Summary


PRSITE20211242
Development - Site
Final Acceptance
OAK VIEW LEES SUMMIT LLC
DEVELOPMENT COMPLETE
DEVELOPER IMPROVEMENTS FOR THE SITE - INCLUDES MASS GRADING, DETENTION AND RETAINING WALL.
03/18/2021
04/08/2021
07/22/2022
Locations
Contacts
OAK VIEW LEES SUMMIT LLC, Address:201 HAWKS RIDGE TRL  
ARC GENERAL CONTRACTING, Address:7833 BARTON ST, Phone:(913) 492-8008  
LYLE GREENE, Address:ARC GENERAL CONTRACTING, Phone:(405) 747-5968  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 03/18/2021 06/03/2021
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Water Insp Fee $282.00 $282.00 Paid 03/18/2021
Water Test Fee $200.00 $200.00 Paid 03/18/2021
Storm Sewer Inspection Fee $5,184.00 $5,184.00 Paid 04/06/2021
Site Grading Fee $2,208.60 $2,208.60 Paid 04/06/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Passed 11/09/2021
Misc
Informational
05/24/2021
5-24-21 9:40am I met with the superintendent Greg Torry on site to pick up my plans and go over the work taking place. Bash excavating is on site prepping the pad site and grading the dirt around the site.
Erosion Control Inspection Passed 11/09/2021
Misc
Informational
05/24/2021
5-245-21 9:59am The erosion controls are in place and working at this time. I spoke with the superintendent Greg Torry in length about the importance of the erosion controls and how they will need to be maintained continuously until the project is completed.
ESC - (Vegetation/Ground Cover) Passed 11/09/2021
Record Drawing Review Passed 11/5/2021 11/09/2021
Grading/Excavation/Fill Inspection Passed 11/09/2021
Misc
Informational
05/24/2021
5-24-21 9:40am I met with the superintendent Greg Torry on site to pick up my plans and go over the work taking place. Bash excavating is on site prepping the pad site and grading the dirt around the site. 5-25-21 9:17am Bash Excavating is on site grading.
Erosion Control Inspection Passed 11/09/2021
Misc
Informational
05/24/2021
5-245-21 9:59am The erosion controls are in place and working at this time. I spoke with the superintendent Greg Torry in length about the importance of the erosion controls and how they will need to be maintained continuously until the project is completed.
Grading/Excavation/Fill Inspection Passed 5/26/2021 5/26/2021 11/09/2021
Misc
Informational
05/25/2021
5-24-21 9:40am I met with the superintendent Greg Torry on site to pick up my plans and go over the work taking place. Bash excavating is on site prepping the pad site and grading the dirt around the site. 5-25-21 9:17am Bash Excavating is on site grading. 5-26-21 10:35am The work taking place is dirt removal. They are keeping the road clean. 11/04/21 Thursday Grading continued throughout the site.
Grading/Excavation/Fill Inspection Passed 11/09/2021
Misc
Informational
05/26/2021
5-24-21 9:40am I met with the superintendent Greg Torry on site to pick up my plans and go over the work taking place. Bash excavating is on site prepping the pad site and grading the dirt around the site. 5-25-21 9:17am Bash Excavating is on site grading. 5-26-21 10:35am The work taking place is dirt removal. They are keeping the road clean.
Site Visit Complete 11/09/2021
Misc
Informational
05/28/2021
5-28-21 9:18am Light rain. There is now work taking place today.
Site Visit Complete 11/09/2021
Misc
Informational
05/28/2021
5-28-21 9:18am Light rain. There is now work taking place today.
Retaining Wall Inspection Passed 07/11/2022
Misc
Informational
08/20/2021
8/20/21 Friday Contractor began cutting grade for footing of retaining wall. 8/26/21 Thursday Subcontractor (BC Hardscapes) continued to work on Retain Wall throughout the week.
Documents & Images

No documents are currently available for viewing.

Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home