Summary


PRSUBD20224251
Public Infrastructure
Issued
CHOYCE LLC
DEVELOPMENT COMPLETE
FULL INFRASTRUCTURE FOR SINGLE FAMILY SUBDIVISION
08/31/2022
04/24/2025
Locations
Contacts
CHOYCE LLC, Address:PO BOX 847  
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
BEEMER CONSTRUCTION COMPANY INC, Address:606 SE CENTRAL DR, Phone:(816) 229-2266  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 12/19/2024 12/19/2024
Daniel Fernandez
Fees
Paid Fees Amount Paid Owing Date Paid
Right of Way Permit Fee $85.00 $85.00 Paid 04/17/2025
Sanitary Sewer Insp Fees $2,440.60 $2,440.60 Paid 10/30/2024
Site Grading Fee $1,922.61 $1,922.61 Paid 09/03/2024
Storm Sewer Inspection Fee $4,381.27 $4,381.27 Paid 04/17/2025
Water Insp Fee $2,673.98 $2,673.98 Paid 02/26/2025
Paved Surface Inspection Fee $8,269.32 $8,269.32 Paid 04/17/2025
Water Test Fee $600.00 $600.00 Paid 02/26/2025
Site Grading Fee $0.00 $0.00 $0.00 N/A
$1,922.61
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Pavement-Surface Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Pavement-Aggregate Base Pending
Water Line - Hydrostatic Test Pending
Sanitary Sewer Construction Inspection Pending 2/27/2025
Misc
Informational
12/24/2024
12-24-24 JS. Crew was onsite installing final manhole with flowable fill coming this afternoon.
Site Visit Pending 7/10/2025
Misc
Informational
06/03/2025
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines. 5-14-25 NS site visited and the construction of the road is complete. it has had the curb put in and the asphalt has been put in. 5-21-25 NS Site visited and it appears that asphalt has been put in. 5-28-25 NS Site visited crews are still doing underground work and the developer said he will be out to put grass seed down with no straw because it drills the seed into the ground. 6-3-25 NS Site visited and no work today because of rain. crew is out here breaking rock down to haul.
Pavement-Proof Roll Pending 7/11/2025
Erosion Control Inspection Pending 7/12/2025
Misc
Informational
05/14/2025
Chapel Ridge Plat 3. Indep-Rd
Site Visit Partial 10/10/2024 10/10/2024 10/10/2024
Misc
Informational
10/10/2024
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out.
Site Visit Partial 11/26/2024 12/13/2024 12/13/2024
Misc
Informational
10/10/2024
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines.
Sanitary Sewer Construction Inspection Partial 12/24/2024 12/24/2024 12/24/2024
Misc
Informational
12/24/2024
12-24-24 JS. Crew was onsite installing final manhole with flowable fill coming this afternoon.
Site Visit Partial 12/24/2024 02/27/2025
Misc
Informational
12/13/2024
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines.
Erosion Control Inspection Partial 5/15/2025 05/14/2025
Misc
Informational
05/14/2025
Chapel Ridge Plat 3. Indep-Rd
Site Visit Partial 5/15/2025 05/14/2025
Misc
Informational
02/27/2025
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines. 5-14-25 NS site visited and the construction of the road is complete. it has had the curb put in and the asphalt has been put in.
Site Visit Partial 5/21/2025 05/21/2025
Misc
Informational
05/14/2025
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines. 5-14-25 NS site visited and the construction of the road is complete. it has had the curb put in and the asphalt has been put in. 5-21-25 NS Site visited and it appears that asphalt has been put in.
Site Visit Partial 5/27/2025 05/28/2025
Misc
Informational
05/21/2025
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines. 5-14-25 NS site visited and the construction of the road is complete. it has had the curb put in and the asphalt has been put in. 5-21-25 NS Site visited and it appears that asphalt has been put in. 5-28-25 NS Site visited crews are still doing underground work and the developer said he will be out to put grass seed down with no straw because it drills the seed into the ground.
Site Visit Partial 6/3/2025 06/03/2025
Misc
Informational
05/28/2025
Chapel Ridge Plat 2 10-4-24 NS received a call from Ryan Heckman and someone complained about the dirt and I called up Jason and he had a water truck come out. 12-13-24 NS Site Visited and crews are working on sewer and will be completed today. 30 days and then we will test the sewer lines. 5-14-25 NS site visited and the construction of the road is complete. it has had the curb put in and the asphalt has been put in. 5-21-25 NS Site visited and it appears that asphalt has been put in. 5-28-25 NS Site visited crews are still doing underground work and the developer said he will be out to put grass seed down with no straw because it drills the seed into the ground. 6-3-25 NS Site visited and no work today because of rain. crew is out here breaking rock down to haul.
Water Line - Construction Inspection Passed 6/18/2025 06/18/2025
Misc
Informational
06/18/2025
6-18-25 NS Site visited, Water has passed.
Grading/Excavation/Fill Inspection Passed 6/18/2025 06/18/2025
Misc
Informational
06/18/2025
6-18-25 NS Site visited, and it appears that the road is being graded in and they will put curbs in after grading is done.
Sanitary Sewer - Air Test Passed 6/18/2025 06/18/2025
Misc
Informational
06/18/2025
6-18-25 NS Site visited, all sewer has passed all test.
Sanitary Sewer - Mandrel Passed 6/18/2025 06/18/2025
Misc
Informational
06/18/2025
6-18-25 NS Site visited, and it appears that sewer has passed all inspections.
Sanitary Sewer - Vacuum Passed 6/18/2025 06/18/2025
Misc
Informational
06/18/2025
6-18-25 NS Site visited, and all sewer has passed inspections.
Storm Sewer Construction Inspection Passed 6/18/2025 06/20/2025
Misc
Informational
06/20/2025
6-20-25 NS Site visited, and it appears that sewer has passed all inspections.
Documents & Images
Date Uploaded File Type Document Name
09/03/2024 Receipt Receipt-Site Grading_PRSUBD20224251
10/10/2024 Letter INSPECTION SUMMARY
10/30/2024 Receipt Receipt-Sanitary_PRSUBD20224251
10/30/2024 Email Approval Email_PRSUBD20224251
12/13/2024 Letter INSPECTION SUMMARY
12/24/2024 Letter INSPECTION SUMMARY
10/30/2024 Plans Stamped Approved Plans FDP Sanitary_PL2022247
12/17/2024 Plans Stamped Approved Plans FDP Street and Storm_PL2022248
02/26/2025 Receipt Receipt_PRSUBD20224251
02/13/2025 Plans Stamped Approved Plans FDP Water_PL2022246
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
04/17/2025 Receipt Receipt_PRSUBD20222451
04/24/2025 Letter DS Building Permit
05/14/2025 Letter INSPECTION SUMMARY
05/14/2025 Letter INSPECTION SUMMARY
05/14/2025 Letter INSPECTION SUMMARY
05/21/2025 Letter INSPECTION SUMMARY
05/28/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
06/18/2025 Letter INSPECTION SUMMARY
06/20/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home