Summary


PRSUBD20180348
Public Infrastructure
Final Acceptance
CLAYTON PROPERTIES GROUP, INC
DEVELOPMENT COMPLETE
Manor at Stoney Creek 3rd plat - sanitary and water, street and storm
02/16/2018
06/23/2018
11/18/2021
Locations
Address
4406 SW AMETHYST DR, LEES SUMMIT, MO 64082

Address
4402 SW AMETHYST DR, LEES SUMMIT, MO 64082

Address
4401 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4405 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4409 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4413 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4417 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4421 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4420 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4416 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4412 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4408 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4404 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4400 SW ALABASTER CIR, LEES SUMMIT, MO 64082

Address
4401 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4405 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4409 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4413 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4417 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4421 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4420 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4416 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4412 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4408 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4404 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Address
4400 SW TANZANITE CIR, LEES SUMMIT, MO 64082

Property
69700122800000000

Property
69700123900000000

Property
69700124000000000

Property
69700122600000000

Property
69700123800000000

Property
69700122900000000

Property
69700124100000000

Property
69700122500000000

Property
69700123000000000

Property
69700123700000000

Property
69700124200000000

Property
69700122400000000

Property
69700123100000000

Property
69700123600000000

Property
69700124300000000

Property
69700122300000000

Property
69700123200000000

Property
69700123500000000

Property
69700124400000000

Property
69700071300000000

Property
69700122100000000

Property
69700122200000000

Property
69700123300000000

Property
69700123400000000

Property
69700124500000000

Property
69700122700000000

Property
69700122000000000

Address
4407 SW AMETHYST DR, LEES SUMMIT, MO 64082

Contacts
ENGINEERING SOLUTIONS, Address:50 SE 30TH ST, Phone:(816) 623-9888  
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
REDFORD CONSTRUCTION INC, Address:PO BOX 1065, Phone:(816) 540-2030  
NOE HEATH & EMILY, Address:4407 SW AMETHYST DR  
FERGER JEFFREY C, Address:4402 SW AMETHYST DR  
ANNIS ALEXANDRA & GEOFFREY, Address:4406 SW AMETHYST DR  
CONWAY DEREK M & LACEY J, Address:4401 SW ALABASTER CIR  
PERCIVAL JERRY & ALICIA, Address:4405 SW ALABASTER CIR  
STATON ERIC, Address:4409 SW ALABASTER CIR  
HOUK NATHAN & EMILY, Address:4413 SW ALABASTER CIR  
STAUFFER GARY L & TINA, Address:4417 SW ALABASTER CIR  
BEAUCHAMP JAMES LARRY & PATRICIA ANN, Address:4421 SW ALABASTER CIR  
GINDLESBERGER ANDREW RILEY & VALERIE JEAN, Address:4400 SW ALABASTER CIR  
RICHARDS SCOTT & AMY, Address:4404 SW ALABASTER CIR  
GRIFFIN T DELIBERO 2013 IRREVOCABLE TRUST, Address:4408 SW ALABASTER CIR  
LARSEN CARL B & YONG NAN, Address:4412 SW ALABASTER CIR  
TRITTEN LESLIE, Address:4416 SW ALABASTER CIR  
MCFARLAND NICOLE R, Address:4420 SW ALABASTER CIR  
PRUETT ANDREA L & CASEY B, Address:4401 SW TANZANITE CIR  
FERGUSON MICHAEL & REGINA, Address:4405 SW TANZANITE CIR  
SMITH BRETT & KATHLEEN, Address:4409 SW TANZANITE CIR  
TAMAYO DANIEL A & JENNIFER H, Address:4413 SW TANZANITE CIR  
TOURE ALASSANE, Address:4417 SW TANZANITE CIR  
WALLACE DARREN, Address:4421 SW TANZANITE CIR  
ODONNELL THOMAS & CALLIE, Address:4400 SW TANZANITE CIR  
AGNEW WILLARD & MARGARET MARY, Address:4404 SW TANZANITE CIR  
LUECK SHAWN & DARCY, Address:4408 SW TANZANITE CIR  
VORIS JESSICA, Address:4412 SW TANZANITE CIR  
SHELTON RAIMONDA D, Address:4416 SW TANZANITE CIR  
GRANADOS ALEXANDER & DORIAN G, Address:4420 SW TANZANITE CIR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 02/16/2018 06/22/2018
Tom Chandler
Fees
Paid Fees Amount Paid Owing Date Paid
91100C9-Water Insp Fee $1,598.23 $1,598.23 Paid 02/23/2018
9110072-Water Test Fee $600.00 $600.00 Paid 02/23/2018
91100C8-Sanitary Sewer Insp Fees $2,412.27 $2,412.27 Paid 02/23/2018
9110068-Storm Fee $1,119.21 $1,119.21 Paid 06/04/2018
9110081-Paved Surface Inspection Fee $3,872.20 $3,872.20 Paid 06/04/2018
9110071-Site Grading Fee $1,456.89 $1,456.89 Paid 06/04/2018
9110069-After Hours Inspections (Public Works)(Per Hour) $50.00 $50.00 Paid 12/04/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Passed 6/22/2018 at 8:30 AM 06/23/2018
Informational
06/23/2018
Tom Chandler 06/23/2018 7:10 AM ESC measures installed. Additional measures to be installed after clearing and grubbing. Will monitor weekly.
Sanitary Sewer Construction Inspection Passed 7/27/2018 08/02/2018
PW-Main inspection
Informational
07/30/2018
Brice Lawson 07/30/2018 8:27 AM On 7/27/18 Redford Construction informed me that they installed 56' of 8" sanitary main from MH-10 to the south. It appeared that the sanitary main is being bedded with clean rock. They were backfilling the road crossing in just south of MH-10. KC Testing was on site and let me know that compaction test results for the trench backfill are all within spec.
Sanitary Sewer Construction Inspection Passed 7/12/2018 at 2:00 PM 08/02/2018
Informational
07/12/2018
Tom Chandler 07/12/2018 3:01 PM Began sanitary sewer construction today.
Sanitary Sewer Construction Inspection Partial 7/31/2018 08/02/2018
Informational
08/02/2018
Tom Chandler 08/02/2018 11:03 AM Installed sanitary sewer main line C. Installed service wyes and MH C-1 and MH C-2.
Sanitary Sewer Construction Inspection Partial 8/1/2018 08/02/2018
Informational
08/02/2018
Tom Chandler 08/02/2018 11:05 AM Installed sanitary sewer main line B. 8" SDR 26 pipe and service wyes up to MH B-1. Installed MH B-1 as well. Second crew on-site installing service laterals for lots 97-99. Installed anode and tracer wire. Will install trench checks later.
Sanitary Sewer Construction Inspection Partial 8/2/2018 at 9:00 AM 08/02/2018
Informational
08/02/2018
Tom Chandler 08/02/2018 11:09 AM Installing sanitary sewer main line B. Installing service wyes as well. Second crew working on installing service laterals for line C. Will pour trench checks this afternoon.
Sanitary Sewer Construction Inspection Partial 8/6/2018 08/07/2018
Informational
08/07/2018
Tom Chandler 08/07/2018 2:02 PM Installed Sanitary sewer main line 1 up to station 3+50. Installed service wyes for lots 94,95,103 and 104.
Sanitary Sewer - Vacuum Partial 10/3/2018 at 7:30 AM 10/04/2018
Informational
10/04/2018
Tom Chandler 10/04/2018 4:06 PM Vacuum tested MH C-1 for 2m and passed. Tested MH C-2 for 2m and passed. MH C-2 looked about 18" low compared to fill that was placed. If MH C-2 need barrel section added will need to retest.
Sanitary Sewer - Air Test Partial 10/3/2018 at 7:30 AM 10/04/2018
Informational
10/04/2018
Tom Chandler 10/04/2018 4:10 PM Air tested Line C from MH A-10 to MH C-1 for 8m36s and from MH C-1 to MH C-2 for 7m34s. Both sections passed.
Site Visit Complete 10/31/2018 10/31/2018
Misc
Informational
10/31/2018
Began installing fly ash for subgrade stabilization today.
Pavement-Stabilized Subgrade Partial 10/31/2018 10/31/2018
Misc
Informational
10/31/2018
Fly ash installed today. KCTE was on site for testing.
Sanitary - Material Verification Passed 11/08/2018
Sanitary Sewer Construction Inspection Passed 11/08/2018
PW-Main inspection
Informational
07/30/2018
Brice Lawson 07/30/2018 8:27 AM On 7/27/18 Redford Construction informed me that they installed 56' of 8" sanitary main from MH-10 to the south. It appeared that the sanitary main is being bedded with clean rock. They were backfilling the road crossing in just south of MH-10. KC Testing was on site and let me know that compaction test results for the trench backfill are all within spec.
Pavement-Stabilized Subgrade Passed 11/8/2018 11/08/2018
Misc
Informational
10/31/2018
Fly ash installed today. KCTE wason site for testing.
Informational
11/08/2018
Tom Chandler 11/08/2018 2:18 PM Subgrade stabilization has been completed and tested by KCTE. Awaiting proof roll test prior MODOT type 5 base rock installation. Weather has delayed the proof roll.
Pavement-Aggregate Base Failed 11/19/2018 11/19/2018
Misc
Corrective Action Required
11/19/2018
John Jackson and I observed the proof roll for the curbs. The test failed. The contractor will reschedule at a later date.
Water Line - Hydrostatic Test Passed 01/15/2019
Misc
Informational
01/15/2019
The Redford Construction crew performed the Hydro test on water lines # 4 & 5. Both lines are connected to Water line # 1 for The Reserve at Stoney Creek 3rd plat and all lines for both subdivisions were tested simultaneously. I observed the crew pressure up the water line to 150 psi and stayed on site while the line held for two hours. The test passed.
Water Line - Coliform Test 1 Partial 2/4/2019 02/04/2019
Misc
Informational
02/04/2019
The Redford Construction crew pulled water samples for the entire water line including the two dead end lines for the Manor at Stoney Creek. I was on site during work and collected and delivered the samples to Keystone Labs for testing. We will know the results of the tests in 24 hours.
Water Line - Coliform Test 1 Passed 2/11/2019 02/11/2019
Misc
Informational
02/04/2019
The Redford Construction crew pulled water samples for the entire water line including the two dead end lines for the Manor at Stoney Creek. I was on site during work and collected and delivered the samples to Keystone Labs for testing. We will know the results of the tests in 24 hours.
Water Line - Coliform Test 2 Passed 2/11/2019 02/11/2019
Water Line - Construction Inspection Partial 02/19/2019
Misc
Informational
02/19/2019
The Redford Construction crew completed the water system install. Today the crew installed the remainder of water line #3. The crew set the fire hydrant assembly and connected to the existing water line at station 1+14.80. The thrust blocks were poured and the crew will be back at a later date to backfill once the concrete sets up. The crew also completed the water line #2 install for The Manor at Stoney Creek 3rd Plat. The crew converted the temporary fire hydrant to a permanent assembly and connected to the existing main at station 0+97.89 Thrust blocks were poured and the crew will be back at a later date to backfill once the concrete sets up.
Misc
Informational
02/19/2019
The Redford Construction crew completed the water system install. Today the crew installed the remainder of water line #3. The crew set the fire hydrant assembly and connected to the existing water line at station 1+14.80. The thrust blocks were poured and the crew will be back at a later date to backfill once the concrete sets up. The crew also completed the water line #2 install for The Manor at Stoney Creek 3rd Plat. The crew converted the temporary fire hydrant to a permanent assembly and connected to the existing main at station 0+97.89 Thrust blocks were poured and the crew will be back at a later date to backfill once the concrete sets up.
Pavement-Proof Roll Passed 7/2/2019 07/02/2019
Misc
Informational
07/02/2019
The Randy Spalding crew proof rolled the fly ash treated sub-grade for this project. I observed the proof roll and verified the correct weight loaded on the truck. The roll test passed.
Curb - Proof Roll Passed 7/9/2019 07/09/2019
Misc
Informational
07/09/2019
I observed the proof roll of the curb line for the public roads at The Reserve / Manor at Stoney Creek. I verified the correct truck type and load weight. The roll test passed. The curb crew plans to start the curb install on Thursday 7/11/19.
Public Curb Inspection Partial 7/12/2019 07/12/2019
Misc
Informational
07/12/2019
JK Concrete is installing the public curb for both The Reserve and The Manor roads. I verified that the correct concrete type is being poured and the correct equipment and material is being used. The crew will have a little more than half of the curb installed and plans to finish the install on Monday 7/15/19.
Public Curb Inspection Partial 7/15/2019 07/15/2019
Misc
Informational
07/12/2019
JK Concrete is installing the public curb for both The Reserve and The Manor roads. I verified that the correct concrete type is being poured and the correct equipment and material is being used. The crew will have a little more than half of the curb installed and plans to finish the install on Monday 7/15/19.
Misc
Informational
07/15/2019
JK Concrete completed the curb machine work for the subdivision. The crew still needs to pour the throats for a number of the curb inlets. I will return for further inspection tomorrow.
Pavement-Proof Roll Passed 07/18/2019
Misc
Informational
07/18/2019
I observed the proof roll for the public streets for this subdivision. I verified the correct truck and load weight. The proof roll passed inspection.
Pavement-Surface Partial 7/20/2019 07/20/2019
Misc
Informational
07/20/2019
Superior Bowen is on site installing the base lift for both The Reserve & Manor at Stoney Creek. I verified the correct mix type, temperature and equipment for the job. The crew plans to install the surface lift on Monday 7/22/19.
Street - Surface Course Partial 7/23/2019 07/23/2019
Misc
Informational
07/23/2019
The Superior Bowen crew is on site installing the surface lift for both The Reserve & Manor at Stoney Creek. I verified the correct mix type, Temperature and equipment for the install.
ADA Inspection Partial 08/09/2019
Misc
Informational
08/09/2019
JK Concrete is on site installing the ADA ramps and a section of the public sidewalk for the subdivision. I inspected the ramp forms and verified the subgrade is in compliance. I will return for further inspection after the concrete has been poured.
ADA Inspection Passed 8/13/2019 08/19/2019
Misc
Informational
08/09/2019
JK Concrete is on site installing the ADA ramps and a section of the public sidewalk for the subdivision. I inspected the ramp forms and verified the subgrade is in compliance. I will return for further inspection after the concrete has been poured.
Misc
Informational
08/19/2019
The ADA Ramps are in compliance.
Erosion Control Inspection Failed 03/19/2020
Misc
Corrective Action Required
03/19/2020
FAILED EROSION CONTROL INSPECTION. The two lots being built on have either insufficient or no erosion control measures in place and are allowing silt and mud to leave the sites and collect on the streets and in the storm water system. Please install proper erosion control measures for these lots, which includes sufficient construction entrances to avoid inspection denial and freezing of building permits. Additionally, the swale behind lots 86 - 90 along SW ALABASTER CIR has no erosion control measures installed and it appears that other foundation spoils have been placed in this area. With the heavy rains these spoils are washing onto the adjacent occupied residential lots and into the existing field inlets for this swale. This area needs to be addressed asap as it is changing the water flow directions as well as infiltrating the storm water collection system with silt. Photos of the area are uploaded to the system.
Record Drawing Review Passed 11/3/2021 11/17/2021
Sanitary Sewer - Vacuum Passed 11/18/2021
Sanitary Sewer - Air Test Passed 11/18/2021
Public Curb Inspection Passed 11/18/2021
Misc
Informational
07/15/2019
JK Concrete is installing the public curb for both The Reserve and The Manor roads. I verified that the correct concrete type is being poured and the correct equipment and material is being used. The crew will have a little more than half of the curb installed and plans to finish the install on Monday 7/15/19.
Misc
Informational
07/15/2019
JK Concrete completed the curb machine work for the subdivision. The crew still needs to pour the throats for a number of the curb inlets. I will return for further inspection tomorrow.
Pavement-Surface Passed 11/18/2021
Misc
Informational
07/20/2019
Superior Bowen is on site installing the base lift for both The Reserve & Manor at Stoney Creek. I verified the correct mix type, temperature and equipment for the job. The crew plans to install the surface lift on Monday 7/22/19.
Street - Surface Course Passed 11/18/2021
Misc
Informational
07/23/2019
The Superior Bowen crew is on site installing the surface lift for both The Reserve & Manor at Stoney Creek. I verified the correct mix type, Temperature and equipment for the install.
Documents & Images
Date Uploaded File Type Document Name
02/23/2018 Receipt Receipt for transaction: 2018-000663
02/23/2018 Receipt Receipt for transaction: 2018-000664
06/04/2018 Receipt Receipt for transaction: 2018-003444
06/22/2018 Letter DE-Permit
06/23/2018 DOC062318-06232018072405
07/09/2018 Scan_0631
07/12/2018 K24510
07/30/2018 Letter DE-Daily Inspection Summary
08/07/2018 Letter DE-Daily Inspection Summary
10/04/2018 Letter DE-Daily Inspection Summary
10/31/2018 image
10/31/2018 image0
10/31/2018 Letter DE-Daily Inspection Summary
10/31/2018 image1
10/31/2018 Letter Inspection Summary
10/31/2018 Letter DE-Daily Inspection Summary
11/08/2018 Letter DE-Daily Inspection Summary
11/19/2018 Letter INSPECTION SUMMARY
11/19/2018 image2
01/15/2019 Letter INSPECTION SUMMARY
02/04/2019 Letter INSPECTION SUMMARY
02/11/2019 Letter DE-Daily Inspection Summary
02/11/2019 WO#1B90177 - City of Lees Summit
02/11/2019 WO#1B90228 - City of Lees Summit
02/19/2019 image3
02/19/2019 image4
02/19/2019 Letter INSPECTION SUMMARY
02/19/2019 Letter INSPECTION SUMMARY
02/19/2019 Letter INSPECTION SUMMARY
07/02/2019 Letter INSPECTION SUMMARY
07/09/2019 Letter INSPECTION SUMMARY
07/12/2019 Letter INSPECTION SUMMARY
07/15/2019 Letter Inspection Summary
07/15/2019 Letter INSPECTION SUMMARY
07/15/2019 Letter DE-Daily Inspection Summary
07/18/2019 Letter INSPECTION SUMMARY
07/20/2019 Letter INSPECTION SUMMARY
07/23/2019 Letter INSPECTION SUMMARY
08/09/2019 Letter INSPECTION SUMMARY
08/19/2019 Letter INSPECTION SUMMARY
11/18/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
11/18/2019 Letter DE-Punch List
11/19/2019 The Manor at Stoney Creek 3rd Plat Signed Certificate of Substantial Completion
11/19/2019 The Manor at Stoney Creek 3rd Plat Signed Punch List
12/04/2019 Receipt Receipt for transaction: 2019-007583
03/19/2020 Letter INSPECTION SUMMARY
03/19/2020 20
03/19/2020 21
03/19/2020 22
06/30/2020 Letter INSPECTION SUMMARY
09/30/2021 Reserve at stoney Creek and Manor at Stoney Creek 3rd Plat Maintenance Bonds
10/26/2021 Plans SANITARY AS-BUILTS 11-14-2019
10/26/2021 WATER ASBUILTS 11-14-2019
10/26/2021 STREET AND STORM ASBUILTS 11-14-2019
11/18/2021 Letter DE-Certificate of Final Acceptance (Commercial)
12/13/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
04/26/2022 Stoney Creek Manor and Reserve 3rd Final Payment Affidavits
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home