Summary


PRSUBD20190249
Public Infrastructure
Final Acceptance
HUNT MIDWEST REAL ESTATE DEV INC
DEVELOPMENT COMPLETE
Off-site water main on the west side of Pryor Rd. From Eagle Creek to Scherer Rd
02/04/2019
07/19/2019
07/25/2023
Locations
Contacts
HUNT MIDWEST REAL ESTATE DEV INC, Address:8300 NE UNDERGROUND DR  
HUNT MIDWEST REAL EST DEV INC, Address:8300 NE UNDERGROUND DR  
PROPERTY RESERVE INC, Address:PO BOX 511196  
Not shown for privacy reasons.
RANDY SPALDING EXCAVATING INC, Address:PO BOX 1421, Phone:(816) 318-9500  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 02/04/2019 02/04/2019
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Water Insp Fee $14,062.20 $14,062.20 Paid 07/11/2019
Water Test Fee $1,000.00 $1,000.00 Paid 07/11/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Water Line - Construction Inspection Partial 08/05/2019
Misc
Informational
08/05/2019
The Redford Construction crew started on the 16” water main install. The crew tied onto the main at station 0+00 and installed approximately 100’FT of the line. Photos of the work are uploaded to the permit. I verified the correct materials used for the connection and install.
Water Line - Construction Inspection Partial 8/6/2019 08/06/2019
Misc
Informational
08/06/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Water - Material Verification Passed 8/6/2019 08/06/2019
Misc
Informational
08/06/2019
Correct materials verified. Photos are uploaded to the permit.
Water Line - Construction Inspection Partial 8/6/2019 08/09/2019
Misc
Informational
08/06/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/09/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Water Line - Construction Inspection Partial 8/12/2019 08/12/2019
Misc
Informational
08/09/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/09/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/12/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/12/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Water Line - Construction Inspection Partial 8/13/2019 08/13/2019
Misc
Informational
08/12/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/12/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/12/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/12/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/13/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Water Line - Construction Inspection Partial 8/14/2019 08/19/2019
Misc
Informational
08/13/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/13/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/13/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/13/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/13/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
08/19/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Water Line - Construction Inspection Partial 8/20/2019 08/22/2019
Misc
Informational
08/19/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/19/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/19/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/19/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/19/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
08/19/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
08/22/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Water Line - Construction Inspection Partial 8/26/2019 08/26/2019
Misc
Informational
08/22/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/22/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/22/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/22/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/22/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
08/22/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
08/22/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
08/26/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Water Line - Construction Inspection Partial 08/29/2019
Misc
Informational
08/26/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/26/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/26/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/26/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/26/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
08/26/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
08/26/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
08/26/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
08/29/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Water Line - Construction Inspection Partial 09/03/2019
Misc
Informational
08/29/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
08/29/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
08/29/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/29/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
08/29/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
08/29/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
08/29/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
08/29/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
08/29/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
09/03/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Water Line - Construction Inspection Partial 09/04/2019
Misc
Informational
09/03/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
09/03/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
09/03/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/03/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/03/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
09/03/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
09/03/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
09/03/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
09/03/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
09/03/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
09/04/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Water Line - Construction Inspection Partial 09/17/2019
Misc
Informational
09/04/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
09/04/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
09/04/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/04/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/04/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
09/04/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
09/04/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
09/04/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
09/04/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
09/04/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
09/04/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
09/17/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Water Line - Construction Inspection Partial 09/27/2019
Misc
Informational
09/17/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
09/17/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
09/17/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/17/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/17/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
09/17/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
09/17/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
09/17/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
09/17/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
09/17/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
09/17/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
09/17/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Misc
Informational
09/27/2019
Redford Construction tied the 16” water line into the existing 20” line at the Pryor & Scherer intersection and installed the three butterfly valves. The crew also poured the thrust block behind the tee. The install was in compliance with the Design & Construction standards for Lee’s Summit. Photos of the work have been uploaded into the system.
Water Line - Construction Inspection Partial 10/08/2019
Misc
Informational
09/27/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
09/27/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
09/27/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/27/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
09/27/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
09/27/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
09/27/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
09/27/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
09/27/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
09/27/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
09/27/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
09/27/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Misc
Informational
09/27/2019
Redford Construction tied the 16” water line into the existing 20” line at the Pryor & Scherer intersection and installed the three butterfly valves. The crew also poured the thrust block behind the tee. The install was in compliance with the Design & Construction standards for Lee’s Summit. Photos of the work have been uploaded into the system.
Misc
Informational
10/08/2019
The bore is complete and the 16” in water line is installed under the road. The connections are made and the crew was continuing the install on the south side of SW Scherer RD. The crew plans to have the install complete and be ready for a pressure test by Monday 10/14/19. Photos of the work are uploaded and I will return for further inspection tomorrow 10/9.
Water Line - Hydrostatic Test Passed 10/17/2019
Misc
Informational
10/17/2019
I observed the hydrostatic pressure test for the entire 16” water main. The gauge held at 150 psi with no drop for two hours. The test passed.
Water Line - Construction Inspection Partial 10/18/2019
Misc
Informational
10/08/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
10/08/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
10/08/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/08/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/08/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
10/08/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
10/08/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
10/08/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
10/08/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
10/08/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
10/08/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
10/08/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Misc
Informational
10/08/2019
Redford Construction tied the 16” water line into the existing 20” line at the Pryor & Scherer intersection and installed the three butterfly valves. The crew also poured the thrust block behind the tee. The install was in compliance with the Design & Construction standards for Lee’s Summit. Photos of the work have been uploaded into the system.
Misc
Informational
10/08/2019
The bore is complete and the 16” in water line is installed under the road. The connections are made and the crew was continuing the install on the south side of SW Scherer RD. The crew plans to have the install complete and be ready for a pressure test by Monday 10/14/19. Photos of the work are uploaded and I will return for further inspection tomorrow 10/9.
Misc
Informational
10/18/2019
The Redford crew tied on to the existing 16” butterfly valve at station 0+00 where they began construction. The crew plans to chlorinate the new line Monday next week. Photos of the install are attached.
Water Line - Construction Inspection Partial 10/21/2019
Misc
Informational
10/18/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
10/18/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
10/18/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/18/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/18/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
10/18/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
10/18/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
10/18/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
10/18/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
10/18/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
10/18/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
10/18/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Misc
Informational
10/18/2019
Redford Construction tied the 16” water line into the existing 20” line at the Pryor & Scherer intersection and installed the three butterfly valves. The crew also poured the thrust block behind the tee. The install was in compliance with the Design & Construction standards for Lee’s Summit. Photos of the work have been uploaded into the system.
Misc
Informational
10/18/2019
The bore is complete and the 16” in water line is installed under the road. The connections are made and the crew was continuing the install on the south side of SW Scherer RD. The crew plans to have the install complete and be ready for a pressure test by Monday 10/14/19. Photos of the work are uploaded and I will return for further inspection tomorrow 10/9.
Misc
Informational
10/18/2019
The Redford crew tied on to the existing 16” butterfly valve at station 0+00 where they began construction. The crew plans to chlorinate the new line Monday next week. Photos of the install are attached.
Misc
Informational
10/21/2019
The Redford crew is chlorinating the new 16” water main from station 0+00 to the end of line. I verified the correct chlorine amount according to the test strips used. The line appears to be sufficiently filled with chlorine. We will flush the line tomorrow to prepare for bacteria testing on Wednesday.
Water Line - Construction Inspection Partial 10/22/2019
Misc
Informational
10/21/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
10/21/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
10/21/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/21/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/21/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
10/21/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
10/21/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
10/21/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
10/21/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
10/21/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
10/21/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
10/21/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Misc
Informational
10/21/2019
Redford Construction tied the 16” water line into the existing 20” line at the Pryor & Scherer intersection and installed the three butterfly valves. The crew also poured the thrust block behind the tee. The install was in compliance with the Design & Construction standards for Lee’s Summit. Photos of the work have been uploaded into the system.
Misc
Informational
10/21/2019
The bore is complete and the 16” in water line is installed under the road. The connections are made and the crew was continuing the install on the south side of SW Scherer RD. The crew plans to have the install complete and be ready for a pressure test by Monday 10/14/19. Photos of the work are uploaded and I will return for further inspection tomorrow 10/9.
Misc
Informational
10/21/2019
The Redford crew tied on to the existing 16” butterfly valve at station 0+00 where they began construction. The crew plans to chlorinate the new line Monday next week. Photos of the install are attached.
Misc
Informational
10/21/2019
The Redford crew is chlorinating the new 16” water main from station 0+00 to the end of line. I verified the correct chlorine amount according to the test strips used. The line appears to be sufficiently filled with chlorine. We will flush the line tomorrow to prepare for bacteria testing on Wednesday.
Misc
Informational
10/22/2019
The Redford crew flushed the 16” water line and de-chlorinated the water. I verified that there was less than 10 ppm of chlorine in the line prior to shutting the valves. We will pull the day 1 bacteria sample and deliver it to Keystone Labs for testing tomorrow morning.
Water Line - Coliform Test 1 Partial 10/23/2019 10/23/2019
Informational
10/23/2019
John DiMauro 10/23/2019 4:04 PM We collected the day 1 samples for bacteria testing and delivered them to Keystone Labs. We will know the results tomorrow.
Water Line - Coliform Test 2 Passed 10/24/2019 10/25/2019
Misc
Informational
10/25/2019
Day 2 bacteria samples were collected and taken to Keystone Lab for testing yesterday 10/24/19. I just received confirmation that the day 2 samples passed. The line is now approved for service.
Water Line - Coliform Test 1 Passed 10/25/2019
Misc
Informational
10/25/2019
The day 1 samples passed.
Water Line - Construction Inspection Passed 10/25/2019
Misc
Informational
10/22/2019
The crew is continuing the 16” water main install along Pryor Rd. The crew is currently backfilling the pipe laid yesterday and breaking rock for the run. I will return this afternoon for further inspection.
Misc
Informational
10/22/2019
The Redford crew is on site continuing the 16” water main install. The crew hit an existing service line and has been working on fixing the line today. They plan to continue laying pipe on Monday 8/12/19.
Misc
Informational
10/22/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/22/2019
Stark Boring Co. is on site boring for the water line install under SW EAGLEVIEW DR. Redford is on site assisting with the bore for the pipe install.
Misc
Informational
10/22/2019
The Redford crew is on site continuing the water line install. The crew has the connection to the bore pipe made and approx 40’ ft of the line installed to the north. Photos are attached to the system.
Misc
Informational
10/22/2019
The Redford crew is on site continuing the 16” water main install. Photos of the current progress are uploaded. I will return later today for further inspection.
Misc
Informational
10/22/2019
The Redford Construction crew is on site continuing the 16” water main install. The crew has the line run to approx station 14+75.0 There issues with the design of the restrain DIP section that are being worked out. The crew moved ahead on the line starting at approx station 15+35.0 to continue the install. I will return later today for further inspection.
Misc
Informational
10/22/2019
The Redford crew is on site working on the off site 16” water line install. The crew is installing the air relief assembly on the line just south of SW EagleView Dr.
Misc
Informational
10/22/2019
The Redford crew is on site working on the 16” water line. The crew set the hydrant assembly at station 45+57.67 The install appears to match the approved plans and materials and methods used are in compliance with the design and construction manual. The crew plans to pour thrust blocks and restraints first thing next week. Photos of the work are uploaded to the system.
Misc
Informational
10/22/2019
The Redford crew set the hydrant and air relief at approx station 37+16.00 and has the main run to approx station 38+00. The crew plans to back fill today and pour thrust blocks and restraints tomorrow. Photos of the work are uploaded to the system.
Misc
Informational
10/22/2019
The crew poured thrust blocks at the hydrant assembly’s that were installed this week. Photos of the work are uploaded to the system
Misc
Informational
10/22/2019
The Redford crew is working on the section of pipe that goes under the 72” storm pipe. The crew installed the water line with the correct fittings and restraint blocks to secure the pipe. Photos of the work are uploaded.
Misc
Informational
10/22/2019
Redford Construction tied the 16” water line into the existing 20” line at the Pryor & Scherer intersection and installed the three butterfly valves. The crew also poured the thrust block behind the tee. The install was in compliance with the Design & Construction standards for Lee’s Summit. Photos of the work have been uploaded into the system.
Misc
Informational
10/22/2019
The bore is complete and the 16” in water line is installed under the road. The connections are made and the crew was continuing the install on the south side of SW Scherer RD. The crew plans to have the install complete and be ready for a pressure test by Monday 10/14/19. Photos of the work are uploaded and I will return for further inspection tomorrow 10/9.
Misc
Informational
10/22/2019
The Redford crew tied on to the existing 16” butterfly valve at station 0+00 where they began construction. The crew plans to chlorinate the new line Monday next week. Photos of the install are attached.
Misc
Informational
10/22/2019
The Redford crew is chlorinating the new 16” water main from station 0+00 to the end of line. I verified the correct chlorine amount according to the test strips used. The line appears to be sufficiently filled with chlorine. We will flush the line tomorrow to prepare for bacteria testing on Wednesday.
Misc
Informational
10/22/2019
The Redford crew flushed the 16” water line and de-chlorinated the water. I verified that there was less than 10 ppm of chlorine in the line prior to shutting the valves. We will pull the day 1 bacteria sample and deliver it to Keystone Labs for testing tomorrow morning.
Misc
Informational
10/25/2019
Both Day 1 & 2 bacteria samples passed. I opened the valves and put the line in service.
Water Line - Construction Taps Removed Passed 11/5/2019 11/05/2019
Misc
Informational
11/05/2019
John DiMauro 11/05/2019 1:10 PM The 16"in water main has been installed and has passed all field and labratory testing.
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home