Permit Application Status

PRSITE20224130


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20224130
Development - Site
Substantial Completion
NLV TOWNHOMES LLC
DEVELOPMENT COMPLETE
Village at New Longview Townhomes FDP - Site Development
08/25/2022
09/08/2022
Locations
Contacts
RUSSELL PEARSON, Address:3152 GRANDSTAND CIR, Phone:(913) 735-9861  
Julie Sellers, Address:Olsson Associates, Phone:(816) 361-1177  
O'REILLY BUILD LLC, Address:5051 S NATIONAL AVE STE 4-110, Phone:(417) 862-9500  
Scott Ready, Phone: 8169691225  
NLV TOWNHOMES LLC, Address:3152 SW GRANDSTAND CIR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 08/25/2022 08/25/2022
Scott Ready
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $3,862.65 $3,862.65 Paid 09/02/2022
91100C9-Water Insp Fee $2,986.38 $2,986.38 Paid 09/02/2022
9110068-Storm Sewer Inspection Fee $2,760.36 $2,760.36 Paid 09/02/2022
9110081-Paved Surface Inspection Fee $15,008.88 $15,008.88 Paid 09/02/2022
9110071-Site Grading Fee $5,700.22 $5,700.22 Paid 09/02/2022
9110072-Water Test Fee $400.00 $400.00 Paid 09/02/2022
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 07/24/2024
9110069-After Hours Inspections (Public Works)(Per Hour) $50.00 $50.00 Paid 07/24/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underground Electrical Inspection - Commercial Pending
Misc
Corrective Action Required
05/10/2023
- Light bases , ground rod with wire attached, conduit in on Haverford plus 1 on East side of Curry
Site Visit Pending
Misc
Informational
04/16/2025
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit. 12-2-24 DP. No site work going on right now. Still expecting All American to show up on site soon to fix needed repairs. 12-17-24 JS. All American is on-site and they are starting to tear out curbs and sidewalk that require repairs. 12-24-24 JS. Contractor poured back areas that needed fixed on SW and curb. 12-30-24 DP. All American removed concrete blankets yesterday and completed needed repairs. 4-16-25 DP. No work on site. First two phases are complete, but this permit will stay open until all phases are complete, which will be long term.
Erosion Control Inspection Pending
Misc
Informational
05/15/2025
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
05/15/2025
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
05/15/2025
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
05/15/2025
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great. 12-30-24 DP. No ESC issues at this time.
Misc
Informational
05/15/2025
2-6-25 DP. All site work is done for this phase. All ESC is in good working order. 3-26-25 DP. No ESC issues at this time. 4-14-25 DP. No changes from previous inspections. This site is not active. 5-15-25 DP. Silt fence is starting to come down in areas without established vegetation. Also, the mowers are mowing the new sod up against the buildings, but haven't touched any other part of the site this year. Silt fence needs to be maintained with areas not vegetated. Grass needs to be mowed ASAP.
Grading/Excavation/Fill Inspection Partial 09/09/2022
Misc
Informational
09/09/2022
Trinity Excavating onsite grading. 9/6/22 ES
Grading/Excavation/Fill Inspection Partial 09/09/2022
Misc
Informational
09/09/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES
Grading/Excavation/Fill Inspection Partial 09/09/2022
Misc
Informational
09/09/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES
Erosion Control Inspection Partial 09/09/2022
Misc
Informational
09/09/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES
Grading/Excavation/Fill Inspection Partial 09/14/2022
Misc
Informational
09/09/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES
Grading/Excavation/Fill Inspection Partial 09/14/2022
Misc
Informational
09/14/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES
Grading/Excavation/Fill Inspection Partial 09/14/2022
Misc
Informational
09/14/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES
Erosion Control Inspection Partial 09/16/2022
Misc
Informational
09/09/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES
Grading/Excavation/Fill Inspection Partial 09/16/2022
Misc
Informational
09/14/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES
Erosion Control Inspection Partial 09/26/2022
Misc
Informational
09/16/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES
Site Visit Partial 09/27/2022
Misc
Informational
09/27/2022
No site work being performed today. 9/27/22 ES
Grading/Excavation/Fill Inspection Partial 09/27/2022
Misc
Informational
09/16/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES
Site Visit Partial 09/28/2022
Misc
Informational
09/27/2022
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES
Water - Material Verification Partial 09/28/2022
Misc
Informational
09/28/2022
Win-Water delivered 8" C900 pipe, epoxy coated fittings, joints and gaskets. 9/28/22 ES
Water Line - Construction Inspection Partial 09/29/2022
Misc
Informational
09/29/2022
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES
Water Line - Construction Inspection Partial 09/30/2022
Misc
Informational
09/29/2022
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES
Water Line - Construction Inspection Partial 09/30/2022
Misc
Informational
09/30/2022
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES
Sanitary - Material Verification Partial 09/30/2022
Misc
Informational
09/30/2022
Had SDR26 sewer pipe delivered, along with fittings. 9/30/22 ES
Water - Material Verification Partial 09/30/2022
Misc
Informational
09/28/2022
Win-Water delivered 8" C900 pipe, epoxy coated fittings, joints and gaskets. 9/28/22 ES Had 6" C900 pipe and additional fittings delivered for fire hydrant installs. 9/30/22 ES
Erosion Control Inspection Partial 10/03/2022
Misc
Informational
09/26/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES
Grading/Excavation/Fill Inspection Partial 10/03/2022
Misc
Informational
09/27/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES Trinity Excavating grading area next to Longview Blvd. 10/3/22 ES
Site Visit Partial 10/03/2022
Misc
Informational
09/28/2022
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES
Sanitary - Material Verification Partial 10/04/2022
Misc
Informational
09/30/2022
Had SDR26 sewer pipe delivered, along with fittings. 9/30/22 ES Had manhole structures delivered. 10/3/22 ES
Sanitary Sewer Construction Inspection Partial 10/04/2022
Misc
Informational
10/04/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES
Sanitary Sewer Construction Inspection Not Ready 10/04/2022
Grading/Excavation/Fill Inspection Partial 10/04/2022
Misc
Informational
10/03/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES Trinity Excavating grading area next to Longview Blvd. 10/3/22 ES Trinity Excavating finished grading area along Longview Blvd parking lot. 10/4/22 ES
Sanitary Sewer Construction Inspection Partial 10/05/2022
Misc
Informational
10/05/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES
Sanitary Sewer Construction Inspection Partial 10/05/2022
Misc
Informational
10/05/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES
Sanitary Sewer Construction Inspection Partial 10/06/2022
Misc
Informational
10/05/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES
Sanitary Sewer Construction Inspection Partial 10/07/2022
Misc
Informational
10/06/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES
Erosion Control Inspection Partial 10/11/2022
Misc
Informational
10/03/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES
Sanitary Sewer Construction Inspection Partial 10/11/2022
Misc
Informational
10/07/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES
Sanitary Sewer Construction Inspection Partial 10/11/2022
Misc
Informational
10/11/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES
Sanitary Sewer Construction Inspection Partial 10/12/2022
Misc
Informational
10/11/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES
Sanitary Sewer Construction Inspection Partial 10/14/2022
Misc
Informational
10/12/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES
Grading/Excavation/Fill Inspection Partial 10/18/2022
Misc
Informational
10/04/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES Trinity Excavating grading area next to Longview Blvd. 10/3/22 ES Trinity Excavating finished grading area along Longview Blvd parking lot. 10/4/22 ES Trinity working on backfilling lot 68, and clearing area down around existing storm drainage basin. Preparing to place new storm structure for 48” outflow pipe. 10/17/22 ES
Storm Sewer Construction Inspection Partial 10/18/2022
Misc
Informational
10/18/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES
Erosion Control Inspection Partial 10/19/2022
Misc
Informational
10/11/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES
Storm Sewer Construction Inspection Partial 10/20/2022
Misc
Informational
10/18/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES
Storm - Material Verification Partial 10/20/2022
Misc
Informational
10/20/2022
Trinity excavating had storm additional structures and ADS pipe delivered. 10/20/22 ES
Storm Sewer Construction Inspection Partial 10/21/2022
Misc
Informational
10/20/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES
Erosion Control Inspection Partial 10/28/2022
Misc
Informational
10/19/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES
Site Visit Partial 10/28/2022
Misc
Informational
10/03/2022
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES
Storm Sewer Construction Inspection Partial 10/28/2022
Misc
Informational
10/21/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES
Sanitary Sewer Construction Inspection Partial 10/28/2022
Misc
Informational
10/14/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES
Misc
Informational
10/28/2022
Storm Sewer Construction Inspection Partial 10/29/2022
Misc
Informational
10/28/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES
Sanitary Sewer Construction Inspection Partial 10/29/2022
Misc
Informational
10/28/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES
Misc
Informational
10/28/2022
Sanitary - Material Verification Partial 10/29/2022
Misc
Informational
10/04/2022
Had SDR26 sewer pipe delivered, along with fittings. 9/30/22 ES Had manhole structures delivered. 10/3/22 ES Manhole bases for: 1-1, 1-2, 1-3, 1-4, 4-1 and 4-2 delivered along with barrel and cone sections. 10/28/22 ES
Storm - Material Verification Partial 10/29/2022
Misc
Informational
10/20/2022
Trinity excavating had storm additional structures and ADS pipe delivered. 10/20/22 ES Storm structures: 1-3, 1-4, 1-5, 1-6, 1-8, 2-1, 4-1 were delivered from Forterra, along with barrel sections, second sections and lids. 1-6 base and second section split pipe coming into structure. 10/28/22 ES
Sanitary Sewer Construction Inspection Partial 10/29/2022
Misc
Informational
10/29/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
10/29/2022
Storm Sewer Construction Inspection Partial 10/29/2022
Misc
Informational
10/29/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES
Erosion Control Inspection Partial 10/31/2022
Misc
Informational
10/28/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES
Sanitary Sewer Construction Inspection Partial 10/31/2022
Misc
Informational
10/29/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
10/29/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES
Storm Sewer Construction Inspection Partial 11/02/2022
Misc
Informational
10/29/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES
Sanitary Sewer Construction Inspection Partial 11/02/2022
Misc
Informational
10/31/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
10/31/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok.
Sanitary Sewer Construction Inspection Partial 11/04/2022
Misc
Informational
11/02/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
11/02/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES
Storm Sewer Construction Inspection Partial 11/04/2022
Misc
Informational
11/02/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES
Storm Sewer Construction Inspection Partial 11/08/2022
Misc
Informational
11/04/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES
Sanitary Sewer Construction Inspection Partial 11/08/2022
Misc
Informational
11/04/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
11/04/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES
Erosion Control Inspection Partial 11/08/2022
Misc
Informational
10/31/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES
Storm Sewer Construction Inspection Partial 11/09/2022
Misc
Informational
11/08/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC.
Sanitary Sewer Construction Inspection Partial 11/17/2022
Misc
Informational
11/08/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
11/08/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES
Storm Sewer Construction Inspection Partial 11/17/2022
Misc
Informational
11/09/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES
Sanitary Sewer Construction Inspection Partial 11/17/2022
Misc
Informational
11/17/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
11/17/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged.
Erosion Control Inspection Partial 11/21/2022
Misc
Informational
11/08/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES
Sanitary Sewer Construction Inspection Partial 11/21/2022
Misc
Informational
11/17/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
11/17/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES
Storm Sewer Construction Inspection Partial 11/21/2022
Misc
Informational
11/17/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES
Storm Sewer Construction Inspection Partial 11/21/2022
Misc
Informational
11/21/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES
Storm Sewer Construction Inspection Partial 12/01/2022
Misc
Informational
11/21/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping.
Storm Sewer Construction Inspection Partial 12/02/2022
Misc
Informational
12/01/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made.
Sanitary Sewer Construction Inspection Partial 12/02/2022
Misc
Informational
11/21/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
11/21/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2.
Storm Sewer Construction Inspection Partial 12/05/2022
Misc
Informational
12/02/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8.
Sanitary Sewer Construction Inspection Partial 12/05/2022
Misc
Informational
12/02/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
12/02/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2.
Storm Sewer Construction Inspection Partial 12/06/2022
Misc
Informational
12/05/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 is may be placed today.
Sanitary Sewer Construction Inspection Partial 12/06/2022
Misc
Informational
12/05/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
12/05/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite.
Storm Sewer Construction Inspection Partial 12/06/2022
Misc
Informational
12/06/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10.
Storm Sewer Construction Inspection Partial 12/07/2022
Misc
Informational
12/06/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day.
Storm Sewer Construction Inspection Partial 12/09/2022
Misc
Informational
12/07/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open.
Storm Sewer Construction Inspection Partial 12/12/2022
Misc
Informational
12/09/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2.
Sanitary Sewer Construction Inspection Partial 12/12/2022
Misc
Informational
12/06/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
12/06/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed.
Sanitary Sewer Construction Inspection Partial 12/21/2022
Misc
Informational
12/12/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
12/12/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70.
Water Line - Construction Inspection Partial 12/21/2022
Misc
Informational
09/30/2022
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3.
Site Visit Partial 12/21/2022
Misc
Informational
10/28/2022
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today.
Sanitary Sewer Construction Inspection Partial 01/06/2023
Misc
Informational
12/21/2022
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
12/21/2022
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20.
Water Line - Construction Inspection Partial 01/06/2023
Misc
Informational
12/21/2022
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes.
Sanitary Sewer Construction Inspection Partial 1/17/2023 1/17/2023 01/17/2023
Misc
Informational
01/06/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
01/06/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line
Water Line - Construction Inspection Partial 1/27/2023 1/27/2023 01/27/2023
Misc
Informational
01/06/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12
Water Line - Construction Inspection Partial 2/2/2023 2/2/2023 02/02/2023
Misc
Informational
01/27/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00
Water Line - Construction Inspection Partial 2/2/2023 2/2/2023 02/02/2023
Misc
Informational
02/02/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00
Water Line - Construction Inspection Partial 2/3/2023 2/3/2023 02/03/2023
Misc
Informational
02/02/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00
Storm Sewer Construction Inspection Partial 2/2/2023 02/06/2023
Misc
Informational
12/12/2022
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2. 1-24-23 RH. Contractor started placing Private Storm line 2. Started digging off of Storm Structure 1-3. 2-6-23 RH. Contractor started placing Private Storm Line 9. Rock had to be broken out so it will take time to be placed.
Storm Sewer Construction Inspection Partial 2/8/2023 2/8/2023 02/08/2023
Misc
Informational
02/06/2023
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2. 1-24-23 RH. Contractor started placing Private Storm line 2. Started digging off of Storm Structure 1-3. 2-6-23 RH. Contractor started placing Private Storm Line 9. Rock had to be broken out so it will take time to be placed. 2-8-23 PS Contractor setting storm box on private storm line 9
Site Visit Partial 2/15/2023 2/15/2023 02/15/2023
Misc
Informational
12/21/2022
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today
Erosion Control Inspection Partial 2/22/2023 2/22/2023 02/22/2023
Misc
Informational
11/21/2022
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Sanitary Sewer Construction Inspection Partial 3/2/2023 3/2/2023 03/02/2023
Misc
Informational
01/17/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
01/17/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1
Storm Sewer Construction Inspection Partial 03/03/2023
Misc
Informational
02/08/2023
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-9-22 RH. Contractor continued on Sanitary Line 1 from 12+20 Lot 9 and was at Lot 10 by AM. Work will stop once all Y's are installed that are on site. Contractor is looking into soil conditions. 1-24-23 RH. Contractor started placing Private Storm line 2. Started digging off of Storm Structure 1-3. 2-6-23 RH. Contractor started placing Private Storm Line 9. Rock had to be broken out so it will take time to be placed. 2-8-23 PS Contractor setting storm box on private storm line 9 2-21-23 RH. Sanitary stubs were being dug up from lot 1 to 14. All fill was being removed from site and woul be replaced from the stockpile on site.
Sanitary Sewer Construction Inspection Partial 03/06/2023
Misc
Informational
03/02/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/02/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench.
Water Line - Construction Inspection Partial 3/6/2023 3/6/2023 03/06/2023
Misc
Informational
02/03/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00 3-6-23 RH. Contractor started digging trench for public water line 1. Correct bedding was used.
Water Line - Construction Inspection Partial 03/08/2023
Misc
Informational
03/06/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00 3-6-23 RH. Contractor started digging trench for public water line 1. Correct bedding was used. 3-7-23 RH. Contractor continues to install public water line 1. 3-8-23 RH. Contrctor installed fire hydrant onto public water line 1.
Site Visit Partial 03/09/2023
Misc
Informational
02/15/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain.
Sanitary Sewer Construction Inspection Partial 3/13/2023 3/13/2023 03/13/2023
Misc
Informational
03/06/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/06/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1.
Sanitary Sewer Construction Inspection Partial 03/14/2023
Misc
Informational
03/13/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/13/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order.
Sanitary Sewer Construction Inspection Partial 03/15/2023
Misc
Informational
03/14/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/14/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in.
Sanitary Sewer Construction Inspection Partial 3/23/2023 3/23/2023 03/23/2023
Misc
Informational
03/15/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/15/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site.
Sanitary Sewer Construction Inspection Partial 3/27/2023 3/27/2023 03/27/2023
Misc
Informational
03/23/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/23/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20.
Storm Sewer Construction Inspection Partial 03/28/2023
Misc
Informational
03/03/2023
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-9-22 RH. Contractor continued on Sanitary Line 1 from 12+20 Lot 9 and was at Lot 10 by AM. Work will stop once all Y's are installed that are on site. Contractor is looking into soil conditions. 1-24-23 RH. Contractor started placing Private Storm line 2. Started digging off of Storm Structure 1-3. 2-6-23 RH. Contractor started placing Private Storm Line 9. Rock had to be broken out so it will take time to be placed. 2-8-23 PS Contractor setting storm box on private storm line 9 2-21-23 RH. Sanitary stubs were being dug up from lot 1 to 14. All fill was being removed from site and woul be replaced from the stockpile on site. 3-14-23 RH. Sanitary laterals started to be installed on sanitary line 1. Fill was all removed and laterals were installed onto the y's. 3-15-23 RH. Sanitary laterals continued to be placed from lots 4 to lots 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-28-23 RH. Sanitrary line 1 continues to be placed for lots 8 and continuing toward lot 14.
Sanitary Sewer Construction Inspection Partial 3/29/2023 3/29/2023 03/29/2023
Misc
Informational
03/27/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/27/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted.
Site Visit Partial 3/30/2023 3/30/2023 03/30/2023
Misc
Informational
03/09/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM.
Sanitary Sewer Construction Inspection Partial 03/31/2023
Misc
Informational
03/29/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/29/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench safely.
Sanitary Sewer Construction Inspection Partial 4/3/2023 4/3/2023 04/03/2023
Misc
Informational
03/31/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
03/31/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly.
Sanitary Sewer Construction Inspection Partial 04/04/2023
Misc
Informational
04/03/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
04/03/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3.
Sanitary Sewer Construction Inspection Partial 04/05/2023
Misc
Informational
04/04/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
04/04/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set.
Sanitary Sewer Construction Inspection Partial 4/6/2023 4/6/2023 04/06/2023
Misc
Informational
04/05/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
04/05/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set. 4-6-23 RH. Sanitary Line 1 was connected to MH1-3 from 1-2. Contractor then plans to start placing laterals off of the Y's for sanitary line 1.
Grading/Excavation/Fill Inspection Partial 4/6/2023 4/6/2023 04/06/2023
Misc
Informational
10/18/2022
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES Trinity Excavating grading area next to Longview Blvd. 10/3/22 ES Trinity Excavating finished grading area along Longview Blvd parking lot. 10/4/22 ES Trinity working on backfilling lot 68, and clearing area down around existing storm drainage basin. Preparing to place new storm structure for 48” outflow pipe. 10/17/22 ES
Misc
Informational
04/06/2023
4-6-23 RH. Contractor is grading road and filling site to grade.
Sanitary Sewer Construction Inspection Partial 4/12/2023 4/12/2023 04/12/2023
Misc
Informational
04/06/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
04/06/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set. 4-6-23 RH. Sanitary Line 1 was connected to MH1-3 from 1-2. Contractor then plans to start placing laterals off of the Y's for sanitary line 1. 4-11-23 RH. Sanitary line 1 continues to have laterals installed on the Y's. 4-12-23 RH. Sanitary Line 1 is having more laterals installed onto the y's.
Water Line - Construction Inspection Partial 04/12/2023
Misc
Informational
03/08/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00 3-6-23 RH. Contractor started digging trench for public water line 1. Correct bedding was used. 3-7-23 RH. Contractor continues to install public water line 1. 3-8-23 RH. Contrctor installed fire hydrant onto public water line 1. 4-12-23 RH. Contractor is running water line under road for private water to the future townhomes.
Water Line - Construction Inspection Partial 04/13/2023
Misc
Informational
04/12/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00 3-6-23 RH. Contractor started digging trench for public water line 1. Correct bedding was used. 3-7-23 RH. Contractor continues to install public water line 1. 3-8-23 RH. Contrctor installed fire hydrant onto public water line 1. 4-12-23 RH. Contractor is running water line crossings under road for private water to the future townhomes. 4-13-23 RH. Contractor continues to place crossing in road in preperation for concrete curb.
Water Line - Hydrostatic Test Partial 4/28/2023 4/28/2023 05/01/2023
Misc
Informational
05/01/2023
4-28-23 DP. Crew performed hydrostatic test of the "loop" private WM #3, 4 and 5. Tested at 150 psi for 2 hours. It passed.
Storm Sewer Construction Inspection Partial 4/28/2023 4/28/2023 05/01/2023
Misc
Informational
03/28/2023
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-9-22 RH. Contractor continued on Sanitary Line 1 from 12+20 Lot 9 and was at Lot 10 by AM. Work will stop once all Y's are installed that are on site. Contractor is looking into soil conditions. 1-24-23 RH. Contractor started placing Private Storm line 2. Started digging off of Storm Structure 1-3. 2-6-23 RH. Contractor started placing Private Storm Line 9. Rock had to be broken out so it will take time to be placed. 2-8-23 PS Contractor setting storm box on private storm line 9 2-21-23 RH. Sanitary stubs were being dug up from lot 1 to 14. All fill was being removed from site and woul be replaced from the stockpile on site. 3-14-23 RH. Sanitary laterals started to be installed on sanitary line 1. Fill was all removed and laterals were installed onto the y's. 3-15-23 RH. Sanitary laterals continued to be placed from lots 4 to lots 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-28-23 RH. Sanitrary line 1 continues to be placed for lots 8 and continuing toward lot 14. 4-28-23 DP. Crew is working on installing private storm sewer line 7
Sanitary Sewer - Vacuum Partial 5/2/2023 5/2/2023 05/02/2023
Misc
Informational
05/02/2023
5-2-23 DP. Crew performed vacuum tests on new Manholes 4-1,2-1 and 1-1 and they all passed.
Water Line - Construction Inspection Partial 5/8/2023 5/8/2023 05/09/2023
Misc
Informational
04/13/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00 3-6-23 RH. Contractor started digging trench for public water line 1. Correct bedding was used. 3-7-23 RH. Contractor continues to install public water line 1. 3-8-23 RH. Contrctor installed fire hydrant onto public water line 1. 4-12-23 RH. Contractor is running water line crossings under road for private water to the future townhomes. 4-13-23 RH. Contractor continues to place crossing in road in preperation for concrete curb. 5-8-23 DP. Contractor tied in water line 1 and also the loop at SW Brummel today. The line was flushed and restored.
Underground Electrical Inspection - Commercial Partial 5/10/2023 5/10/2023 05/10/2023
Misc
Corrective Action Required
05/10/2023
- Light bases , ground rod with wire attached, conduit in on Haverford plus 1 on East side of Curry
Sanitary Sewer - Vacuum Partial 5/24/2023 5/24/2023 05/24/2023
Misc
Informational
05/02/2023
5-2-23 DP. Crew performed vacuum tests on new Manholes 4-1,2-1 and 1-1 and they all passed. 5-24-23 DP. Crew preformed vacuum tests on New Manholes 1-2,1-3,1-4,4-2 and existing manholes after being restacked 35-410 and 35-411. All passed.
Sanitary Sewer - Air Test Partial 5/25/2023 5/25/2023 05/25/2023
Misc
Informational
05/25/2023
5-25-23 DP. Sanitary line 1 pressure test is failing so contractor is currently exposing trying to find the leak
Water Line - Coliform Test 1 Partial 5/25/2023 5/25/2023 05/25/2023
Misc
Informational
05/25/2023
5-23-23 DP. Sample 1- water line 1 was taken today 5-24-23 DP. Sample 1- Water line 1 passed
Water Line - Coliform Test 2 Partial 5/25/2023 5/25/2023 05/25/2023
Misc
Informational
05/25/2023
5-24-23 DP. Sample 2 water line 1 was taken 5-25-23 DP. Sample 2 water line 1 passed
Site Visit Partial 6/12/2023 6/12/2023 06/12/2023
Misc
Informational
03/30/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development
Pavement-Proof Roll Passed 6/21/2023 6/21/2023 06/21/2023
Misc
Informational
06/21/2023
6-19-23 DP. Crew passed their proof roll for road
Pavement-Surface Partial 6/21/2023 6/21/2023 06/21/2023
Misc
Informational
06/21/2023
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now
Pavement-Surface Partial 6/21/2023 6/21/2023 06/21/2023
Misc
Informational
06/21/2023
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt.
Site Visit Partial 6/23/2023 6/23/2023 06/23/2023
Misc
Informational
06/12/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs.
Pavement-Surface Partial 6/26/2023 6/26/2023 06/27/2023
Misc
Informational
06/21/2023
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project.
Pavement-Curb Construction Partial 6/26/2023 6/26/2023 06/27/2023
Misc
Informational
06/27/2023
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Water Line - Coliform Test 1 Partial 6/27/2023 6/27/2023 06/28/2023
Misc
Informational
05/25/2023
5-23-23 DP. Sample 1- water line 1 was taken today 5-24-23 DP. Sample 1- Water line 1 passed 6-27-23 DP. The water line loop was chlorinated at 3pm
Water Line - Coliform Test 1 Partial 6/29/2023 6/29/2023 06/29/2023
Misc
Informational
06/28/2023
5-23-23 DP. Sample 1- water line 1 was taken today 5-24-23 DP. Sample 1- Water line 1 passed 6-27-23 DP. The water line loop was chlorinated at 3pm 6-29-23 DP. Sample 1 on water line 2 was taken today
Water Line - Coliform Test 1 Passed 7/10/2023 7/10/2023 07/11/2023
Misc
Informational
06/29/2023
5-23-23 DP. Sample 1- water line 1 was taken today 5-24-23 DP. Sample 1- Water line 1 passed 6-27-23 DP. The water line loop was chlorinated at 3pm 6-29-23 DP. Sample 1 on water line 2 was taken today 6-30-23 DP. Sample 1 on waterline 2 passed.
Water Line - Coliform Test 2 Passed 7/3/2023 7/3/2023 07/11/2023
Misc
Informational
05/25/2023
5-24-23 DP. Sample 2 water line 1 was taken 5-25-23 DP. Sample 2 water line 1 passed 6-30-23 DP. Sample 2 water line 2 was taken 7-3-23 DP. Sample 2 water line 2 passed
Erosion Control Inspection Failed 7/24/2023 7/24/2023 07/24/2023
Misc
Informational
02/22/2023
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
07/24/2023
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Pavement-Curb Construction Partial 11/15/2023 11/15/2023 11/15/2023
Misc
Informational
06/27/2023
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
11/15/2023
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd.
Site Visit Partial 11/17/2023 11/17/2023 11/17/2023
Misc
Informational
06/23/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading.
Erosion Control Inspection Partial 12/4/2023 12/4/2023 12/04/2023
Misc
Informational
07/24/2023
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
07/24/2023
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/04/2023
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control.
Site Visit Partial 12/5/2023 12/5/2023 12/05/2023
Misc
Informational
11/17/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading. 12-5-23 DP. Collaborated with Ryan, Russ and Scott today to phase out the future phases.
Erosion Control Inspection Partial 12/20/2023 12/20/2023 12/20/2023
Misc
Informational
12/04/2023
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
12/04/2023
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/04/2023
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor.
Site Visit Partial 1/5/2024 1/5/2024 01/05/2024
Misc
Informational
12/05/2023
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading. 12-5-23 DP. Collaborated with Ryan, Russ and Scott today to phase out the future phases. 1-5-24 DP. The crew that was removing excess dirt got shut down once the snow started falling. They have mud tracked through the round a bout on longview. They are in the process of cleaning it up.
Pavement-Surface Partial 2/9/2024 2/9/2024 02/09/2024
Misc
Informational
06/27/2023
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project. 9-8-23 A.A laid asphalt along SW longview blvd 2-9-24 DP. Walked Curry Rd with Steve today, we painted out areas of asphalt and curb that will need to be removed before being restored.
Grading/Excavation/Fill Inspection Failed 3/11/2024 3/11/2024 03/11/2024
Misc
Informational
04/06/2023
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES Trinity Excavating grading area next to Longview Blvd. 10/3/22 ES Trinity Excavating finished grading area along Longview Blvd parking lot. 10/4/22 ES Trinity working on backfilling lot 68, and clearing area down around existing storm drainage basin. Preparing to place new storm structure for 48” outflow pipe. 10/17/22 ES
Misc
Informational
04/06/2023
4-6-23 RH. Contractor is grading road and filling site to grade. 3-11-24 DP. Bair did a proof roll on curry rd and it failed.
Curb - Proof Roll Passed 3/28/2024 3/28/2024 03/28/2024
Misc
Informational
03/28/2024
3-28-24 DP. Bair proof rolled Curry rd today with 21 tons. it passed
Water - Material Verification Passed 3/28/2024 3/28/2024 03/28/2024
Misc
Informational
09/30/2022
Win-Water delivered 8" C900 pipe, epoxy coated fittings, joints and gaskets. 9/28/22 ES Had 6" C900 pipe and additional fittings delivered for fire hydrant installs. 9/30/22 ES
Water Line - Hydrostatic Test Passed 3/28/2024 3/28/2024 03/28/2024
Misc
Informational
05/01/2023
4-28-23 DP. Crew performed hydrostatic test of the "loop" private WM #3, 4 and 5. Tested at 150 psi for 2 hours. It passed.
Water Line - Construction Inspection Passed 3/28/2024 3/28/2024 03/28/2024
Misc
Informational
05/09/2023
Tony's crew with Trinity Excavating was onsite today working on the private water line 3. They had about 100' of pipe laid, with tracer wire, with rock beneath and covering top of pipe. Waiting on 6" C900 pipe for fire hydrant connection and will continue laying pipe in the remainder of the trench they had dug. 9/29/22 ES Tony's crew working on line 3, they were installing the first fire hydrant assembly as a straight set. 9/30/22am ES Tony's crew installed first fire hydrant and continued our on line 3 to the north. 9/30/22 ES 12-20-22 RH. Water line started being installed for Water line 5. Going towards a T at waterline 3. 12-27-22 RH. Water line was started back up today. Water line was installed to 11+29 8” gate valve. Contractor continued to install water line after that. 12-28-22 RH. Water line continues to be installed to starting at 13+00. Gate valve was installed before the T. Thrust blocks will poured after line gets to the end. 12-29-22 RH. Water line continues at 13+35. Contractor is installing all bends and was doing vertical changes to the line to avoid the storm line going above it. Contractor plans to finish water line 5 today. Water line is being finished, and backfilled. Contractor will take pictures of thrust blocks and give to Ryan on Tuesday. Contractor will be starting on sewer monday. 1-3-22 RH. Water Line 5 was completed and contractor will not start on other lines until sanitary is finishes. 1-27-23 PS Contractor worked on water line #4, installing hydrant at 12+59 and valve box at 10+12 2-2-23 PS Contractor setting gate valve and backflow at vault box water line #3, 15+00. Contractor all set gate valve and backflow at vault box water line#4, 10+00 2-3-23 PS Contractor worked on honing and setting blocks for gate valve in vault box at water line #3, 15+00 3-6-23 RH. Contractor started digging trench for public water line 1. Correct bedding was used. 3-7-23 RH. Contractor continues to install public water line 1. 3-8-23 RH. Contrctor installed fire hydrant onto public water line 1. 4-12-23 RH. Contractor is running water line crossings under road for private water to the future townhomes. 4-13-23 RH. Contractor continues to place crossing in road in preperation for concrete curb. 5-8-23 DP. Contractor tied in water line 1 and also the loop at SW Brummel today. The line was flushed and restored.
Storm - Material Verification Passed 3/28/2024 3/28/2024 03/28/2024
Misc
Informational
10/29/2022
Trinity excavating had storm additional structures and ADS pipe delivered. 10/20/22 ES Storm structures: 1-3, 1-4, 1-5, 1-6, 1-8, 2-1, 4-1 were delivered from Forterra, along with barrel sections, second sections and lids. 1-6 base and second section split pipe coming into structure. 10/28/22 ES
Pavement-Curb Construction Partial 4/4/2024 4/4/2024 04/05/2024
Misc
Informational
11/15/2023
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
11/15/2023
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd. 4-4-24 DP. American Concrete is on site and formed and poured about 100' of curb on Curry road
Pavement-Curb Construction Partial 4/8/2024 4/8/2024 04/08/2024
Misc
Informational
04/05/2024
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
04/05/2024
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd. 4-4-24 DP. American Concrete is on site and formed and poured about 100' of curb on Curry road 4-8-24 DP. Crew in still onsite forming and pouring curb back along Curry Road.
Pavement-Curb Construction Partial 4/9/2024 4/9/2024 04/09/2024
Misc
Informational
04/08/2024
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
04/08/2024
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd. 4-4-24 DP. American Concrete is on site and formed and poured about 100' of curb on Curry road 4-8-24 DP. Crew in still onsite forming and pouring curb back along Curry Road. 4-9-24 DP. Crew is still on Curry Road. They poured around 60' today and have about the same amount formed up.
Pavement-Curb Construction Partial 4/11/2024 4/11/2024 04/11/2024
Misc
Informational
04/09/2024
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
04/09/2024
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd. 4-4-24 DP. American Concrete is on site and formed and poured about 100' of curb on Curry road 4-8-24 DP. Crew in still onsite forming and pouring curb back along Curry Road. 4-9-24 DP. Crew is still on Curry Road. They poured around 60' today and have about the same amount formed up. 4-11-24 DP. American Concrete is still on site working on pouring back curb. They have the final areas formed up now. Pouring tomorrow.
Pavement-Curb Construction Partial 4/12/2024 4/12/2024 04/12/2024
Misc
Informational
04/11/2024
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
04/11/2024
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd. 4-4-24 DP. American Concrete is on site and formed and poured about 100' of curb on Curry road 4-8-24 DP. Crew in still onsite forming and pouring curb back along Curry Road. 4-9-24 DP. Crew is still on Curry Road. They poured around 60' today and have about the same amount formed up. 4-11-24 DP. American Concrete is still on site working on pouring back curb. They have the final areas formed up now. Pouring tomorrow. 4-12-24 DP. American Concrete finished repouring the curb on curry today.
Pavement-Surface Partial 4/22/2024 4/22/2024 04/23/2024
Misc
Informational
02/09/2024
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project. 9-8-23 A.A laid asphalt along SW longview blvd 2-9-24 DP. Walked Curry Rd with Steve today, we painted out areas of asphalt and curb that will need to be removed before being restored. 4-22-24 DP. Hanarhan restored base asphalt on Curry Road using 263.32 tons of type 2-01 asphalt
Erosion Control Inspection Failed 4/26/2024 4/26/2024 04/26/2024
Misc
Informational
12/20/2023
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
12/20/2023
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/20/2023
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible.
Erosion Control Inspection Partial 4/30/2024 4/30/2024 04/30/2024
Misc
Informational
04/26/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
04/26/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
04/26/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up
Erosion Control Inspection Failed 5/6/2024 5/6/2024 05/06/2024
Misc
Informational
04/30/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
04/30/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
04/30/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned.
Sanitary Sewer Construction Inspection Partial 11/29/2023 11/29/2023 05/15/2024
Misc
Informational
04/12/2023
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
04/12/2023
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set. 4-6-23 RH. Sanitary Line 1 was connected to MH1-3 from 1-2. Contractor then plans to start placing laterals off of the Y's for sanitary line 1. 4-11-23 RH. Sanitary line 1 continues to have laterals installed on the Y's. 4-12-23 RH. Sanitary Line 1 is having more laterals installed onto the y's.
Sanitary Sewer Construction Inspection Partial 6/4/2024 6/4/2024 06/04/2024
Misc
Informational
05/15/2024
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
05/15/2024
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set. 4-6-23 RH. Sanitary Line 1 was connected to MH1-3 from 1-2. Contractor then plans to start placing laterals off of the Y's for sanitary line 1. 4-11-23 RH. Sanitary line 1 continues to have laterals installed on the Y's. 4-12-23 RH. Sanitary Line 1 is having more laterals installed onto the y's.
Miscellaneous Correction
Corrective Action Required
06/04/2024
6-4-24 DP. There is an unnecessary WYE on the sewer main that runs down Curry road. It has infiltration pouring into the wye. Per LS water, this WYE will need to be removed and replaced with a straight piece of pipe and 2 max adapters. I noticed yesterday that there is a Service WYE missing for lot 65. On the FDP 5th submittal plans this shows a wye and sewer stub ran to Lot 65. That will also need to be installed. Once these corrections are completed, we will need to perform an air pressure tested on that section of sewer main. Mike with O'Reilly Build has been notified.
Sanitary Sewer Construction Inspection Partial 6/19/2024 6/19/2024 06/20/2024
Misc
Informational
06/04/2024
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
06/04/2024
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set. 4-6-23 RH. Sanitary Line 1 was connected to MH1-3 from 1-2. Contractor then plans to start placing laterals off of the Y's for sanitary line 1. 4-11-23 RH. Sanitary line 1 continues to have laterals installed on the Y's. 4-12-23 RH. Sanitary Line 1 is having more laterals installed onto the y's.
Miscellaneous Correction
Corrective Action Required
06/04/2024
6-4-24 DP. There is an unnecessary WYE on the sewer main that runs down Curry road. It has infiltration pouring into the wye. Per LS water, this WYE will need to be removed and replaced with a straight piece of pipe and 2 max adapters. I noticed yesterday that there is a Service WYE missing for lot 65. On the FDP 5th submittal plans this shows a wye and sewer stub ran to Lot 65. That will also need to be installed. Once these corrections are completed, we will need to perform an air pressure tested on that section of sewer main. Mike with O'Reilly Build has been notified. 6-19-24 DP. Troy's crew removed unecessary wye and installed a wye and stub for lot 65
Erosion Control Inspection Partial 6/25/2024 6/25/2024 06/25/2024
Misc
Informational
05/06/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
05/06/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
05/06/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Pavement-Surface Partial 7/24/2024 7/24/2024 07/24/2024
Misc
Informational
04/23/2024
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project. 9-8-23 A.A laid asphalt along SW longview blvd 2-9-24 DP. Walked Curry Rd with Steve today, we painted out areas of asphalt and curb that will need to be removed before being restored. 4-22-24 DP. Hanarhan restored base asphalt on Curry Road using 263.32 tons of type 2-01 asphalt
Misc
Informational
07/24/2024
7-24-24 DP. All American concrete passed a proof roll on the subgrade for Alleyway 1. They are working on compacting AB3 right now.
Site Visit Partial 7/26/2024 7/26/2024 07/26/2024
Misc
Informational
01/05/2024
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading. 12-5-23 DP. Collaborated with Ryan, Russ and Scott today to phase out the future phases. 1-5-24 DP. The crew that was removing excess dirt got shut down once the snow started falling. They have mud tracked through the round a bout on longview. They are in the process of cleaning it up. 7-26-24 DP. No site work for FEI today
Erosion Control Inspection Failed 8/15/2024 8/15/2024 08/15/2024
Misc
Informational
06/25/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
06/25/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
06/25/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
08/15/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up.
Erosion Control Inspection Failed 8/20/2024 8/20/2024 08/20/2024
Misc
Informational
08/15/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
08/15/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
08/15/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
08/15/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads.
Erosion Control Inspection Failed 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
08/20/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
08/20/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
08/20/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
08/20/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures.
Site Visit Partial 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
07/26/2024
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading. 12-5-23 DP. Collaborated with Ryan, Russ and Scott today to phase out the future phases. 1-5-24 DP. The crew that was removing excess dirt got shut down once the snow started falling. They have mud tracked through the round a bout on longview. They are in the process of cleaning it up. 7-26-24 DP. No site work for FEI today 9-4-24 DP. All american was starting to pour private sidewalk behind buildings 3 and 4 close to brummel rd. They have also started to prep the alley approach that needs completed before TCO on buildings 1 and 2.
Pavement-Surface Partial 9/3/2024 9/3/2024 09/06/2024
Misc
Informational
07/24/2024
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project. 9-8-23 A.A laid asphalt along SW longview blvd 2-9-24 DP. Walked Curry Rd with Steve today, we painted out areas of asphalt and curb that will need to be removed before being restored. 4-22-24 DP. Hanrahan restored base asphalt on Curry Road using 263.32 tons of type 2-01 asphalt 9-3-24 DP. Hanrahan completed surface asphalt from Longview to SW Brummel Rd on Curry road which is what is needed for occupancy.
Misc
Informational
07/24/2024
7-24-24 DP. All American concrete passed a proof roll on the subgrade for Alleyway 1. They are working on compacting AB3 right now.
Pavement-Surface Partial 9/5/2024 9/5/2024 09/06/2024
Misc
Informational
09/06/2024
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project. 9-8-23 A.A laid asphalt along SW longview blvd 2-9-24 DP. Walked Curry Rd with Steve today, we painted out areas of asphalt and curb that will need to be removed before being restored. 4-22-24 DP. Hanrahan restored base asphalt on Curry Road using 263.32 tons of type 2-01 asphalt 9-3-24 DP. Hanrahan completed surface asphalt from Longview to SW Brummel Rd on Curry road which is what is needed for occupancy.
Misc
Informational
09/06/2024
7-24-24 DP. All American concrete passed a proof roll on the subgrade for Alleyway 1. They are working on compacting AB3 right now. 9-5-24 DP. All American poured the final approach to Alleyway 1.
Erosion Control Inspection Partial 9/10/2024 9/10/2024 09/10/2024
Misc
Informational
09/04/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
09/04/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
09/04/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
09/04/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up.
Sidewalk Inspection Partial 9/13/2024 9/13/2024 09/13/2024
Misc
Informational
09/13/2024
9-13-24 DP. I met Lyle with All American concrete onsite to work through how to get the sidewalk along Curry Rd. ADA compliant. Bob Burns came onsite and we determined that we need to run a form from the storm box to the ADA pad which will be A to B. There is no other option of getting the sidewalk closer to compliance. Once Lyle gets the SW formed, I will check the running slope and try to get it as close as possible.
Site Visit Partial 9/16/2024 9/16/2024 09/16/2024
Misc
Informational
09/04/2024
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading. 12-5-23 DP. Collaborated with Ryan, Russ and Scott today to phase out the future phases. 1-5-24 DP. The crew that was removing excess dirt got shut down once the snow started falling. They have mud tracked through the round a bout on longview. They are in the process of cleaning it up. 7-26-24 DP. No site work for FEI today 9-4-24 DP. All american was starting to pour private sidewalk behind buildings 3 and 4 close to brummel rd. They have also started to prep the alley approach that needs completed before TCO on buildings 1 and 2. 9-16-24 DP. No work for FEI today. All American is planning on replacing the section of private sidewalk with the step by the ADA pad tomorrow.
Pavement-Surface Passed 10/10/2024 10/10/2024 10/11/2024
Misc
Informational
09/06/2024
6-21-23. Crew is laying down base asphalt today. They are using type 2 recycled and installing in two different lifts. The first lift is 3" and completed, they are working on their 2" lift now 6-21-23 DP. Crew finished both lifts of base today on the entire project except on SW Brummel. It was still too hot. They do have 1 lift down on SW Brummel. On Monday they are going to do the second Base Lift on SW Brummel and then they will begin with laying Surface on all of the roads, finishing with surface asphalt on SW Brummel. The laid 1,084.09 tons of type 2-01 Base Asphalt today. I am also having the concrete crew install temporary curbs at all of the Alley throats before laying surface asphalt. 6-26-23 Crew went back and finished laying the second base life on SW Brummel but did not surface anything. They finished Brummel with 200 tons of base totaling 1,284.09 tons of base asphalt for the project. 9-8-23 A.A laid asphalt along SW longview blvd 2-9-24 DP. Walked Curry Rd with Steve today, we painted out areas of asphalt and curb that will need to be removed before being restored. 4-22-24 DP. Hanrahan restored base asphalt on Curry Road using 263.32 tons of type 2-01 asphalt 9-3-24 DP. Hanrahan completed surface asphalt from Longview to SW Brummel Rd on Curry road which is what is needed for occupancy. 10-10-24 DP. Hanrahan was onsite and finished laying surface asphalt today. They had to finish surface on Curry Rd and Haversford. They used 275.98 tons of Type 3 virgin asphalt
Misc
Informational
09/06/2024
7-24-24 DP. All American concrete passed a proof roll on the subgrade for Alleyway 1. They are working on compacting AB3 right now. 9-5-24 DP. All American poured the final approach to Alleyway 1.
Erosion Control Inspection Partial 10/14/2024 10/14/2024 10/14/2024
Misc
Informational
09/10/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
09/10/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
09/10/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
09/10/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well.
Water Service Inspection Failed 10/21/2024 10/21/2024 10/21/2024
Miscellaneous Correction
Corrective Action Required
10/21/2024
10-21-24 DP. This was sent in an email form to Jacob. On the front: 441- Mostly ok, just needing to dig out mud and add clean gravel closer to the setter nuts 443- Top of meter is 5” below sod, bottom needs mud removed and gravel added. Meter depth will be approximately 22” once pit gets raised. 445- ok 447- Top of lid is 3” below grade, mud needs cleaned out of bottom of pit and gravel added, meter depth should be ok once riser on pit is added, but needs to be rechecked. 449-Top of lid is 4” below grade, bottom of pit needs mud removed and gravel added, meter depth should be ok once riser on pit is added, but needs to be rechecked. 451- Top of pit is 3” below grade, bottom of pit needs to be cleaned out with gravel put back in. The meter depth is currently at 18”, so a riser would make this out of spec. 453- Top of lid is 3” below grade, meter depth looks like It will be ok with riser, but will need rechecked. Bottom of pit needs mud removed and gravel added. 455- add some gravel to bottom of pit, otherwise ok 457- top of lid is 3” below grade with a meter depth at 16.5”. This depth should be ok after riser, but will need rechecked. 459- ok 461- ok 463- ok 465- ok 467- pit is collapsed and needs to be replaces. On the back: 440- needs mud removed, gravel added 442- needs mud removed, gravel added 444- needs mud removed, gravel added 446- 21.5” deep, meter needs raised 448- ok 450- clean out box and broken lid from bottom of meter pit, adjust pit so meter setter isn’t pushed up against side of pit. 452- Clean out bottom of meter pit, add rock and also raise the meter. It is currently at 20” in depth. 454- Raise meter depth. Currently at 22” deep 456- Raise meter depth. Currently at 22” deep. 458- Raise meter depth. Currently at 23” deep.
Water Service Inspection Partial 10/24/2024 10/24/2024 10/24/2024
Miscellaneous Correction
Corrective Action Required
10/21/2024
10-21-24 DP. This was sent in an email form to Jacob. On the front: 441- Mostly ok, just needing to dig out mud and add clean gravel closer to the setter nuts 443- Top of meter is 5” below sod, bottom needs mud removed and gravel added. Meter depth will be approximately 22” once pit gets raised. 445- ok 447- Top of lid is 3” below grade, mud needs cleaned out of bottom of pit and gravel added, meter depth should be ok once riser on pit is added, but needs to be rechecked. 449-Top of lid is 4” below grade, bottom of pit needs mud removed and gravel added, meter depth should be ok once riser on pit is added, but needs to be rechecked. 451- Top of pit is 3” below grade, bottom of pit needs to be cleaned out with gravel put back in. The meter depth is currently at 18”, so a riser would make this out of spec. 453- Top of lid is 3” below grade, meter depth looks like It will be ok with riser, but will need rechecked. Bottom of pit needs mud removed and gravel added. 455- add some gravel to bottom of pit, otherwise ok 457- top of lid is 3” below grade with a meter depth at 16.5”. This depth should be ok after riser, but will need rechecked. 459- ok 461- ok 463- ok 465- ok 467- pit is collapsed and needs to be replaces. On the back: 440- needs mud removed, gravel added 442- needs mud removed, gravel added 444- needs mud removed, gravel added 446- 21.5” deep, meter needs raised 448- ok 450- clean out box and broken lid from bottom of meter pit, adjust pit so meter setter isn’t pushed up against side of pit. 452- Clean out bottom of meter pit, add rock and also raise the meter. It is currently at 20” in depth. 454- Raise meter depth. Currently at 22” deep 456- Raise meter depth. Currently at 22” deep. 458- Raise meter depth. Currently at 23” deep. 10-24-24 DP. Bair is onsite and started working away at the above list. I printed this list out and handed it to the contractor onsite.
Grading/Excavation/Fill Inspection Passed 10/31/2024 10/31/2024 10/31/2024
Misc
Informational
03/11/2024
Trinity Excavating onsite grading. 9/6/22 ES Trinity Excavating onsite grading. 9/7/22 ES Trinity Excavating onsite grading. 9/8/22 ES Trinity Excavating onsite grading. 9/9/22 ES Trinity Excavating onsite grading. 9/12/22 ES Trinity Excavating onsite grading. 9/13/22 ES Trinity Excavating onsite grading. 9/14/22 ES Trinity Excavating onsite grading. 9/15/22 ES Hauling dirt from pile off site. 9/26/22 ES Trinity Excavating grading area next to Longview Blvd. 10/3/22 ES Trinity Excavating finished grading area along Longview Blvd parking lot. 10/4/22 ES Trinity working on backfilling lot 68, and clearing area down around existing storm drainage basin. Preparing to place new storm structure for 48” outflow pipe. 10/17/22 ES
Misc
Informational
03/11/2024
4-6-23 RH. Contractor is grading road and filling site to grade. 3-11-24 DP. Bair did a proof roll on curry rd and it failed. 10-31-24 DP. All grading around buildings 1-4 have been completed.
Pavement-Curb Construction Passed 10/31/2024 10/31/2024 10/31/2024
Misc
Informational
04/12/2024
6-26-23 DP. All curb work for the project has been complete including the temporary curbs i had them pour at each alley way before laying asphalt.
Misc
Informational
04/12/2024
11-15-23 DP. Crew is cleaning up on curry and has a contractor doing precision cutting in preparation for the reconstruction on Curry Rd. 4-4-24 DP. American Concrete is on site and formed and poured about 100' of curb on Curry road 4-8-24 DP. Crew in still onsite forming and pouring curb back along Curry Road. 4-9-24 DP. Crew is still on Curry Road. They poured around 60' today and have about the same amount formed up. 4-11-24 DP. American Concrete is still on site working on pouring back curb. They have the final areas formed up now. Pouring tomorrow. 4-12-24 DP. American Concrete finished repouring the curb on curry today. 10-31-24 DP. All curb has been installed onsite.
Sanitary - Material Verification Passed 10/31/2024
Misc
Informational
10/29/2022
Had SDR26 sewer pipe delivered, along with fittings. 9/30/22 ES Had manhole structures delivered. 10/3/22 ES Manhole bases for: 1-1, 1-2, 1-3, 1-4, 4-1 and 4-2 delivered along with barrel and cone sections. 10/28/22 ES
Sanitary Sewer - Air Test Passed 10/31/2024
Misc
Informational
05/25/2023
5-25-23 DP. Sanitary line 1 pressure test is failing so contractor is currently exposing trying to find the leak
Erosion Control Inspection Partial 11/19/2024 11/19/2024 11/19/2024
Misc
Informational
10/14/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
10/14/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
10/14/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
10/14/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated.
Sanitary Sewer - Vacuum Passed 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
05/24/2023
5-2-23 DP. Crew performed vacuum tests on new Manholes 4-1,2-1 and 1-1 and they all passed. 5-24-23 DP. Crew preformed vacuum tests on New Manholes 1-2,1-3,1-4,4-2 and existing manholes after being restacked 35-410 and 35-411. All passed.
Sanitary Sewer Construction Inspection Passed 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
06/20/2024
Tony's crew was onsite digging holes for sanitary sewer wye cut ins. 10/4/22 ES Tony's crew had exposed 8" pvc sewer main and were setting their trench boxes to begin cutting out sections to install wyes. They had SDR26 wyes and max adapter couplings onsite. Will begin work tomorrow if they receive their pump to perform bypass on sewer main. Also let them know we needed at least 4' in between any fittings, this might require them to cut out a little further if they encountered bells in their connection holes. 10/5/22 ES Spoke with Tony and Scott with Trinity Excavating about concerns with location of lot 71's sanitary sewer stub in correlation to the new MH 2-1. It appears this connection will be too close(within 4' of outside wall of the new MH) and will need to most likely be moved to the East side of this new MH. 10/5/22 ES Tony's crew had fusible pipe completed today. Plugged MH 35-411 and bypass pumped to MH 35-410 and installed wye connection for lot 66 on existing 8" SDR26 sanitary sewer line. 10/6/22 ES Tony's crew worked on installing wyes on existing 8" public sanitary line. Installed lots 67 and 69 wyes while bypass pumping using MH 35-411 to 35-410 again. 10/7/22 ES Tony's crew working on laying out laterals for the wyes they had cut in. Had lot 66 laid and working on lot 67. 10/10/22 ES Tony's crew working on backfilling pipe lot 66 and 67, They had placed a solid block under each wye connection for additional support. We also talked about getting their impervious trench checks put in and explained specs from the detail sheet for those. 10/11/22 ES Tony’s crew poured ditch checks for lot 66, 67, and 69 laterals. Backfilled lots 67 and 69 lateral lines marking end of pipe with white pvc standpipes. Also began digging for lot 68 lateral install. While digging for lot 68 uncovered 2 existing Tee connections. Spoke with Steve and Kent regarding these and it was determined they will need to cut both Tee connections out and replace with just the single wye as indicated on plans. Shared an older set of prints with Tony showing him we might run into this same scenario as we work closer towards lot 75. 10/12/22 ES Tony's crew finished backfilling open holes from lots 66 and 69 lateral installs. Then they completed the cut in of the new wye on lot 68 using 2 max adapters, and cutting out the two existing tee connections that were exposed in their hole. They ran 1 stick of 4" SDR26 pipe out of wye to continue their lateral construction. 10/14/22 ES Trinity crew set MH 2-1 and service wye for lot 71. The wye for lot 71 was installed ~4.5' to the east of MH 2-1 as where it was designed on plans was outside of DNC specs. 10/27/22 ES Tony's crew worked on laying pipe out for lot 71 service, and began working out on private line 2 from MH 2-1. 10/28/22 ES Trinity crew installed 3 sticks of 8" SDR26 pipe from MH 2-1 towards MH 2-2 and plugged pipe and marked at ground level. Also began digging holes to prepare for installation of MH 1-1 and service for lot 65. These installations will take place early next week, they are closing NB Longview Blvd in order to pump around existing manholes. 10/29/22 ES
Misc
Informational
06/20/2024
Trinity crew installed MH 1-1 inline on existing public main for new private sanitary line 1. Also installed service wye for lot 65. 10/31/22 ES 11-2-22 RH. Sanitary MH 4-1 was placed connecting to exciting Sanitary. They used Max adapters to connect to the main line. The inlet will not be poured until tomorrow. One of the sides of the pipe did not line up correctly vertically but contractor installed and said that it was ok. Trinity crew worked on pouring inverts in new manholes 1-1, 2-1, and 4-1. Also began stacking out MH 1-1 and 2-1 and backfilling in prior to rain. 11/3/22 ES Trinity crew worked on digging out service for lot 65 to run lateral pipe. Also began putting barrel sections on MH 2-1 and 4-1. 11/7/22 ES 1-14-22 RH. Lateral continue to be dug and placed connecting to exciting Sanitary main between Exciting Sanitary MH and MH 4-1. 3 Y’s were placed today. 11-16-22 RH. Crew started connecting stubs to Y’s placed on the 14th. Rock had to be broke out to place stubs. Trinity crew working on lateral for lot 76, had lots 77 and 78 dug up, but had not cut in wye connections. 11/17/22am ES 11-17-22 RH. Contractor started setting up to cut in Y’s for Lots 78 and 79. Contractor plugged the area up stream and cut in Y. Y was then plugged. Trinity crew was working on laying pipe towards 4-2 and set base for 4-2. 11/21/22 ES 12-2-22 RH. Sanitary crew began digging out tench from sanitary from 1-1 to 1-2. 12-5-22 RH. Contractor started filling around Sanitary MH 1-1 and while compacting moved the top sections. They are now going to take apart and put back together before continuing toward 1-2. 12-6-22 RH. Contractor has decided to use aggregate to encase sanitary in the ground instead of fill on jobsite. 12-7-22 RH. Contractor is continuing toward MH 1-2. The y for Lot 1 was placed. 12-14-22 RH. Contractor installed Sanitary MH 1-2. They then started running the Stubs for Lots 65 and 66. They planned to continue to lots 67 and on now that the old storm structure pipe was out of the way. 12-15-22 RH. Contractor continues to install stubs for Lots. Stubs 67 and 68 were being placed while on site. Contractor plans to install stub 69 as well today. Stub was place for lot 69. 12-16-22 RH. Contractors are breaking out rock to continue to place sanitary line. Contractor is also placing the stub for Lot 70. 12-28-22 RH. Contractor is starting to dig the Sanitary Line 1 again. They are going to dig stubs as they dig the main. 1-4-23 RH. Contractor started on sanitary today on Line 1. Contractor will dig a long trench installing the 8” main and then start installing rest of the stubs for each property. Contractor was able to get to 11+00 when they had to stop work. 1-5-23 RH. Contractor continued to dig the Sanitary Line 1 starting at 11+00. AM inspection showed they had placed line up to lot 5 with Y's being installed as they dug out the trench. Contractor got to lot 7. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-17-23 PS Contractor is going to begin clearing soil that has caved in to trench and discussed beginning construction on sewer line 3-2-23 Contractor excavating and removing soil for install of sanitary line#1 3-6-23 RH. Contractor continues to dig out out the lateral for Line 1. The contractor is moving all fill to avoid more fill from falling into trench. 3-13-23 PS Contractor excavating and preparing for installation of sanitary laterals and sanitary line#1. 3-14-23 RH. Erosion Control is up and in working order. 3-15-23 RH. Sanitary laterals continued to be placed from 4 to 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-27-23 RH. Sanitary line 1 continues to have laterals dug out and attached to Y's for lots 8 and 20. 3-29-23 RH. Sanitary Line 1 was found to be out of grade when installing laterals. When investigated it was found to be due to MH 1-2 being off grade so entire main and laterals were removed. MH 1-2 will be adjusted. 3-31-23 RH. Sanitary line 1 was completely removed. Contractor is now filling trench back in so they can redig trench for the sanitary line safely. 4-3-23 RH. Sanitary line 1 is now being re dug and replaced now that MH 1-2 is fixed. Line 1 will be placed and Y's being placed correctly. 4-4-23 RH. Sanitary Line 1 continues to be reinstalled from 1-2 toward 1-3. 4-5-23 RH. Sanitary Line 1 was ran all the way to MH 1-3 and structure began to be set. 4-6-23 RH. Sanitary Line 1 was connected to MH1-3 from 1-2. Contractor then plans to start placing laterals off of the Y's for sanitary line 1. 4-11-23 RH. Sanitary line 1 continues to have laterals installed on the Y's. 4-12-23 RH. Sanitary Line 1 is having more laterals installed onto the y's.
Miscellaneous Correction
Corrective Action Required
06/20/2024
6-4-24 DP. There is an unnecessary WYE on the sewer main that runs down Curry road. It has infiltration pouring into the wye. Per LS water, this WYE will need to be removed and replaced with a straight piece of pipe and 2 max adapters. I noticed yesterday that there is a Service WYE missing for lot 65. On the FDP 5th submittal plans this shows a wye and sewer stub ran to Lot 65. That will also need to be installed. Once these corrections are completed, we will need to perform an air pressure tested on that section of sewer main. Mike with O'Reilly Build has been notified. 6-19-24 DP. Troy's crew removed unecessary wye and installed a wye and stub for lot 65
Sidewalk Inspection Passed 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
09/13/2024
9-13-24 DP. I met Lyle with All American concrete onsite to work through how to get the sidewalk along Curry Rd. ADA compliant. Bob Burns came onsite and we determined that we need to run a form from the storm box to the ADA pad which will be A to B. There is no other option of getting the sidewalk closer to compliance. Once Lyle gets the SW formed, I will check the running slope and try to get it as close as possible.
Site Visit Complete 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
09/16/2024
No site work being performed today. 9/27/22 ES No site work being performed today. 9/28/22 ES No utility work being done, only grading along Longview Blvd. 10/3/22 ES No work being performed on 10/24 or 10/25 due to rain/mud. 10/25/22 ES 12-21-22 RH. No work on site today. 2-15-23 PS No work on site today 3-9-23 RH. No work for development today due to rain. 3-30-23 RH. Now work being completed for development in the AM. 6-12-23 DP. No work for development 6-23-23 DP. I had contractor install temporary curbs at every alley way before surface asphalt goes down which is on monday. Today the contractor installed all temp curbs. 11-17-23 DP. Builder has hired Bair to reconstruct the road. They are on site cleaning up and backfilling the trenches. I scheduled Waters sewer bond inspection for 11-27-23. Trinity is also still on site backfilling curbs and doing some grading. 12-5-23 DP. Collaborated with Ryan, Russ and Scott today to phase out the future phases. 1-5-24 DP. The crew that was removing excess dirt got shut down once the snow started falling. They have mud tracked through the round a bout on longview. They are in the process of cleaning it up. 7-26-24 DP. No site work for FEI today 9-4-24 DP. All american was starting to pour private sidewalk behind buildings 3 and 4 close to brummel rd. They have also started to prep the alley approach that needs completed before TCO on buildings 1 and 2. 9-16-24 DP. No work for FEI today. All American is planning on replacing the section of private sidewalk with the step by the ADA pad tomorrow.
Storm Sewer Construction Inspection Passed 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
05/01/2023
Trinity Excavating had 2 crews onsite working on clearing around existing storm basin area. Preparing to set new storm outlet structure. 10/17/22 ES Tony's crew was working on digging out site for box 1-1. 10/18/22 ES Tony's crew continued working on site for box 1-1. Existing 42" pipe was sitting on bedrock that had to be broken out prior to setting box 1-1. Existing 42" pipe was cracked through and needed to be banded and coupled with a short piece of 42" pipe from existing pipe removed. Elevations were off for flow line and box sits ~6" high. Will need to modify incoming flow line from box 1-2 in order to get 1-1 set on existing storm pipe. 10/19/22 ES Tony's crew got box 1-1 set, band coupling existing piece of pipe and piece going into box added. Started running 36" pipe out towards structure 1-2(new flow will be close to 1.6%. 10/20/22 ES Tony's crew continued on public storm line 1, making it to box 1-2 with 36" HDPE line, but still don't have structure 1-2. on site to continue from this point. 10/21/22 ES Trinity Excavating crews poured collars around 42" outlet pipe and 36" inlet pipe in box 1-1 and poured invert. 10/27/22 ES Trinity crew continued working on public line 1 and set box 1-2. 10/28/22 ES Trinity crew laid final piece of 36" outflow pipe into box 1-2. The area going towards 1-3 was too sloppy to continue construction towards that box. 10/29/22 ES Trinity crew continued working on storm line 1. Set curb inlet box 1-3 and laid 5 sticks of 36" pipe out towards box 1-4. Have concrete called in for tomorrow morning to work on collars and inverts on 1-2 and 1-3 and sanitary MH 1-1, 2-1, and 4-1. 11/2/22 ES Trinity crew continued working towards box 1-4 on storm line 1. They got the box set in ground, but not completely to grade. They poured collars on boxes 1-2 and 1-3. 11/3/22 ES Trinity crew continued working on storm line 1. They had a couple sticks of pipe float in the ditch on them and had to reset them between boxes 1-3 and 1-4. They got those sticks laid and set box 1-4 base. 11/7/22 ES 11-9-22 RH. Crew continued to lay storm line to 1-4. Crew was using correct bedding of rock. Compaction was also being tested on site by a 3rd party QC. 11-10-22 RH. Crew Poured inlet and Collars for Line 1 1-2, 1-3, and 1-4. Contractor then went to breaking bed rock between 1-4 and 1-5 so they could continue to place more line. 11-14-22 RH. Crew continues to break rock out between Storm 1-4 and 1-5. 2 sticks of pipe were layer. 11-16-22 RH. Crew continues to break rock out to placed storm structure 1-5. Trinity crew working on storm line 1. Placed structure 1-5, but alignment wasn’t correct. Spencer was working with surveyors and determined their marks needed corrected. They were also stacking out boxes 1-2 and 1-3. 11/17/22am ES Spoke with Spencer this AM about the concerns we had with how box 1-5 was cut and the lack of any solid concrete to tie into for rebar bracing if repouring side of box. Let them know if we got shop drawings from the manufacturer or other documentation that they would deem the structure sound and could show a way to reinforce box we might let it stay, but that would likely require the complete reconstruction of the western side of box going towards box 1-6. We noted that the northern side would be ok as long as sufficient rebar reinforcing was placed as their dowel locations showed. 11/21/22am ES Based upon our conversation this morning Trinity crew started digging out and breaking rock to set box 1-6 in order to continue on public storm line 1 install until a solution for box 1-5 was reached. 11/21/22 ES 12-1-22 RH. Crew continued to dig out Stormline 1. Storm Structure 1-6 was set and they continued toward structure 1-7. Contractor installed storm structure 1-7 and continued to 1-8. 1-8 was installed and that was crew was stopping for the day before continuing on. Other areas were being filled in above the piping. 12-2-22 RH. Crew started running pipe from Structure 1-8 to Structure 1-9. Contractor also plans to start stacking storm structures and drilling dowels into structure 1-5 due to mis designed flow lines when structure was made. 12-5-22 RH. Contractor is going to fix structure 1-5 today by drilling into structure and using rebar to fill in holes when structure was design incorrectly. Contractor will also continue to dig toward storm inlet 1-9 from 1-8. 12-6-22 RH. Contractor is pouring Storm Inlets and Collars for 1-5 and 1-6. Fixes were also completed on storm box 1-5 with concrete and rebar. Crew plans to move on to inlets 1-7 inlet and collars once 1-6 is complete. Storm box 1-9 was placed today and contractor will continue to dig towards inlet 1-10. 12-7-22 RH. Contractor continues to run storm from 1-9 to 1-10. Felt continues to be used around piping in ground with correct aggregate bedding. Storm box 1-10 was installed and tied into the exciting system. Backfilling pipe rest of the day. 12-9-22 RH. Contractor started pouring inlets and collars for storm structures still open. 12-12-22 RH. Contractor installed storm structure 8-1 and will stub out toward 8-2. 15” HDPE was used between 8-1 and 1-8. Contractor will not start working out from 1-8 to structure 6-1. Once 6-1 was set contractor continued toward 6-2. 1-6-23 RH. Contractor continues to lay sanitary line 1 with trench falling in. Once the trench box is moved the sides of trench fall in. They will dig out the material that fell in to start compacting over the line. Contractor has placed line up to Lot 9 station 12+20. 1-9-22 RH. Contractor continued on Sanitary Line 1 from 12+20 Lot 9 and was at Lot 10 by AM. Work will stop once all Y's are installed that are on site. Contractor is looking into soil conditions. 1-24-23 RH. Contractor started placing Private Storm line 2. Started digging off of Storm Structure 1-3. 2-6-23 RH. Contractor started placing Private Storm Line 9. Rock had to be broken out so it will take time to be placed. 2-8-23 PS Contractor setting storm box on private storm line 9 2-21-23 RH. Sanitary stubs were being dug up from lot 1 to 14. All fill was being removed from site and woul be replaced from the stockpile on site. 3-14-23 RH. Sanitary laterals started to be installed on sanitary line 1. Fill was all removed and laterals were installed onto the y's. 3-15-23 RH. Sanitary laterals continued to be placed from lots 4 to lots 8. Laterals will continued to be installed and filled in. 3-16-23 RH. Sanitary laterls were installed from Lots 15 to Lots 18. Contractor was reminded Y's coming off the main needed to between 30 and 45 degrees. 3-20-23 RH Sanitary lateral for Lot 19 was installed. Contracotor has started filling over the laterals now that they are placed for lots 15-19. 3-23-23 RH. Saniatry Line 1 continues to have laterals place off of the Y's. Contractor is pumping water out of hole in the morning and will continue to place fill and test compaction on site. 3-28-23 RH. Sanitrary line 1 continues to be placed for lots 8 and continuing toward lot 14. 4-28-23 DP. Crew is working on installing private storm sewer line 7
Water Service Inspection Passed 11/21/2024 11/21/2024 11/21/2024
Miscellaneous Correction
Corrective Action Required
10/24/2024
10-21-24 DP. This was sent in an email form to Jacob. On the front: 441- Mostly ok, just needing to dig out mud and add clean gravel closer to the setter nuts 443- Top of meter is 5” below sod, bottom needs mud removed and gravel added. Meter depth will be approximately 22” once pit gets raised. 445- ok 447- Top of lid is 3” below grade, mud needs cleaned out of bottom of pit and gravel added, meter depth should be ok once riser on pit is added, but needs to be rechecked. 449-Top of lid is 4” below grade, bottom of pit needs mud removed and gravel added, meter depth should be ok once riser on pit is added, but needs to be rechecked. 451- Top of pit is 3” below grade, bottom of pit needs to be cleaned out with gravel put back in. The meter depth is currently at 18”, so a riser would make this out of spec. 453- Top of lid is 3” below grade, meter depth looks like It will be ok with riser, but will need rechecked. Bottom of pit needs mud removed and gravel added. 455- add some gravel to bottom of pit, otherwise ok 457- top of lid is 3” below grade with a meter depth at 16.5”. This depth should be ok after riser, but will need rechecked. 459- ok 461- ok 463- ok 465- ok 467- pit is collapsed and needs to be replaces. On the back: 440- needs mud removed, gravel added 442- needs mud removed, gravel added 444- needs mud removed, gravel added 446- 21.5” deep, meter needs raised 448- ok 450- clean out box and broken lid from bottom of meter pit, adjust pit so meter setter isn’t pushed up against side of pit. 452- Clean out bottom of meter pit, add rock and also raise the meter. It is currently at 20” in depth. 454- Raise meter depth. Currently at 22” deep 456- Raise meter depth. Currently at 22” deep. 458- Raise meter depth. Currently at 23” deep. 10-24-24 DP. Bair is onsite and started working away at the above list. I printed this list out and handed it to the contractor onsite. 11-21-24 DP. All repairs have been completed.
Site Visit Partial 11/21/2024 11/21/2024 11/21/2024
Misc
Informational
11/21/2024
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit.
Site Visit Partial 12/2/2024 12/2/2024 12/02/2024
Misc
Informational
11/21/2024
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit. 12-2-24 DP. No site work going on right now. Still expecting All American to show up on site soon to fix needed repairs.
Erosion Control Inspection Failed 12/5/2024 12/5/2024 12/05/2024
Misc
Informational
11/19/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
11/19/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
11/19/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
11/19/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice.
Erosion Control Inspection Partial 12/9/2024 12/9/2024 12/09/2024
Misc
Informational
12/05/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
12/05/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/05/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
12/05/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place.
Erosion Control Inspection Partial 12/12/2024 12/12/2024 12/12/2024
Misc
Informational
12/09/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
12/09/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/09/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
12/09/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great.
Site Visit Partial 12/17/2024 12/17/2024 12/17/2024
Misc
Informational
12/02/2024
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit. 12-2-24 DP. No site work going on right now. Still expecting All American to show up on site soon to fix needed repairs. 12-17-24 JS. All American is on sit and they are starting to tear out curbs and sidewalk that require repairs.
Site Visit Partial 12/24/2024 12/24/2024 12/24/2024
Misc
Informational
12/17/2024
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit. 12-2-24 DP. No site work going on right now. Still expecting All American to show up on site soon to fix needed repairs. 12-17-24 JS. All American is on-site and they are starting to tear out curbs and sidewalk that require repairs. 12-24-24 JS. Contractor poured back areas that needed fixed on SW and curb.
Site Visit Partial 12/30/2024 12/30/2024 12/31/2024
Misc
Informational
12/24/2024
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit. 12-2-24 DP. No site work going on right now. Still expecting All American to show up on site soon to fix needed repairs. 12-17-24 JS. All American is on-site and they are starting to tear out curbs and sidewalk that require repairs. 12-24-24 JS. Contractor poured back areas that needed fixed on SW and curb. 12-30-24 DP. All American removed concrete blankets yesterday and completed needed repairs.
Erosion Control Inspection Partial 12/30/2024 12/30/2024 12/31/2024
Misc
Informational
12/12/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
12/12/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/12/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
12/12/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great. 12-30-24 DP. No ESC issues at this time.
Erosion Control Inspection Partial 2/6/2025 2/6/2025 02/06/2025
Misc
Informational
12/31/2024
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
12/31/2024
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
12/31/2024
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
12/31/2024
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great. 12-30-24 DP. No ESC issues at this time.
Misc
Informational
02/06/2025
2-6-25 DP. All site work is done for this phase. All ESC is in good working order.
Erosion Control Inspection Partial 2/24/2025 2/24/2025 03/26/2025
Misc
Informational
02/06/2025
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
02/06/2025
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
02/06/2025
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
02/06/2025
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great. 12-30-24 DP. No ESC issues at this time.
Misc
Informational
02/06/2025
2-6-25 DP. All site work is done for this phase. All ESC is in good working order. 3-26-25 DP. No ESC issues at this time.
Site Visit Partial 4/14/2025 4/14/2025 04/16/2025
Misc
Informational
12/31/2024
11-21-24 DP. There are multiple areas of private curb that needs to be fixed. Most areas are painted in pink paint. There are also 4- 10" sidewalk panels that need replaced. There are 2 curbs in front of ADA ramps that need replaced which is also painted in pink. Areas for future phases need to be vegetated and keep silt fence in proper working order. There is still private sidewalk and sewer main/ service that will need installed for future phases that are still on this permit. 12-2-24 DP. No site work going on right now. Still expecting All American to show up on site soon to fix needed repairs. 12-17-24 JS. All American is on-site and they are starting to tear out curbs and sidewalk that require repairs. 12-24-24 JS. Contractor poured back areas that needed fixed on SW and curb. 12-30-24 DP. All American removed concrete blankets yesterday and completed needed repairs. 4-16-25 DP. No work on site. First two phases are complete, but this permit will stay open until all phases are complete, which will be long term.
Erosion Control Inspection Partial 4/14/2025 4/14/2025 04/16/2025
Misc
Informational
03/26/2025
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
03/26/2025
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
03/26/2025
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
03/26/2025
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great. 12-30-24 DP. No ESC issues at this time.
Misc
Informational
03/26/2025
2-6-25 DP. All site work is done for this phase. All ESC is in good working order. 3-26-25 DP. No ESC issues at this time. 4-14-25 DP. No changes from previous inspections. This site is not active.
Erosion Control Inspection Failed 5/15/2025 5/15/2025 05/15/2025
Misc
Informational
04/16/2025
Erosion control measure installed around perimeter of project site. 9/6/22 ES Spoke with Scott from Trinity about areas behind movie theater without silt fence in place after grading operations took it out. He will be getting new silt fence installed. 9/15/22 ES Areas behind theater had new silt fence installed. 9/26/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures unable to contain some runoff of open storm trenches allowing some silt to make its way through to basin on SE side of Kessler drive. Most other erosion control measures intact and functioning to contain erosion on site. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. All vehicles were parked around perimeter of site and no erosion issues noted. 11/7/22 ES Erosion control measures installed, intact, and functioning. The corner of concern has not failed, but also does not appear to have been addressed. 11/21/22 ES 2-22-23 RH. Erosion Control is up and in working order.
Miscellaneous Correction
Corrective Action Required
04/16/2025
7-24-23 DP. Erosion control issues need addressed especially in areas that are not vegetated.
Misc
Corrective Action Required
04/16/2025
12-4-23 DP. Spoke with Mike from O'Reilly Build about getting the site in the perimeter cleaned up and in order. He is going to be getting someone to street sweep and catching up on erosion control. 12-20-23 DP. There were some minor issues with erosion control on site. I communicated with Mike from O'Reilly Build and the issues were addressed in a timely manor. 4-26-24 DP. Immediate Erosion Control Issues on site. These silt fences/ erosion control measures should be fixed as soon as possible. 4-30-24 DP. Gordon Silt fence has been out and put some silt fence up. There are places that fence would be added. The streets still need cleaned up 5-6-24 DP. Streets still need to be cleaned. 6-25-24 DP. Gordon Fencing came out and fixed down silt fence. There private roads still need to be cleaned off
Miscellaneous Correction
Corrective Action Required
04/16/2025
8-15-24 DP. Erosion Control measures onsite need to be improved. There is a decent amount of sediment at the corner of Curry and Haversford that needs to be cleaned up. The entire onsite area needs to be kept up a little better going forward. I do know they have to drive the lift in and out of mud but we might need a sweeper more available if this rain keeps up. 8-20-24 DP. Erosion Control measures onsite still need to be improved. The site needs to be cleaned up from construction trash and sediment that has leached out onto the private roads. 9-4-24 DP. Still lacking on keeping debris and silt off the private roads. Sill need to improve onsite erosion control measures. 9-10-24 DP. When I left site this afternoon, Gordon fencing was beginning to install silt fence. I will check tomorrow and see what's left to clean up. 10-14-24 DP. Need silt fence added on far east side of property. Jacob said Gordon is coming out this week to dress up silt fence and replace gutter buddies. Kiwi is expected to start laying sod around buildings 3 and 4 this week as well. 11-19-24 DP. Silt fence still needs addressed in areas that are not vegetated. 12-5-24 DP. Silt fence still needs to be added in areas and needs to be reestablished in others. This needs to happen by Monday. Next inspection with no response will result in a 2 day notice. 12-9-24 DP. Gordon Silt fence was on site today and reconnected down silt fence. They didn't add silt fence anywhere, but did give an effort to dress up what's in place. 12-12-24 DP. Gordon came back out and installed new silt fence. The area looks great. 12-30-24 DP. No ESC issues at this time.
Misc
Informational
04/16/2025
2-6-25 DP. All site work is done for this phase. All ESC is in good working order. 3-26-25 DP. No ESC issues at this time. 4-14-25 DP. No changes from previous inspections. This site is not active. 5-15-25 DP. Silt fence is starting to come down in areas without established vegetation. Also, the mowers are mowing the new sod up against the buildings, but haven't touched any other part of the site this year. Silt fence needs to be maintained with areas not vegetated. Grass needs to be mowed ASAP.
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home