapping or cut off text in Storm Sewer Lines 1, 3, and 5 Profile views for clarity. • Structure 2-4 is mislabeled as 2-5 in Storm Line 2 Profile view. Please revise. • Please extend grade lines in Storm Sewer Line 3 Profile view. • Structure 5-3 is mislabeled as 5-2 in Storm Line 6 Plan view. Please revise.
Miscellaneous Correction
Corrective Action Required
06/18/2024

Sheet C.001: • As previously requested, please revise Street & Storm Sewer Note 1 to reflect the 6” aggregate base requirement. • Please revise the main title to match the plat title. • Please revise the title block on this sheet and throughout the plan set to reflect this project.
Miscellaneous Correction
Corrective Action Required
06/18/2024

Sheet C.100: Please label both existing end sections in the same manner.
Miscellaneous Correction
Corrective Action Required
06/18/2024

Sheet C.200: Please show the proposed contours tie back in to the existing contours.
Miscellaneous Correction
Corrective Action Required
06/18/2024

Sheet C.201: Please replace “???” on Lots 30 & 31 rear lot corners.
Engineering Review - Sanitary No Comments 06/17/2024 06/18/2024
Sue Pyles, P.E.
Miscellaneous Correction
Resolved
06/20/2024

General: • Existing and proposed line types and line weighs aren’t consistent throughout the plan set. Please review and revise. • NEW: The City now requires that CAD drawings be submitted of the approved plans at permit issuance and of the accepted record drawings prior to issuance of a Certificate of Final Acceptance.
Miscellaneous Correction
Resolved
06/20/2024

Sheets C.401 & C.402: • Please review the sanitary sewer stubs in both Plan views and Stub Tables and verify each is labeled as existing or proposed correctly. Revise as needed. • Please label the existing MHs with City numbers. Proposed line A connects to MH 08-315 and Proposed Line B connects to MH 08-360. • The drop through MH A-1 does not meet the 0.5’ minimum drop requirement. Please revise.
Miscellaneous Correction
Resolved
06/20/2024

Sheet C.403: It appears that the existing MH Line B connects to will need raised. Please verify and revise as necessary.
Miscellaneous Correction
Resolved
06/20/2024

Sheet C.404: • Please remove any unnecessary details. • City standard details have been updated. Please include the updated details in the plan set. • Please include a Trench and Backfill detail and the City’s standard detail SAN-9 MH Boxout in Pavement.
Engineering Review - Water No Comments 06/17/2024 06/18/2024
Sue Pyles, P.E.
Miscellaneous Correction
Resolved
06/19/2024

General: • Existing and proposed line types and line weighs aren’t consistent throughout the plan set. Please review and revise. • NEW: The City now requires that CAD drawings be submitted of the approved plans at permit issuance and of the accepted record drawings prior to issuance of a Certificate of Final Acceptance. • Please extend Line 1 west to the west side of NE Chapel Ridge Place.
Miscellaneous Correction
Resolved
06/19/2024

Sheet C.500: • Please revise Water Note 3 to reference butterfly valves larger than 12” as 12” mains now require gate valves. • Please include FEMA and oil/gas well notes.
Miscellaneous Correction
Resolved
06/19/2024

Sheet C.502: Please revise the water main material class to Class 235.
Miscellaneous Correction
Resolved
06/19/2024

Sheet C.503: • Please remove any unnecessary details. • City standard details have been updated. Please include the updated details in the plan set. • Please include a Trench and Backfill detail.
Engineer Review - Grading No Comments 05/24/2024 05/24/2024
Sue Pyles, P.E.
Engineering Review - Sanitary Corrections 05/24/2024 05/24/2024
Sue Pyles, P.E.
Miscellaneous Correction
Corrective Action Required
05/24/2024

General: • Existing and proposed line types and line weighs aren’t consistent throughout the plan set. Please review and revise. • NEW: The City now requires that CAD drawings be submitted of the approved plans at permit issuance and of the accepted record drawings prior to issuance of a Certificate of Final Acceptance.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheets C.401 & C.402: • Please review the sanitary sewer stubs in both Plan views and Stub Tables and verify each is labeled as existing or proposed correctly. Revise as needed. • Please label the existing MHs with City numbers. Proposed line A connects to MH 08-315 and Proposed Line B connects to MH 08-360. • The drop through MH A-1 does not meet the 0.5’ minimum drop requirement. Please revise.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.403: It appears that the existing MH Line B connects to will need raised. Please verify and revise as necessary.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.404: • Please remove any unnecessary details. • City standard details have been updated. Please include the updated details in the plan set. • Please include a Trench and Backfill detail and the City’s standard detail SAN-9 MH Boxout in Pavement.
Engineering Review - Water Corrections 05/24/2024 05/24/2024
Sue Pyles, P.E.
Miscellaneous Correction
Corrective Action Required
05/24/2024

General: • Existing and proposed line types and line weighs aren’t consistent throughout the plan set. Please review and revise. • NEW: The City now requires that CAD drawings be submitted of the approved plans at permit issuance and of the accepted record drawings prior to issuance of a Certificate of Final Acceptance. • Please extend Line 1 west to the west side of NE Chapel Ridge Place.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.500: • Please revise Water Note 3 to reference butterfly valves larger than 12” as 12” mains now require gate valves. • Please include FEMA and oil/gas well notes.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.502: Please revise the water main material class to Class 235.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.503: • Please remove any unnecessary details. • City standard details have been updated. Please include the updated details in the plan set. • Please include a Trench and Backfill detail.
Engineering Review - Street and Storm Corrections 05/24/2024 05/24/2024
Sue Pyles, P.E.
Miscellaneous Correction
Corrective Action Required
05/24/2024

General: • Existing and proposed line types and line weighs aren’t consistent throughout the plan set. Please review and revise. • NEW: The City now requires that CAD drawings be submitted of the approved plans at permit issuance and of the accepted record drawings prior to issuance of a Certificate of Final Acceptance. • Show the existing detention basin and 100-yr WSE boundary, and label the 100-yr WSE elevation on Tract E throughout the plan set. • Please include design details regarding the tract off-street areas. Clarify if the area adjacent to Lot 37 is a parking area, too.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.001: • Please revise Street & Storm Sewer Note 1 to reference KCMMB asphalt. • Residential streets now require 6” of aggregate base. Please revise Street & Storm Sewer Note 1 and Typical Section accordingly. • Please revise Street & Storm Sewer Note 3 references to remove Junction Box and include Curb Inlet.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.100: • Please show existing water lines. • Label Tract H on this sheet and throughout the plan set.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheet C.201: • Please label 100-yr WSE at all storm structures if above grade. • MBOEs are required on lots that include or are adjacent to any stormwater feature that has a 100-yr WSE associated with it.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Sheets C.301-C.303: • Please denote all existing pipe of end sections to be removed in Plan views as well as Profile views. • Please relocate overlapping or cut off text in Storm Sewer Lines 1, 3, and 5 Profile views for clarity. • Structure 2-4 is mislabeled as 2-5 in Storm Line 2 Profile view. Please revise. • Please extend grade lines in Storm Sewer Line 3 Profile view. • Structure 5-3 is mislabeled as 5-2 in Storm Line 6 Plan view. Please revise.
Traffic Review - Streets No Comments 05/24/2024 05/24/2024
Erin Ralovo
Fees
Paid Fees Amount Paid Owing Date Paid
Water Insp Fee $1,426.87 $1,426.87 Paid 08/01/2024
Storm Sewer Inspection Fee $3,351.49 $3,351.49 Paid 08/01/2024
Paved Surface Inspection Fee $8,492.91 $8,492.91 Paid 08/01/2024
Site Grading Fee $2,100.00 $2,100.00 Paid 08/01/2024
Sanitary Sewer Insp Fees $4,160.49 $4,160.49 Paid 08/01/2024
Water Test Fee $400.00 $400.00 Paid 08/01/2024
Right of Way Permit Fee $85.00 $85.00 Paid 08/01/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Pending 7/12/2025
Misc
Corrective Action Required
05/14/2025
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues 1-10-25 NS Site Visited and still no erosion control issues 1-16-25 NS Site Visited and still no erosion control issues 1-24-25 NS Site Visited and still no erosion control issues 1-31-25 NS Site Visited and still no erosion control issues 2-3-25 NS Site Visited and still no erosion control issues 2-10-25 NS Site Visited and still no erosion control issues 2-17-25 NS Site Visited and still no erosion control issues 2-24-25 NS Site Visited and still no erosion control issues 2-28-25 NS Site visited and it appears that no erosion control issues
Sanitary Sewer Construction Inspection Pending 1/1/2026
Misc
Informational
09/18/2024
9-5-24 NS Site visited and talked to the foreman about what standards are required. 9-6-24 NS Workers are staging sewer manholes and receiving all materials. 9-9-24 NS Crews are out working on sewer manhole. Chad Project Manager/Owner kept arguing with me about tracer wire being put on the main. 9-10-24 NS site visited and crews are working on cutting in new services line. 9-11-24 NS crews are working on sewer line and keep hitting rock. 9-17-24 NS Site visited and crews were not working on sewer because the backhoe broke and started working on storm water. 9-18-24 NS Site visited and the crews are working on sewer.
Grading/Excavation/Fill Inspection Pending 1/1/2026
Water Line - Construction Inspection Pending 1/1/2026
Pavement-Proof Roll Pending 1/1/2026
Pavement-Surface Pending 1/1/2026
Install Street and Stop Signs Pending 1/1/2026
Pavement-Aggregate Base Pending 1/1/2026
Pavement-Curb Construction Pending 1/1/2026
Pavement-Stabilized Subgrade Pending 1/1/2026
Sanitary - Material Verification Pending 1/1/2026
Sanitary Sewer Construction Inspection Pending 1/1/2026
Sanitary Sewer - Air Test Pending 1/1/2026
Sanitary Sewer - Mandrel Pending 1/1/2026
Sanitary Sewer - Vacuum Pending 1/1/2026
Punch List Inspection Pending 1/1/2026
Storm Sewer Construction Inspection Pending 1/1/2026
Misc
Informational
12/27/2024
12-24-24 RH. Contractor was prepping exciting storm inlet to connect to new storm wate. Contractor will be cutting on Friday to start the storm towards storm inlet 1-1 12-27-24 RH. Contractor cut into exciting storm inlet and started to run storm toward 1-1. They only got two lines in before stopping due to the rain. Propper bedding was used and they would be covering with fill later on.
Sanitary Sewer Construction Inspection Partial 9/18/2024 9/18/2024 09/18/2024
Misc
Informational
09/18/2024
9-5-24 NS Site visited and talked to the foreman about what standards are required. 9-6-24 NS Workers are staging sewer manholes and receiving all materials. 9-9-24 NS Crews are out working on sewer manhole. Chad Project Manager/Owner kept arguing with me about tracer wire being put on the main. 9-10-24 NS site visited and crews are working on cutting in new services line. 9-11-24 NS crews are working on sewer line and keep hitting rock. 9-17-24 NS Site visited and crews were not working on sewer because the backhoe broke and started working on storm water. 9-18-24 NS Site visited and the crews are working on sewer.
Erosion Control Inspection Failed 10/11/2024 10/14/2024
Misc
Corrective Action Required
10/14/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr.
Erosion Control Inspection Partial 10/31/2024 10/31/2024
Misc
Corrective Action Required
10/14/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection.
Erosion Control Inspection Partial 11/13/2024 11/13/2024
Misc
Corrective Action Required
10/31/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed
Erosion Control Inspection Partial 11/13/2024 11/13/2024
Misc
Corrective Action Required
11/13/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed
Site Visit Partial 11/14/2024 11/21/2024 11/21/2024
Misc
Informational
11/21/2024
11-8-24 NS Site visited and crews have started working without a pre-con and Dillion the Forman called to let me know what is going on and I talked to Steve and said I was okay with them working since they let me know. 11-15-24 NS Site visited and crews started to work on sewer and core into the side of the existing sewer stub 11-18-24 NS no work being done because of rain. 11-20-24 NS crews are working only on sewer stubs 11-21-24 NS Site visited crews are working on sewer and they have the west side almost complete. I talked to the Forman about dead ends and that they need the inverts to be filled with concrete. incase they have a back up with sewer and it will properly drain.
Site Visit Partial 11/26/2024 11/26/2024
Misc
Informational
11/21/2024
Chapel Ridge Townhomes Part 1 11-8-24 NS Site visited and crews have started working without a pre-con and Dillion the Forman called to let me know what is going on and I talked to Steve and said I was okay with them working since they let me know. 11-15-24 NS Site visited and crews started to work on sewer and core into the side of the existing sewer stub 11-18-24 NS no work being done because of rain. 11-20-24 NS crews are working only on sewer stubs 11-21-24 NS Site visited crews are working on sewer and they have the west side almost complete. I talked to the Forman about dead ends and that they need the inverts to be filled with concrete. incase they have a back up with sewer and it will properly drain. 11-25-24 NS Site visited and talked to Richard and the crews are working on sewer and going to pour flow-able-fill tomorrow
Erosion Control Inspection Partial 12/13/2024 12/13/2024
Misc
Corrective Action Required
11/13/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues
Site Visit Partial 11/26/2024 12/13/2024 12/13/2024
Misc
Informational
11/26/2024
Chapel Ridge Townhomes Part 1 11-8-24 NS Site visited and crews have started working without a pre-con and Dillion the Forman called to let me know what is going on and I talked to Steve and said I was okay with them working since they let me know. 11-15-24 NS Site visited and crews started to work on sewer and core into the side of the existing sewer stub 11-18-24 NS no work being done because of rain. 11-20-24 NS crews are working only on sewer stubs 11-21-24 NS Site visited crews are working on sewer and they have the west side almost complete. I talked to the Forman about dead ends and that they need the inverts to be filled with concrete. incase they have a back up with sewer and it will properly drain. 11-25-24 NS Site visited and talked to Richard and the crews are working on sewer and going to pour flow-able-fill tomorrow 12-13-24 NS Site Visited and crews have been working on sewer.
Storm Sewer Construction Inspection Partial 12/27/2024
Misc
Informational
12/27/2024
12-24-24 RH. Contractor was prepping exciting storm inlet to connect to new storm wate. Contractor will be cutting on Friday to start the storm towards storm inlet 1-1 12-27-24 RH. Contractor cut into exciting storm inlet and started to run storm toward 1-1. They only got two lines in before stopping due to the rain. Propper bedding was used and they would be covering with fill later on.
Site Visit Partial 12/31/2024 12/31/2024
Misc
Informational
12/31/2024
12-31-24 NS Site visited it appears crews are working on storm water and have put in water and sewer are completed.
Erosion Control Inspection Partial 12/31/2024 12/31/2024
Misc
Corrective Action Required
12/13/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues
Erosion Control Inspection Partial 1/25/2025 01/25/2025
Misc
Corrective Action Required
12/31/2024
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues 1-10-25 NS Site Visited and still no erosion control issues 1-16-25 NS Site Visited and still no erosion control issues 1-24-25 NS Site Visited and still no erosion control issues
Erosion Control Inspection Partial 1/31/2025 01/31/2025
Misc
Corrective Action Required
01/25/2025
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues 1-10-25 NS Site Visited and still no erosion control issues 1-16-25 NS Site Visited and still no erosion control issues 1-24-25 NS Site Visited and still no erosion control issues 1-31-25 NS Site Visited and still no erosion control issues
Erosion Control Inspection Partial 2/24/2025 02/24/2025
Misc
Corrective Action Required
01/31/2025
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues 1-10-25 NS Site Visited and still no erosion control issues 1-16-25 NS Site Visited and still no erosion control issues 1-24-25 NS Site Visited and still no erosion control issues 1-31-25 NS Site Visited and still no erosion control issues 2-3-25 NS Site Visited and still no erosion control issues 2-10-25 NS Site Visited and still no erosion control issues 2-17-25 NS Site Visited and still no erosion control issues 2-24-25 NS Site Visited and still no erosion control issues
Erosion Control Inspection Partial 2/28/2025 02/28/2025
Misc
Corrective Action Required
02/24/2025
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues 1-10-25 NS Site Visited and still no erosion control issues 1-16-25 NS Site Visited and still no erosion control issues 1-24-25 NS Site Visited and still no erosion control issues 1-31-25 NS Site Visited and still no erosion control issues 2-3-25 NS Site Visited and still no erosion control issues 2-10-25 NS Site Visited and still no erosion control issues 2-17-25 NS Site Visited and still no erosion control issues 2-24-25 NS Site Visited and still no erosion control issues 2-28-25 NS Site visited and it appears that no erosion control issues
Erosion Control Inspection Partial 5/15/2025 05/14/2025
Misc
Corrective Action Required
02/28/2025
Chapel Ridge part 1 10-14-24 NS Site visited and it appears that silt fence needs to be replaced or fixed around jobsite with gutter buddies on Sundown Dr. 10-31-24 NS Site Visited and no work has been done since last inspection. 11-6-24 NS Site Visited and still needs silt fence repaired 11-13-24 NS Site Visited will call Kevin and ask when he will have the problem fixed 12-13-24 NS Site Visited and still no erosion control issues 12-31-24 NS Site Visited and still no erosion control issues 1-10-25 NS Site Visited and still no erosion control issues 1-16-25 NS Site Visited and still no erosion control issues 1-24-25 NS Site Visited and still no erosion control issues 1-31-25 NS Site Visited and still no erosion control issues 2-3-25 NS Site Visited and still no erosion control issues 2-10-25 NS Site Visited and still no erosion control issues 2-17-25 NS Site Visited and still no erosion control issues 2-24-25 NS Site Visited and still no erosion control issues 2-28-25 NS Site visited and it appears that no erosion control issues
Documents & Images
Date Uploaded File Type Document Name
05/06/2024 Cost Estimate Mass Grading_PRSUBD20242255
05/06/2024 Cost Estimate Sanitary_PRSUBD20242255
05/06/2024 Cost Estimate Streets and Storm_PRSUBD20242255
05/06/2024 Cost Estitmate Water_PRSUBD20242255
05/06/2024 Mass Grading, Erosion Plans_PRSUBD20242255
05/06/2024 Plans Sanitary Sewer Plans_Rev0_PRSUBD20242255
05/06/2024 Plans Street and Storm Plans_Rev0_PRSUBD20242255
05/06/2024 Plans Water Line Plans_Rev0_PRSUBD20242255
05/29/2024 Letter SUBD Comment Letter_PRSUBD20242255
05/31/2024 Plans Water Line Plans_Rev1_PRSUBD20242255
05/31/2024 Plans Street and Storm Plans_Rev1_PRSUBD20242255
05/31/2024 Plans Sanitary Sewer Plans_Rev1_PRSUBD20242255
05/31/2024 Letter City Comments_PRSUBD20242255
05/31/2024 Engineers Estimate COST ESTIMATE WATER_PRSUBD20242255
05/31/2024 Engineers Estimate COST ESTIMATE SANITARY_PRSUBD20242255
05/31/2024 Engineers Estimate COST ESTIMATE STREET AND STORM_PRSUBD20242255
06/20/2024 Plans Street and Storm Plans_PRSUBD20242255
06/26/2024 Letter SUBD MDNR SANITARY CONCURRENCE LETTER
06/26/2024 Letter SUBD MDNR WATER CONCURRENCE LETTER
07/02/2024 Letter MDNR Concurrence Letter - PRSUBD20242255 Sanitary Townhomes of Chapel Ridge 3rd
07/11/2024 Engineers Estimate Fee Worksheet
07/30/2024 Letter Townhomes of Chapel Ridge 3rd Plat Water Model
07/30/2024 Letter Townhomes of Chapel Ridge 3rd MDNR Conc Letter WAT Signed
07/30/2024 Letter Townhomes of Chapel Ridge 3rd MDNR Conc Letter SAN Signed
07/31/2024 Plans Street and Storm Plans_PRSUBD20242255
07/31/2024 Plans Sanitary Sewer Plans_PRSUBD20242255
07/31/2024 Approved Plans Stamped Approved Plans - Sanitary_PRSUBD20242255
07/31/2024 Approved Plans Stamped Approved Plans - Street and Storm_PRSUBD20242255
07/31/2024 Approved Plans Stamped Approved Plans - Water_PRSUBD2024255
08/01/2024 Receipt Receipt_PRSUBD2024255
09/04/2024 Letter MDNR Letter_PRSUBD20242255
09/18/2024 Letter SUBD Comment Letter
09/18/2024 Letter SUBD Comment Letter
09/18/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter DE-Permit
10/14/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter SUBD Building Permit
11/13/2024 Letter INSPECTION SUMMARY
11/13/2024 Letter INSPECTION SUMMARY
11/13/2024 Letter INSPECTION SUMMARY
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter Commercial Permit Issuance - Engineering
11/21/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter Commercial Permit Issuance - Engineering
11/26/2024 Letter INSPECTION SUMMARY
12/03/2024 Plans Sanitary Sewer Plans_PRSUBD20242255
12/03/2024 Plans Street and Storm Plans_PRSUBD20242255
12/04/2024 Approved Plans Stamped Approved Plans - Sanitary_PRSUBD20242255- REVISED
12/04/2024 Approved Plans Stamped Approved Plans - Street and Storm_PRSUBD20242255- REVISED
12/05/2024 Letter SUBD Approval Letter_PRSUBD20242255
12/13/2024 Letter SUBD MDNR SANITARY CONCURRENCE LETTER
12/13/2024 Letter INSPECTION SUMMARY
12/13/2024 Letter INSPECTION SUMMARY
12/27/2024 Letter INSPECTION SUMMARY
12/31/2024 Letter INSPECTION SUMMARY
12/31/2024 Letter INSPECTION SUMMARY
01/25/2025 Letter INSPECTION SUMMARY
01/31/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/28/2025 Letter INSPECTION SUMMARY
05/14/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home