Summary


PRSITE20215386
Development - Site
Final Acceptance
WEST PRYOR OWNERS ASSOCIATION INC
DEVELOPMENT COMPLETE
STREETS OF WEST PRYOR - LOT 7 PUBLIC SANITARY
10/14/2021
11/22/2021
01/25/2023
Locations
Contacts
WEST PRYOR OWNERS ASSOCIATION INC, Address:7200 W 132ND ST STE 109  
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 10/14/2021 11/22/2021
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 11/22/2021
91100C8-Sanitary Sewer Insp Fees $3,746.10 $3,746.10 Paid 11/22/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary - Material Verification Passed 02/15/2022
Misc
Informational
02/15/2022
All sanitary materials meet LS specs. RP 2-15-22
Sanitary Sewer Construction Inspection Passed 02/15/2022
Misc
Informational
02/15/2022
Matt’s crew from ESS installed all sanitary lines and manholes. RP 2-15-22
Sanitary Sewer Construction Inspection Passed 02/15/2022
Misc
Informational
02/15/2022
Matt’s crew from ESS installed all sanitary lines and manholes. RP 2-15-22
Grading/Excavation/Fill Inspection Partial 2/15/2022 2/15/2022 02/15/2022
Misc
Informational
02/15/2022
ESS has started grading the site with fines left over from the rock crusher for the mines. RP 2-15-22
Site Visit Partial 2/17/2022 2/17/2022 02/21/2022
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Site Visit Partial 2/22/2022 2/22/2022 02/22/2022
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Sanitary Sewer - Air Test Partial 2/22/2022 2/22/2022 02/22/2022
Misc
Informational
02/22/2022
Jeremiah from ESS did air testing on the sanitary line from existing manhole to manhole A6. All segments passed testing. RP 2-22-22
Site Visit Partial 2/23/2022 2/23/2022 02/23/2022
Misc
Informational
02/22/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
02/23/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Sanitary Sewer - Mandrel Partial 02/23/2022
Misc
Informational
02/23/2022
The correct size mandrel passed through the sanitary line from manhole A-2 to A-6. RP 2-23-22
Sanitary Sewer - Air Test Passed 2/23/2022 2/23/2022 02/24/2022
Misc
Informational
02/22/2022
Jeremiah from ESS did air testing on the sanitary line from existing manhole to manhole A6. All segments passed testing. RP 2-22-22
Sanitary Sewer - Mandrel Partial 02/24/2022
Misc
Informational
02/23/2022
The correct size mandrel passed through the sanitary line from manhole A-2 to A-6. RP 2-23-22
Misc
Corrective Action Required
02/24/2022
Bad invert in manhole A-2, couldn’t get the mandrel into the line. Jeremiah has to grind it down. RP 2-24-22
Site Visit Partial 2/24/2022 2/24/2022 02/24/2022
Misc
Informational
02/23/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/23/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
02/23/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/24/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Site Visit Partial 2/25/2022 2/25/2022 02/25/2022
Misc
Informational
02/24/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/24/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
02/24/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/24/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Site Visit Partial 2/28/2022 2/28/2022 02/28/2022
Misc
Informational
02/25/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/25/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
02/25/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/25/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
02/28/2022
No work being done on site today. RP 2-28-22
Sanitary Sewer - Vacuum Partial 2/23/2022 2/23/2022 03/02/2022
Misc
Informational
03/02/2022
Manholes A-3 and A-4 passed their vacuum testing, while manholes A-5 and A-6 failed testing. RP 3-2-22
Site Visit Partial 3/2/2022 3/2/2022 03/14/2022
Misc
Informational
02/28/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/28/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
02/28/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
02/28/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
02/28/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
02/28/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Site Visit Partial 03/14/2022
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
03/14/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/14/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
ESS is just grading the site today. RP 3-14-22
Site Visit Partial 3/15/2022 3/15/2022 03/18/2022
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
03/14/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/14/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/14/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/14/2022
ESS is just grading the site today. RP 3-14-22
Misc
Informational
03/18/2022
No work being done today. 3/18/22 ES
Erosion Control Inspection Partial 03/23/2022
Misc
Informational
03/23/2022
No erosion issues to report on the job site today. RP 3-23-22
Erosion Control Inspection Partial 03/24/2022
Misc
Informational
03/23/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Sanitary Sewer - Vacuum Failed 3/4/2022 3/4/2022 03/25/2022
Misc
Informational
03/02/2022
Manholes A-3 and A-4 passed their vacuum testing, while manholes A-5 and A-6 failed testing. RP 3-2-22
Misc
Corrective Action Required
03/25/2022
Manhole A-5 failed it’s vacuum test again. We didn’t try manholes A-1, A-2 or A-6 yet. RP 3-25-22
Sanitary Sewer - Mandrel Passed 03/25/2022
Misc
Informational
02/24/2022
The correct size mandrel passed through the sanitary line from manhole A-2 to A-6. RP 2-23-22
Misc
Corrective Action Required
02/24/2022
Bad invert in manhole A-2, couldn’t get the mandrel into the line. Jeremiah has to grind it down. RP 2-24-22
Misc
Informational
03/25/2022
The correct size mandrel passed through from manhole A-1 to manhole A-2. RP 3-25-22
Sanitary Sewer - Vacuum Failed 3/29/2022 3/29/2022 03/29/2022
Misc
Informational
03/25/2022
Manholes A-3 and A-4 passed their vacuum testing, while manholes A-5 and A-6 failed testing. RP 3-2-22
Misc
Corrective Action Required
03/25/2022
Manhole A-5 failed it’s vacuum test again. We didn’t try manholes A-1, A-2 or A-6 yet. RP 3-25-22
Misc
Corrective Action Required
03/29/2022
Manholes A-2 and A-6 passed, but manholes A-1 and A-5 failed vacuum testing. RP 3-29-22
Sanitary Sewer - Vacuum Partial 3/31/2022 3/31/2022 04/06/2022
Misc
Informational
03/29/2022
Manholes A-3 and A-4 passed their vacuum testing, while manholes A-5 and A-6 failed testing. RP 3-2-22
Misc
Corrective Action Required
03/29/2022
Manhole A-5 failed it’s vacuum test again. We didn’t try manholes A-1, A-2 or A-6 yet. RP 3-25-22
Misc
Corrective Action Required
03/29/2022
Manholes A-2 and A-6 passed, but manholes A-1 and A-5 failed vacuum testing. RP 3-29-22
Misc
Corrective Action Required
04/06/2022
Manhole A-5 passed, but manhole A-1 failed again. RP 4-6-22
Site Visit Partial 04/06/2022
Misc
Informational
03/18/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/18/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
03/18/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
03/18/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
03/18/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/18/2022
No work being done on site today. RP 2-28-22
Misc
Informational
03/18/2022
No work being done on site today. RP 3-10-22
Misc
Informational
03/18/2022
ESS is just grading the site today. RP 3-14-22
Misc
Informational
03/18/2022
No work being done today. 3/18/22 ES
Misc
Informational
04/06/2022
We retested some of the sanitary lines that failed previously. No utility work or grading being done today. RP 4-6-22
Sanitary Sewer - Vacuum Passed 4/7/2022 4/7/2022 04/20/2022
Misc
Informational
04/06/2022
Manholes A-3 and A-4 passed their vacuum testing, while manholes A-5 and A-6 failed testing. RP 3-2-22
Misc
Corrective Action Required
04/06/2022
Manhole A-5 failed it’s vacuum test again. We didn’t try manholes A-1, A-2 or A-6 yet. RP 3-25-22
Misc
Corrective Action Required
04/06/2022
Manholes A-2 and A-6 passed, but manholes A-1 and A-5 failed vacuum testing. RP 3-29-22
Misc
Corrective Action Required
04/06/2022
Manhole A-5 passed, but manhole A-1 failed again. RP 4-6-22
Misc
Informational
04/20/2022
Manhole A-1 finally passed vacuum testing. RP 4-20-22
Site Visit Partial 4/7/2022 4/7/2022 04/20/2022
Misc
Informational
04/06/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/06/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
04/06/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
04/06/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
04/06/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/06/2022
No work being done on site today. RP 2-28-22
Misc
Informational
04/06/2022
No work being done on site today. RP 3-10-22
Misc
Informational
04/06/2022
ESS is just grading the site today. RP 3-14-22
Misc
Informational
04/06/2022
No work being done today. 3/18/22 ES
Misc
Informational
04/06/2022
We retested some of the sanitary lines that failed previously. No utility work or grading being done today. RP 4-6-22
Misc
Informational
04/20/2022
Jeremiah came out for more testing. Manhole A-1 passed it’s vacuum test and the invert in manhole A-6 finally accepted the mandrel. RP 4-20-22
Sanitary Sewer - Camera Test Partial 06/30/2022
Misc
Informational
06/30/2022
Met with Ops Techs from WU about gap in pipe connection and mandrel string in a couple of the manholes/inverts. 6/29/22 ES
Sanitary Sewer - Camera Test Partial 8/1/2022 07/05/2022
Misc
Informational
06/30/2022
Met with Ops Techs from WU about gap in pipe connection and mandrel string in a couple of the manholes/inverts. 6/29/22 ES Spoke with Reese again about getting measurements on drop lines inside MH A-3 and A-4 as well as cleaning mandrel string from MH A-3 and A-5. Rudy was to be working on those this afternoon. 7/5/22 ES
Sanitary Sewer - Camera Test Partial 8/4/2022 08/09/2022
Misc
Informational
07/05/2022
Met with Ops Techs from WU about gap in pipe connection and mandrel string in a couple of the manholes/inverts. 6/29/22 ES Spoke with Reese again about getting measurements on drop lines inside MH A-3 and A-4 as well as cleaning mandrel string from MH A-3 and A-5. Rudy was to be working on those this afternoon. 7/5/22 ES Spoke with Reese and Codi about flushing the two lines water had identified as needing flushed. 8/8/22 ES
Sanitary Sewer - Camera Test Passed 9/8/2022 09/09/2022
Misc
Informational
08/09/2022
Met with Ops Techs from WU about gap in pipe connection and mandrel string in a couple of the manholes/inverts. 6/29/22 ES Spoke with Reese again about getting measurements on drop lines inside MH A-3 and A-4 as well as cleaning mandrel string from MH A-3 and A-5. Rudy was to be working on those this afternoon. 7/5/22 ES Spoke with Reese and Codi about flushing the two lines water had identified as needing flushed. 8/8/22 ES Lines were flushed by ACE Pipe cleaning. 8/20/22 ES
Erosion Control Inspection Passed 09/09/2022
Misc
Informational
03/24/2022
No erosion issues to report on the job site today. RP 3-23-22
Misc
Informational
03/24/2022
Another rain day, still no erosion issues to report. RP 3-24-22
Misc
Informational
09/09/2022
This construction is completed. Erosion control measures for this portion covered by other projects in area. 9/9/22 ES
Record Drawing Review Partial 10/6/2022 10/05/2022
Misc
Informational
10/05/2022
Comments submitted to SP and DB for review. 10/5/22 ES
Record Drawing Review Partial 10/12/2022 10/17/2022
Misc
Informational
10/05/2022
Comments submitted to SP and DB for review. 10/5/22 ES Additional information provided by Dustin w/ ESS. Changed flow line out on MH A-5. Sent to DB and SP. 10/17/22 ES
Record Drawing Review Passed 10/24/2022 11/02/2022
Misc
Informational
10/17/2022
Comments submitted to SP and DB for review. 10/5/22 ES Additional information provided by Dustin w/ ESS. Changed flow line out on MH A-5. Sent to DB and SP. 10/17/22 ES
Site Visit Failed - Stop Work 4/29/2022 01/25/2023
Misc
Informational
04/20/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/20/2022
Jeremiah from ESS was on site doing sanitary testing. The lines were too wet to run mandrels, so they just did air testing for the day. RP 2-22-22
Misc
Informational
04/20/2022
Temperature was too cold to start the compressor for air and vacuum testing. Jeremiah had the diameter for the mandrel testing. He had the right size delivered on site. RP 2-23-22
Misc
Corrective Action Required
04/20/2022
Invert wouldn’t let the mandrel in to the line. Jeremiah needs to grind down the invert. RP 2-24-22
Misc
Informational
04/20/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/20/2022
No work being done on site today. RP 2-28-22
Misc
Informational
04/20/2022
No work being done on site today. RP 3-10-22
Misc
Informational
04/20/2022
ESS is just grading the site today. RP 3-14-22
Misc
Informational
04/20/2022
No work being done today. 3/18/22 ES
Misc
Informational
04/20/2022
We retested some of the sanitary lines that failed previously. No utility work or grading being done today. RP 4-6-22
Misc
Informational
04/20/2022
Jeremiah came out for more testing. Manhole A-1 passed it’s vacuum test and the invert in manhole A-6 finally accepted the mandrel. RP 4-20-22
Documents & Images
Date Uploaded File Type Document Name
11/22/2021 Receipt Receipt for transaction:2021-008895
11/22/2021 Approved Plans Streets of West Pryor Lot 7A and 7B Public Sanitary Approved 11.22.21
11/22/2021 Letter DE-Permit
02/15/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/21/2022 Letter INSPECTION SUMMARY
02/22/2022 Letter INSPECTION SUMMARY
02/22/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/25/2022 Letter INSPECTION SUMMARY
02/28/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/18/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/24/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/29/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/20/2022 Letter INSPECTION SUMMARY
04/20/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
07/05/2022 Letter INSPECTION SUMMARY
08/09/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter DE-Certificate of Substantial Completion Single Lot
09/13/2022 Letter DE-Punch List
09/13/2022 SWP LOT 7 SS PUBLIC PUNCH LIST 2021 5386
09/13/2022 SWP LOT 7 SS PUBLIC SUBSTANTIAL 2021 5386
09/29/2022 SOWP Lot 7 SANITARY As Built 9-20-22
10/05/2022 Letter INSPECTION SUMMARY
10/17/2022 Letter INSPECTION SUMMARY
11/02/2022 Letter INSPECTION SUMMARY
01/25/2023 SOWP Lot 7a 7b Public Sanitary Sewer - 3 year bond - ESS 9.20.22
01/25/2023 SOWP LOT 7 SANITARY SEWER FINAL AFFIDAVIT & AGREEMENT - X 1.24.23
01/25/2023 Letter DE-Certificate of Final Acceptance (Commercial)
01/25/2023 SOWP Lot 7 Public Sanitary Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home