Permit Application Status

PRSITE20200304


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20200304
Development - Site
Final Acceptance
SAINT LUKES EAST HOSPITAL
DEVELOPMENT COMPLETE
SITE IMPROVEMENTS FOR BUILDING ADDITION
02/10/2020
02/18/2020
12/06/2021
Locations
Contacts
SAINT LUKES EAST HOSPITAL, Address:901 E 104TH ST MAILSTOP 900N  
MCCOWN GORDON CONSTRUCTION LLC, Address:850 MAIN ST, Phone:(816) 960-1111  
Travis Grimes, Address:McCown Gordon Construction, Phone:(816) 960-1111  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 02/10/2020 02/10/2020
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $2,244.60 $2,244.60 Paid 02/13/2020
91100C9-Water Insp Fee $2,407.35 $2,407.35 Paid 02/13/2020
9110072-Water Test Fee $200.00 $200.00 Paid 02/13/2020
9110068-Storm Fee $1,619.55 $1,619.55 Paid 02/13/2020
9110081-Paved Surface Inspection Fee $524.16 $524.16 Paid 02/13/2020
9110071-Site Grading Fee $8,198.97 $8,198.97 Paid 02/13/2020
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Partial 3/2/2020 03/02/2020
Misc
Informational
03/02/2020
3-2-20 2:55pm There is no work on site at this time.
Site Visit Partial 03/10/2020
Misc
Informational
03/02/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/10/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Sanitary - Material Verification Partial 03/13/2020
Misc
Informational
03/13/2020
The sanitary pipe is SDR 26 all fittings and connections appear to be correct . Manholes appear to be correct.
Storm - Material Verification Partial 3/13/2020 03/13/2020
Misc
Informational
03/13/2020
3-13-20 All storm material appears to be correct for the job.
Storm - Pipe Partial 3/13/2020 03/13/2020
Misc
Informational
03/13/2020
3-13-20 8:43am They have boarded out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Storm - Pipe Partial 3/17/2020 03/18/2020
Misc
Informational
03/13/2020
3-13-20 8:43am They have boarded out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/17/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Storm - Pipe Partial 3/18/2020 03/18/2020
Misc
Informational
03/18/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/18/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
03/18/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Site Visit Partial 3/19/2020 03/19/2020
Misc
Informational
03/10/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/10/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/19/2020
3-19-20 There is no activity on site today.
Storm - Pipe Partial 3/20/2020 03/20/2020
Misc
Informational
03/18/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/18/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
03/18/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
03/20/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
03/20/2020
Sanitary Sewer Construction Inspection Partial 3/23/2020 03/23/2020
Misc
Informational
03/23/2020
3-23-20 10:30am They have cored The existing manhole at STA. 0+00 and have one stick of pipe installed. They are dealing with lots of rock. 3:32pm They are getting close to installing there second stick of pipe.
Sanitary Sewer Construction Inspection Partial 3/24/2020 03/24/2020
Misc
Informational
03/24/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/24/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/24/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Sanitary Sewer Construction Inspection Partial 3/25/2020 03/25/2020
Misc
Informational
03/25/2020
3-25-20 They are holding up on sanitary until a fire hydrant is moved.
Storm - Pipe Partial 03/25/2020
Misc
Informational
03/20/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/20/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
03/20/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
03/20/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
03/20/2020
Misc
Informational
03/25/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today.
Sanitary Sewer Construction Inspection Partial 3/27/2020 03/27/2020
Misc
Informational
03/27/2020
3-27-20 8:50am They installed two sticks of sanitary line on 3-26-20. They are currently hammering rock.
Misc
Informational
03/27/2020
3-27-20 8:50am They installed two sticks of sanitary line on 3-26-20. They are currently hammering rock. 3:26pm They have installed one stick of sanitary line today due to rock. They are still breaking.
Sanitary Sewer Construction Inspection Partial 3/30/2020 03/30/2020
Misc
Informational
03/27/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/27/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/27/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/30/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Storm - Pipe Partial 3/30/2020 03/30/2020
Misc
Informational
03/25/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/25/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
03/25/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
03/25/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
03/25/2020
Misc
Informational
03/25/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
03/26/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
03/30/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Storm - Pipe Partial 3/31/2020 03/31/2020
Misc
Informational
03/30/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
03/30/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/30/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
03/30/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
03/30/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
03/30/2020
Misc
Informational
03/30/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
03/30/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
03/31/2020
3-30-20 They installed six sticks.
Sanitary Sewer Construction Inspection Partial 3/31/2020 03/31/2020
Misc
Informational
03/30/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/30/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/30/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/30/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
03/31/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
03/31/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
03/31/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Site Visit Partial 04/01/2020
Misc
Informational
03/19/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/19/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/19/2020
3-19-20 There is no activity on site today.
Misc
Informational
04/01/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm.
Storm - Pipe Partial 4/1/2020 04/01/2020
Misc
Informational
03/31/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
03/31/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
03/31/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
03/31/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
03/31/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
03/31/2020
Misc
Informational
03/31/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
03/31/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
03/31/2020
3-30-20 They installed six sticks.
Misc
Informational
03/31/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Storm - Pipe Partial 4/2/2020 04/02/2020
Misc
Informational
04/01/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/01/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/01/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/01/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/01/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/01/2020
Misc
Informational
04/01/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/01/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/01/2020
3-30-20 They installed six sticks.
Misc
Informational
04/01/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/02/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Sanitary Sewer Construction Inspection Partial 4/3/2020 04/03/2020
Misc
Informational
03/31/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/31/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/31/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
03/31/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
03/31/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
03/31/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
03/31/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/03/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Storm - Pipe Partial 4/4/2020 04/04/2020
Misc
Informational
04/02/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/02/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/02/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/02/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/02/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/02/2020
Misc
Informational
04/02/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/02/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/02/2020
3-30-20 They installed six sticks.
Misc
Informational
04/02/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/02/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/04/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Sanitary Sewer Construction Inspection Partial 4/4/2020 04/04/2020
Misc
Informational
04/03/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/03/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/03/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/03/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
04/03/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/03/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/03/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/03/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
04/04/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Storm - Pipe Partial 04/06/2020
Misc
Informational
04/04/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/04/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/04/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/04/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/04/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/04/2020
Misc
Informational
04/04/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/04/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/04/2020
3-30-20 They installed six sticks.
Misc
Informational
04/04/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/04/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/04/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/04/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Storm - Pipe Partial 4/6/2020 04/06/2020
Misc
Informational
04/06/2020
3-30-20 They installed six sticks.
Misc
Informational
04/06/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/06/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/06/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/06/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/06/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/06/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/06/2020
Misc
Informational
04/06/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/06/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/06/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/06/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/06/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/06/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Storm - Pipe Partial 04/07/2020
Misc
Informational
04/06/2020
3-30-20 They installed six sticks.
Misc
Informational
04/06/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/06/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/06/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/06/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/06/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/06/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/06/2020
Misc
Informational
04/06/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/06/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/06/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/06/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/06/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/06/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/07/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Storm - Pipe Partial 4/8/2020 04/08/2020
Misc
Informational
04/07/2020
3-30-20 They installed six sticks.
Misc
Informational
04/07/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/07/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/07/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/07/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/07/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/07/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/07/2020
Misc
Informational
04/07/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/07/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/07/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/07/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/07/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/07/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/07/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/08/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Sanitary Sewer Construction Inspection Partial 4/9/2020 04/09/2020
Misc
Informational
04/04/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/04/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/04/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/04/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
04/04/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/04/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/04/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/04/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
04/04/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Misc
Informational
04/09/2020
4-9-20 10:44am They are digging out around the water main to install more sanitary line. They have installed 14’ today at this time. 3:01pm They have installed one more stick of sanitary and are working backfilling and putting the fire hydrant back in service.
Sanitary Sewer Construction Inspection Partial 4/13/2020 04/13/2020
Misc
Informational
04/09/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/09/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/09/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/09/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
04/09/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/09/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/09/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/09/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
04/09/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Misc
Informational
04/09/2020
4-9-20 10:44am They are digging out around the water main to install more sanitary line. They have installed 14’ today at this time. 3:01pm They have installed one more stick of sanitary and are working backfilling and putting the fire hydrant back in service.
Misc
Informational
04/13/2020
4-13-20 They are on site preparing to start installing sanitary.
Misc
Informational
04/13/2020
4-13-20 They are on site preparing to start installing sanitary. 1:38pm They have two sticks of sanitary line installed at this time. They will install one more stick then start working on installing the manhole.
Sanitary Sewer Construction Inspection Partial 4/14/2020 04/14/2020
Misc
Informational
04/13/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/13/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/13/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/13/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
04/13/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/13/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/13/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/13/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
04/13/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Misc
Informational
04/13/2020
4-9-20 10:44am They are digging out around the water main to install more sanitary line. They have installed 14’ today at this time. 3:01pm They have installed one more stick of sanitary and are working backfilling and putting the fire hydrant back in service.
Misc
Informational
04/13/2020
4-13-20 They are on site preparing to start installing sanitary.
Misc
Informational
04/13/2020
4-13-20 They are on site preparing to start installing sanitary. 1:38pm They have two sticks of sanitary line installed at this time. They will install one more stick then start working on installing the manhole.
Misc
Informational
04/14/2020
4-14-20 10:52am All of the sanitary is installed and we have started the 30 day clock. On 5-13-20 we can start testing.
Storm - Pipe Partial 4/14/2020 04/14/2020
Misc
Informational
04/08/2020
3-30-20 They installed six sticks.
Misc
Informational
04/08/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/08/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/08/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/08/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/08/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/08/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/08/2020
Misc
Informational
04/08/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/08/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/08/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/08/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/08/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/08/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/08/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/08/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/14/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Storm - Pipe Partial 4/15/2020 04/15/2020
Misc
Informational
04/14/2020
3-30-20 They installed six sticks.
Misc
Informational
04/14/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/14/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/14/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/14/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/14/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/14/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/14/2020
Misc
Informational
04/14/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/14/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/14/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/14/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/14/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/14/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/14/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/14/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/14/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/15/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early.
Storm - Pipe Partial 4/16/2020 04/16/2020
Misc
Informational
04/15/2020
3-30-20 They installed six sticks.
Misc
Informational
04/15/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/15/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/15/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/15/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/15/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/15/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/15/2020
Misc
Informational
04/15/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/15/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/15/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/15/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/15/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/15/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/15/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/15/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/15/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/15/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain.
Storm - Pipe Partial 04/17/2020
Misc
Informational
04/16/2020
3-30-20 They installed six sticks.
Misc
Informational
04/16/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/16/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/16/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/16/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/16/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/16/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/16/2020
Misc
Informational
04/16/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/16/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/16/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/16/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/16/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/16/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/16/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/16/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/16/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/16/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Storm - Pipe Partial 4/20/2020 04/20/2020
Misc
Informational
04/17/2020
3-30-20 They installed six sticks.
Misc
Informational
04/17/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/17/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/17/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/17/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/17/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/17/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/17/2020
Misc
Informational
04/17/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/17/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/17/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/17/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/17/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/17/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/17/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/17/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/17/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/17/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
04/20/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Storm - Pipe Partial 4/21/2020 04/21/2020
Misc
Informational
04/20/2020
3-30-20 They installed six sticks.
Misc
Informational
04/20/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/20/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/20/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/20/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/20/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/20/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/20/2020
Misc
Informational
04/20/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/20/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/20/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/20/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/20/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/20/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/20/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/20/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/20/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/20/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
04/20/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
04/21/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe.
Water Line - Construction Inspection Partial 4/22/2020 04/22/2020
Misc
Informational
04/07/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.
Water Line - Construction Inspection Partial 4/23/2020 04/23/2020
Misc
Informational
04/23/2020
4-23-20 10:31am They have approximately 172’ of waterline installed and will be pouring kickers later today. 3:34pm They have approximately 233’ installed and will pour thrust blocks in the morning at 8:15am.
Site Visit Partial 04/27/2020
Misc
Informational
04/01/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
04/01/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
04/01/2020
3-19-20 There is no activity on site today.
Misc
Informational
04/01/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather.
Water Line - Construction Inspection Partial 4/28/2020 04/28/2020
Misc
Informational
04/23/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week.
Storm - Pipe Partial 4/30/2020 04/30/2020
Misc
Informational
04/21/2020
3-30-20 They installed six sticks.
Misc
Informational
04/21/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/21/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/21/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/21/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/21/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/21/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/21/2020
Misc
Informational
04/21/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/21/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/21/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/21/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/21/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/21/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/21/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/21/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/21/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/21/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
04/21/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
04/21/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.
Sanitary Sewer Construction Inspection Partial 4/30/2020 04/30/2020
Misc
Informational
04/14/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/14/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/14/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/14/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
04/14/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/14/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/14/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/14/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
04/14/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Misc
Informational
04/14/2020
4-9-20 10:44am They are digging out around the water main to install more sanitary line. They have installed 14’ today at this time. 3:01pm They have installed one more stick of sanitary and are working backfilling and putting the fire hydrant back in service.
Misc
Informational
04/14/2020
4-13-20 They are on site preparing to start installing sanitary.
Misc
Informational
04/14/2020
4-13-20 They are on site preparing to start installing sanitary. 1:38pm They have two sticks of sanitary line installed at this time. They will install one more stick then start working on installing the manhole.
Misc
Informational
04/14/2020
4-14-20 10:52am All of the sanitary is installed and we have started the 30 day clock. On 5-13-20 we can start testing. 4-30-20 They are working on the service line going to the existing manhole.
Site Visit Partial 05/01/2020
Misc
Informational
04/27/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
04/27/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
04/27/2020
3-19-20 There is no activity on site today.
Misc
Informational
04/27/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.
Site Visit Partial 05/01/2020
Misc
Informational
05/01/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/01/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/01/2020
3-19-20 There is no activity on site today.
Misc
Informational
05/01/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair.
Site Visit Partial 5/4/2020 05/04/2020
Misc
Informational
05/01/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/01/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/01/2020
3-19-20 There is no activity on site today.
Misc
Informational
05/01/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day.
Site Visit Partial 05/05/2020
Misc
Informational
05/04/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/04/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/04/2020
3-19-20 There is no activity on site today.
Misc
Informational
05/04/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital.
Storm - Pipe Partial 5/6/2020 05/06/2020
Misc
Informational
04/30/2020
3-30-20 They installed six sticks.
Misc
Informational
04/30/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
04/30/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
04/30/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
04/30/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
04/30/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
04/30/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
04/30/2020
Misc
Informational
04/30/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
04/30/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
04/30/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
04/30/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
04/30/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
04/30/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
04/30/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
04/30/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
04/30/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
04/30/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
04/30/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
04/30/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.5-5-20 they have four sticks of storm pipe coming out of the existing storm box going for box 101. 5-6-20 Rodrigues has completed storm line 1. They poured all collars and inverts and have back filled.
Storm - Pipe Partial 5/7/2020 05/07/2020
Misc
Informational
05/06/2020
3-30-20 They installed six sticks.
Misc
Informational
05/06/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
05/06/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
05/06/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
05/06/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
05/06/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
05/06/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
05/06/2020
Misc
Informational
05/06/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
05/06/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
05/06/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
05/06/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
05/06/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
05/06/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
05/06/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
05/06/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
05/06/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
05/06/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
05/06/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
05/06/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.5-5-20 they have four sticks of storm pipe coming out of the existing storm box going for box 101. 5-6-20 Rodrigues has completed storm line 1. They poured all collars and inverts and have back filled. 5-7-20 9:04am They have set box 103 and ran approximately 60’ of pipe to the existing box. They will be pouring collars and inverts at 1pm today. They got the collars and inverts poured.
Storm - Pipe Partial 5/8/2020 05/08/2020
Misc
Informational
05/07/2020
3-30-20 They installed six sticks.
Misc
Informational
05/07/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
05/07/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
05/07/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
05/07/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
05/07/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
05/07/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
05/07/2020
Misc
Informational
05/07/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
05/07/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
05/07/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
05/07/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
05/07/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
05/07/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
05/07/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
05/07/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
05/07/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
05/07/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
05/07/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
05/07/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.5-5-20 they have four sticks of storm pipe coming out of the existing storm box going for box 101. 5-6-20 Rodrigues has completed storm line 1. They poured all collars and inverts and have back filled. 5-7-20 9:04am They have set box 103 and ran approximately 60’ of pipe to the existing box. They will be pouring collars and inverts at 1pm today. They got the collars and inverts poured.
Storm - Pipe Partial 5/12/2020 05/13/2020
Misc
Informational
05/08/2020
3-30-20 They installed six sticks.
Misc
Informational
05/08/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
05/08/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
05/08/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
05/08/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
05/08/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
05/08/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
05/08/2020
Misc
Informational
05/08/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
05/08/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
05/08/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
05/08/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
05/08/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
05/08/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
05/08/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
05/08/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
05/08/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
05/08/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
05/08/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
05/08/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.5-5-20 they have four sticks of storm pipe coming out of the existing storm box going for box 101. 5-6-20 Rodrigues has completed storm line 1. They poured all collars and inverts and have back filled. 5-7-20 9:04am They have set box 103 and ran approximately 60’ of pipe to the existing box. They will be pouring collars and inverts at 1pm today. They got the collars and inverts poured.
Misc
Informational
05/12/2020
5-12-20 Rodriguez installed box 301 and 201. All storm pipe has been installed and collars poured with inverts. They are now working on line 4. They have cut Into box 402 and will be installing storm pipe going to box 401.
Storm - Pipe Partial 5/13/2020 05/13/2020
Misc
Informational
05/13/2020
3-30-20 They installed six sticks.
Misc
Informational
05/13/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
05/13/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
05/13/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
05/13/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
05/13/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
05/13/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
05/13/2020
Misc
Informational
05/13/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
05/13/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
05/13/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
05/13/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
05/13/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
05/13/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
05/13/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
05/13/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
05/13/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
05/13/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
05/13/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
05/13/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.5-5-20 they have four sticks of storm pipe coming out of the existing storm box going for box 101. 5-6-20 Rodrigues has completed storm line 1. They poured all collars and inverts and have back filled. 5-7-20 9:04am They have set box 103 and ran approximately 60’ of pipe to the existing box. They will be pouring collars and inverts at 1pm today. They got the collars and inverts poured.
Misc
Informational
05/13/2020
5-12-20 Rodriguez installed box 301 and 201. All storm pipe has been installed and collars poured with inverts. They are now working on line 4. They have cut Into box 402 and will be installing storm pipe going to box 401. 5-12-20 They installed the storm pipe and poured collars and inverts.
Sanitary Sewer - Vacuum Partial 05/14/2020
Misc
Informational
05/14/2020
5-14-20 Manhole 1-B has passed the vacuum test.
Sanitary Sewer - Vacuum Partial 5/15/2020 05/15/2020
Misc
Informational
05/15/2020
5-15-20 Manhole 1-A and 1-B have passed the vacuum test.
Sanitary Sewer - Mandrel Partial 5/15/2020 05/15/2020
Misc
Informational
05/15/2020
5-15-20 2;04PM They pulled the mandrel from C-1 to 1-B. It has passed.
Sanitary Sewer Construction Inspection Partial 5/18/2020 05/18/2020
Misc
Informational
04/30/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/30/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/30/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
04/30/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
04/30/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/30/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/30/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
04/30/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
04/30/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Misc
Informational
04/30/2020
4-9-20 10:44am They are digging out around the water main to install more sanitary line. They have installed 14’ today at this time. 3:01pm They have installed one more stick of sanitary and are working backfilling and putting the fire hydrant back in service.
Misc
Informational
04/30/2020
4-13-20 They are on site preparing to start installing sanitary.
Misc
Informational
04/30/2020
4-13-20 They are on site preparing to start installing sanitary. 1:38pm They have two sticks of sanitary line installed at this time. They will install one more stick then start working on installing the manhole.
Misc
Informational
04/30/2020
4-14-20 10:52am All of the sanitary is installed and we have started the 30 day clock. On 5-13-20 we can start testing. 4-30-20 They are working on the service line going to the existing manhole. 5-18-20 They are digging up the sanitary line to fix a sag. When the repair is made and backfilled we will start the 30 day clock.
Water Line - Construction Inspection Partial 5/19/2020 05/19/2020
Misc
Informational
04/28/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today.
Sanitary Sewer - Mandrel Passed 5/19/2020 05/19/2020
Misc
Informational
05/19/2020
5-19-20 4:18pm They pulled the mandrel through from the existing to manhole 1-A and it passed.
Water Line - Construction Inspection Partial 5/21/2020 05/22/2020
Misc
Informational
05/19/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20.
Water Line - Hydrostatic Test Partial 5/26/2020 5/26/2020 05/26/2020
Misc
Informational
05/26/2020
5-26-20 Rodrigues has started the test. The gauge is not certified however Steve Robbins knows the crew and trust the gauge to be accurate. The gauge is new. The water line has passed. 150 for two hours.
Water Line - Construction Inspection Partial 5/26/2020 5/26/2020 05/26/2020
Misc
Informational
05/22/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20. 5-26-20 They have flushed the line and are setting up for the hydrostatic test. 5-26-20 Rodriguez is staring to chlorinate the water line. The water line is chlorinated. We will flush in 24 hours.
Water Line - Hydrostatic Test Passed 05/26/2020
Misc
Informational
05/26/2020
5-26-20 Rodrigues has started the test. The gauge is not certified however Steve Robbins knows the crew and trust the gauge to be accurate. The gauge is new. The water line has passed. 150 for two hours.
Water Line - Construction Inspection Partial 5/27/2020 5/27/2020 05/27/2020
Misc
Informational
05/26/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20. 5-26-20 They have flushed the line and are setting up for the hydrostatic test. 5-26-20 Rodriguez is staring to chlorinate the water line. The water line is chlorinated. We will flush in 24 hours. 5-27-20 Rodriguez flushed all of the chlorine out and we will pull samples on 5-28-20.
Water Line - Coliform Test 1 Partial 05/28/2020
Misc
Informational
05/28/2020
5-28-20 9:30am Raining. We pulled 5 water samples at 10am. 10:35am I have dropped the samples off at the lab. These are for first round.
Water Line - Coliform Test 2 Partial 5/29/2020 5/29/2020 05/29/2020
Misc
Informational
05/29/2020
5-29-20 We pulled 5 samples for the second round. I will deliver them downtown.
Misc
Informational
05/29/2020
5-29-20 We pulled 5 samples for the second round. I will deliver them downtown. 11:19am The samples have been dropped off at the lab.
Water Line - Construction Inspection Partial 5/30/2020 5/30/2020 05/30/2020
Misc
Informational
05/27/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20. 5-26-20 They have flushed the line and are setting up for the hydrostatic test. 5-26-20 Rodriguez is staring to chlorinate the water line. The water line is chlorinated. We will flush in 24 hours. 5-27-20 Rodriguez flushed all of the chlorine out and we will pull samples on 5-28-20.
Misc
Informational
05/30/2020
Sunny mid 60”s at 7:00 AM Rodriguez began installing 4” temporary fire line & water line. Approximately 108’ of fire line 4” DIP & 90’ of water main 4” DIP. 2/45 degree bends and (2/90 degree bend with backing block) on the fire line. 2/45 degree bend on the water main. Contractor draw a rough draft of temporary fire main & water main.
Water Line - Construction Inspection Partial 6/1/2020 6/1/2020 06/01/2020
Misc
Informational
05/30/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20. 5-26-20 They have flushed the line and are setting up for the hydrostatic test. 5-26-20 Rodriguez is staring to chlorinate the water line. The water line is chlorinated. We will flush in 24 hours. 5-27-20 Rodriguez flushed all of the chlorine out and we will pull samples on 5-28-20.
Misc
Informational
05/30/2020
Sunny mid 60”s at 7:00 AM Rodriguez began installing 4” temporary fire line & water line. Approximately 108’ of fire line 4” DIP & 90’ of water main 4” DIP. 2/45 degree bends and (2/90 degree bend with backing block) on the fire line. 2/45 degree bend on the water main. Contractor draw a rough draft of temporary fire main & water main. 6-1-20 We have shut the water off for the tie-in on the west side of the job site. The are currently draining the water. The tie-in is finished and water is on.
Site Visit Partial 06/03/2020
Misc
Informational
05/05/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/05/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/05/2020
3-19-20 There is no activity on site today.
Misc
Informational
05/05/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off.
Site Visit Partial 6/4/2020 6/4/2020 06/04/2020
Misc
Informational
06/03/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
06/03/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
06/03/2020
3-19-20 There is no activity on site today.
Misc
Informational
06/03/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight.
Water Line - Construction Inspection Partial 06/05/2020
Misc
Informational
06/01/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20. 5-26-20 They have flushed the line and are setting up for the hydrostatic test. 5-26-20 Rodriguez is staring to chlorinate the water line. The water line is chlorinated. We will flush in 24 hours. 5-27-20 Rodriguez flushed all of the chlorine out and we will pull samples on 5-28-20.
Misc
Informational
06/01/2020
Sunny mid 60”s at 7:00 AM Rodriguez began installing 4” temporary fire line & water line. Approximately 108’ of fire line 4” DIP & 90’ of water main 4” DIP. 2/45 degree bends and (2/90 degree bend with backing block) on the fire line. 2/45 degree bend on the water main. Contractor draw a rough draft of temporary fire main & water main. 6-1-20 We have shut the water off for the tie-in on the west side of the job site. The are currently draining the water. The tie-in is finished and water is on. 6-4-20 10:41pm We performed a test shut down at 5am and all was well. We are getting ready to shut off the water to tie-in the water main. 11:06pm They are working on getting everything in place. 6-5-20 2:36am They have all water lines connected and are back filling with rock. 2:59am We have turned the water back on and are filling the main. The main is filled and air is out. The hospital is back in service.
Site Visit Partial 6/9/2020 6/9/2020 06/09/2020
Misc
Informational
06/04/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
06/04/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
06/04/2020
3-19-20 There is no activity on site today.
Misc
Informational
06/04/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today.
Pavement-Curb Construction Failed 6/11/2020 6/11/2020 06/11/2020
Misc
Informational
06/11/2020
6-11-20 10:22am Shaw is pouring the curb on the South West corner of the site. They have been informed to use white cure. PSI did a subgrade inspection. They installed geogrid and type 5 base. I was not informed of the pour taking place. 2:50pm Shaw did not cure any of the curb fully the tempature out side 85 degrees. There is approximately 244 ‘ that received no cure at all for over 5 hours. The intire run of curb had no cure on the back side leaving bare concrete exposed in the heat for approximately 5 plus hours. It is my recommendation that it be removed and replaced. Cure should be applied right after final finish.
Pavement-Proof Roll Partial 6/15/2020 6/15/2020 06/15/2020
Misc
Informational
06/15/2020
6-15-20 We proof rolled at 11am. It has passed with at 20 ton load.
Pavement-Surface Partial 6/16/2020 6/16/2020 06/16/2020
Misc
Informational
06/16/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Street - Wedge Lift Partial 06/17/2020
Misc
Informational
06/17/2020
6-17-20 ON 6-16 They layed the second lift on the road when the temp was at spec.
Street - Surface Course Partial 6/17/2020 6/17/2020 06/17/2020
Miscellaneous Correction
Informational
06/17/2020
6-17-20 8:20am Seal O Matic are placing the surface. They have started at the SW corner of the site an are working there way around the West side. The temps are 295 degree average out of the trucks.
Miscellaneous Correction
Informational
06/17/2020
6-17-20 8:20am Seal O Matic are placing the surface. They have started at the SW corner of the site an are working there way around the West side. The temps are 295 degree average out of the trucks. 1:30pm They are done with the asphalt and have everything blocked off.
Miscellaneous Correction
Informational
06/17/2020
6-17-20 8:20am Seal O Matic are placing the surface. They have started at the SW corner of the site an are working there way around the West side. The temps are 295 degree average out of the trucks. 1:30pm They are done with the asphalt and have everything blocked off.
Site Visit Partial 06/18/2020
Misc
Informational
06/09/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
06/09/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
06/09/2020
3-19-20 There is no activity on site today.
Misc
Informational
06/09/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today.
Site Visit Partial 06/29/2020
Misc
Informational
06/18/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
06/18/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
06/18/2020
3-19-20 There is no activity on site today.
Misc
Informational
06/18/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time.
Site Visit Partial 6/30/2020 6/30/2020 06/30/2020
Misc
Informational
06/29/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
06/29/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
06/29/2020
3-19-20 There is no activity on site today.
Misc
Informational
06/29/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time.
Site Visit Partial 07/01/2020
Misc
Informational
06/30/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
06/30/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
06/30/2020
3-19-20 There is no activity on site today.
Misc
Informational
06/30/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time.
Site Visit Partial 07/06/2020
Misc
Informational
07/01/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/01/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/01/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/01/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time.
Site Visit Partial 07/07/2020
Misc
Informational
07/06/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/06/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/06/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/06/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time.
Site Visit Partial 07/08/2020
Misc
Informational
07/07/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/07/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/07/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/07/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections.
Sanitary - Material Verification Passed 07/09/2020
Water Line - Fire Hydrant Passed 07/09/2020
Misc
Informational
07/09/2020
All of the fire hydrants are installed
Misc
Informational
07/09/2020
All of the fire hydrants are installed
Site Visit Partial 07/09/2020
Misc
Informational
07/08/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/08/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/08/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/08/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time.
Site Visit Partial 07/10/2020
Misc
Informational
07/09/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/09/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/09/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/09/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today.
Site Visit Partial 7/13/2020 7/13/2020 07/13/2020
Misc
Informational
07/10/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/10/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/10/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/10/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time.
Site Visit Partial 07/14/2020
Misc
Informational
07/13/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/13/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/13/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/13/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time.
Site Visit Partial 07/16/2020
Misc
Informational
07/14/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/14/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/14/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/14/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time.
Site Visit Partial 7/20/2020 7/20/2020 07/20/2020
Misc
Informational
07/16/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/16/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/16/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/16/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now.
Site Visit Partial 7/24/2020 7/24/2020 07/24/2020
Misc
Informational
07/20/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/20/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/20/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/20/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time.
Site Visit Partial 7/31/2020 7/31/2020 07/31/2020
Misc
Informational
07/24/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/24/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/24/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/24/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather.
Site Visit Partial 08/05/2020
Misc
Informational
07/31/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
07/31/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
07/31/2020
3-19-20 There is no activity on site today.
Misc
Informational
07/31/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection.
Site Visit Partial 08/06/2020
Misc
Informational
08/05/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
08/05/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
08/05/2020
3-19-20 There is no activity on site today.
Misc
Informational
08/05/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today.
Site Visit Partial 08/14/2020
Misc
Informational
08/06/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
08/06/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
08/06/2020
3-19-20 There is no activity on site today.
Misc
Informational
08/06/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections.
Site Visit Partial 08/17/2020
Misc
Informational
08/14/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
08/14/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
08/14/2020
3-19-20 There is no activity on site today.
Misc
Informational
08/14/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections.
Site Visit Partial 08/21/2020
Misc
Informational
08/17/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
08/17/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
08/17/2020
3-19-20 There is no activity on site today.
Misc
Informational
08/17/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection.
Site Visit Partial 08/31/2020
Misc
Informational
08/21/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
08/21/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
08/21/2020
3-19-20 There is no activity on site today.
Misc
Informational
08/21/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land.
Sanitary Sewer - Air Test Passed 09/08/2020
Misc
Corrective Action Required
05/14/2020
5-13-20 The air test for manhole 1-A to 1-B has passed. The air test for line 1 from existing manhole to manhole 1-A has passed
Sanitary Sewer - Vacuum Passed 09/08/2020
Misc
Informational
05/15/2020
5-14-20 Manhole 1-B has passed the vacuum test.
Sanitary Sewer Construction Inspection Passed 09/08/2020
Misc
Informational
05/18/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
05/18/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
05/18/2020
3-24-20 They have install one stick of sanitary line today. They are concerned with crossing the water line at the hydrant.
Misc
Informational
05/18/2020
3-30-20 7:35am They installed 5 sticks of sanitary line on 3-28-20 and are now getting ready to install manhole A1. 12:43pm They have tied into the manhole and are now backfilling.
Misc
Informational
05/18/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
05/18/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
05/18/2020
3-31-20 10:27am Manhole 1A is installed and they have approximately 14’ coming out going to manhole 1B.
Misc
Informational
05/18/2020
4-3-20 7:51am They have set manhole 1-B had have approximately 70’ of sanitary line installed heading to manhole 1-C. They will be adding tracer tape at a later date. 12:03pm They are stopping for the day due to weather.
Misc
Informational
05/18/2020
4-4-20 8:31am They have two crews working on sanitary. They are digging down to the main to cut in a wye and stub out for the service line on the NW side of the site. They now have approximately 112’ coming out of manhole 1-B. 10:29am They have the wye cut in and it appears to be at a 45 degree angle. They have tracer wire taped to the service line and are starting to backfill.
Misc
Informational
05/18/2020
4-9-20 10:44am They are digging out around the water main to install more sanitary line. They have installed 14’ today at this time. 3:01pm They have installed one more stick of sanitary and are working backfilling and putting the fire hydrant back in service.
Misc
Informational
05/18/2020
4-13-20 They are on site preparing to start installing sanitary.
Misc
Informational
05/18/2020
4-13-20 They are on site preparing to start installing sanitary. 1:38pm They have two sticks of sanitary line installed at this time. They will install one more stick then start working on installing the manhole.
Misc
Informational
05/18/2020
4-14-20 10:52am All of the sanitary is installed and we have started the 30 day clock. On 5-13-20 we can start testing. 4-30-20 They are working on the service line going to the existing manhole. 5-18-20 They are digging up the sanitary line to fix a sag. When the repair is made and backfilled we will start the 30 day clock.
Site Visit Partial 09/08/2020
Misc
Informational
08/31/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
08/31/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
08/31/2020
3-19-20 There is no activity on site today.
Misc
Informational
08/31/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time.
Site Visit Partial 9/10/2020 9/10/2020 09/10/2020
Misc
Informational
09/08/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/08/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/08/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/08/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain.
Site Visit Partial 9/11/2020 9/11/2020 09/11/2020
Misc
Informational
09/10/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/10/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/10/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/10/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather.
Site Visit Partial 9/14/2020 9/14/2020 09/14/2020
Misc
Informational
09/11/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/11/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/11/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/11/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me.
Site Visit Partial 9/16/2020 9/16/2020 09/16/2020
Misc
Informational
09/14/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/14/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/14/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/14/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site.
Retaining Wall Inspection Partial 9/18/2020 9/18/2020 09/18/2020
Misc
Informational
09/18/2020
9-18-20 7:58am They have approximately 5 rows of blocks set and filled with rock
Retaining Wall Inspection Partial 9/21/2020 9/21/2020 09/21/2020
Misc
Informational
09/18/2020
9-18-20 7:58am They have approximately 5 rows of blocks set and filled with rock. 9-21-20 10:07am The wall on the south side of the site is built. They now need to backfill.
Pavement-Surface Partial 09/21/2020
Misc
Informational
06/16/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
09/21/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week.
Pavement-Surface Partial 09/22/2020
Misc
Informational
09/21/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
09/21/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock.
Site Visit Partial 09/23/2020
Misc
Informational
09/16/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/16/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/16/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/16/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time.
Site Visit Partial 09/24/2020
Misc
Informational
09/23/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/23/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/23/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/23/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building.
Pavement-Proof Roll Failed 9/24/2020 9/24/2020 09/24/2020
Misc
Informational
06/15/2020
6-15-20 We proof rolled at 11am. It has passed with at 20 ton load. 9-24-20 11:35am The truck was to light. He had no proof of load weight.
Water Line - Construction Inspection Passed 9/29/2020 9/29/2020 09/29/2020
Misc
Informational
06/05/2020
4-7-20 2:04pm They had removed a fire hydrant to run sanitary and they have now installed back.9:19am They are starting to dig out to start installing waterline. They have approximately 30’ installed.4-24-20 8:10am They have poured thrust blocks and will be working on getting a fire hydrant installed before rain moves in. 4-28-20 8:55am All of the water line has been installed along with all thrust blocks and straddle blocks. Rodriguez plans of filling the water line later this week. 5-19-20 Rodriguez is running the service water lines to the vaults. They will be pouring the concrete thrust blocks later today. 5-21-20 They have poured all the trust restraints up to the vaults. They are currently working on setting up and pouring the thrust blocks coming out of the vaults. 5-22-20 All of the thrust blocks are poured. They are going to fill and flush the water line. We will pressure test on Tuesday 5-26-20. 5-26-20 They have flushed the line and are setting up for the hydrostatic test. 5-26-20 Rodriguez is staring to chlorinate the water line. The water line is chlorinated. We will flush in 24 hours. 5-27-20 Rodriguez flushed all of the chlorine out and we will pull samples on 5-28-20.
Misc
Informational
06/05/2020
Sunny mid 60”s at 7:00 AM Rodriguez began installing 4” temporary fire line & water line. Approximately 108’ of fire line 4” DIP & 90’ of water main 4” DIP. 2/45 degree bends and (2/90 degree bend with backing block) on the fire line. 2/45 degree bend on the water main. Contractor draw a rough draft of temporary fire main & water main. 6-1-20 We have shut the water off for the tie-in on the west side of the job site. The are currently draining the water. The tie-in is finished and water is on. 6-4-20 10:41pm We performed a test shut down at 5am and all was well. We are getting ready to shut off the water to tie-in the water main. 11:06pm They are working on getting everything in place. 6-5-20 2:36am They have all water lines connected and are back filling with rock. 2:59am We have turned the water back on and are filling the main. The main is filled and air is out. The hospital is back in service. 9-29-20 6:39pm Rodriguez has shut the water off and moved fire hydrant 016-031. The are turning the water back on now. 6:53pm The water is back on and they will pour the thrust blocks in the morning.
Water Line - Thrust Restraint Passed 09/30/2020
Misc
Informational
09/30/2020
9-30-20 10:54am The thrust restraints are poured.
Pavement-Proof Roll Passed 9/30/2020 9/30/2020 09/30/2020
Misc
Informational
09/24/2020
6-15-20 We proof rolled at 11am. It has passed with at 20 ton load. 9-24-20 11:35am The truck was to light. He had no proof of load weight. 9–29-20 1:19am 1:43pm The driveway on the SE side of the site failed. 9-30-20 2:19pm The driveway has passed the proof roll at this time.
Pavement-Surface Partial 10/05/2020
Misc
Informational
09/22/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
09/22/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site.
Pavement-Curb Construction Partial 10/06/2020
Misc
Informational
06/11/2020
6-11-20 10:22am Shaw is pouring the curb on the South West corner of the site. They have been informed to use white cure. PSI did a subgrade inspection. They installed geogrid and type 5 base. I was not informed of the pour taking place. 2:50pm Shaw did not cure any of the curb fully the tempature out side 85 degrees. There is approximately 244 ‘ that received no cure at all for over 5 hours. The intire run of curb had no cure on the back side leaving bare concrete exposed in the heat for approximately 5 plus hours. It is my recommendation that it be removed and replaced. Cure should be applied right after final finish.
Misc
Informational
10/06/2020
10-6-20 10:47am Precision Conctete has poured curb along the building. They have used white cure.
Pavement-Surface Partial 10/6/2020 10/6/2020 10/06/2020
Misc
Informational
10/05/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
10/05/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site.
Pavement-Surface Partial 10/7/2020 10/7/2020 10/07/2020
Misc
Informational
10/06/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
10/06/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out.
Proof roll parking lot Partial 10/08/2020
Misc
Informational
10/08/2020
10-8-20 11:15am They have proof rolled the drive on the east and west have passed. The parking lot in the center has failed and will need corrections and a new proof roll.
Proof roll parking lot Passed 10/9/2020 10/9/2020 10/09/2020
Misc
Informational
10/08/2020
10-8-20 11:15am They have proof rolled the drive on the east and west have passed. The parking lot in the center has failed and will need corrections and a new proof roll. 10-9-20 8:54am The parking lot has a soft spot approximately 15’ that will need corrected. 9:44am We are waiting on a truck to proof roll again. 10:30am There is still a soft spot. They have dug it down and will add more base asphalt. PSI is on site and agrees with this correction.
Pavement-Surface Partial 10/9/2020 10/9/2020 10/09/2020
Misc
Informational
10/07/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
10/07/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out. 10-9-20 8:40am Seal-O-Matic is on site laying the asphalt for the parking and road on the south side of the site. They are laying Type 1. They will try to lay the surface later today. The Forman for the crew became argumentative with me over the temps of the base. We require 140 degrees before the next lift. Steve Robbins came out to vererify the temps. They were averaging 150 to 165. Steve allowed them to continue. They will be emailing me with copies of the tickets.
Pavement-Surface Partial 10/12/2020 10/12/2020 10/12/2020
Misc
Informational
10/09/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
10/09/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out. 10-9-20 8:40am Seal-O-Matic is on site laying the asphalt for the parking and road on the south side of the site. They are laying Type 1. They will try to lay the surface later today. The Forman for the crew became argumentative with me over the temps of the base. We require 140 degrees before the next lift. Steve Robbins came out to vererify the temps. They were averaging 150 to 165. Steve allowed them to continue. They will be emailing me with copies of the tickets. 10-12-20 9:53am They are setting up the drives on the south side of the buildings for concrete. 2:58pm I have spoke with the superintendent and they will be pouring on 10-13-20.
Pavement-Surface Partial 10/13/2020 10/13/2020 10/13/2020
Misc
Informational
10/12/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
10/12/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out. 10-9-20 8:40am Seal-O-Matic is on site laying the asphalt for the parking and road on the south side of the site. They are laying Type 1. They will try to lay the surface later today. The Forman for the crew became argumentative with me over the temps of the base. We require 140 degrees before the next lift. Steve Robbins came out to vererify the temps. They were averaging 150 to 165. Steve allowed them to continue. They will be emailing me with copies of the tickets. 10-12-20 9:53am They are setting up the drives on the south side of the buildings for concrete. 2:58pm I have spoke with the superintendent and they will be pouring on 10-13-20. 10-13-20 9:14am They are pouring concrete on the east side of the garage at this time. 10-14-20 8:54am The drives are poured and they are cutting the joints.
Site Visit Complete 10/23/2020
Misc
Informational
09/24/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
09/24/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
09/24/2020
3-19-20 There is no activity on site today.
Misc
Informational
09/24/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-16-20 8:48am There is no work on site at this time. 10-22-20 8:13am There was a rain event. There is no work taking place at this time. 10-23-20 8:45am Raining. There is no work on site today.
Erosion Control Inspection Partial 10/23/2020 10/23/2020 10/23/2020
Misc
Informational
10/23/2020
10-23-20 9:40am Raining. There are no erosion issues at this time.
Site Visit Partial 10/27/2020
Misc
Informational
10/15/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
10/15/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
10/15/2020
3-19-20 There is no activity on site today.
Misc
Informational
10/15/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today.
Sidewalk Inspection Partial 10/28/2020
Misc
Informational
10/28/2020
10-28-2020 They are pouring the sidewalk next to the drive on the south side of the site.
Site Visit Partial 10/28/2020
Misc
Informational
10/27/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
10/27/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
10/27/2020
3-19-20 There is no activity on site today.
Misc
Informational
10/27/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time.
Sidewalk Inspection Partial 10/29/2020
Misc
Informational
10/28/2020
10-28-2020 They are pouring the sidewalk next to the drive on the south side of the site. 10-29-20 2:05pm They have poured the sidewalk on the west side of the garage doors.
Sidewalk Inspection Partial 10/30/2020
Misc
Informational
10/29/2020
10-28-2020 They are pouring the sidewalk next to the drive on the south side of the site. 10-29-20 2:05pm They have poured the sidewalk on the west side of the garage doors. 10-30-20 3:25pm They have poured the walk for the helicopter pad. The sidewalk by the doors are ADA compliant.
Site Visit Partial 11/02/2020
Misc
Informational
10/28/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
10/28/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
10/28/2020
3-19-20 There is no activity on site today.
Misc
Informational
10/28/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 1-2-20 8:28am There is no work taking place at this time.
Site Visit Partial 11/04/2020
Misc
Informational
11/02/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
11/02/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
11/02/2020
3-19-20 There is no activity on site today.
Misc
Informational
11/02/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time.
Site Visit Partial 11/06/2020
Misc
Informational
11/04/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
11/04/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
11/04/2020
3-19-20 There is no activity on site today.
Misc
Informational
11/04/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time.
Sidewalk Inspection Passed 11/06/2020
Misc
Informational
10/30/2020
10-28-2020 They are pouring the sidewalk next to the drive on the south side of the site. 10-29-20 2:05pm They have poured the sidewalk on the west side of the garage doors. 10-30-20 3:25pm They have poured the walk for the helicopter pad. The sidewalk by the doors are ADA compliant.
Site Visit Partial 11/9/2020 11/9/2020 11/09/2020
Misc
Informational
11/06/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
11/06/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
11/06/2020
3-19-20 There is no activity on site today.
Misc
Informational
11/06/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-12-20 7:35am No work on site at this time. 11-13-20 8:01am No work on site at this time that requires inspections. 11-19-20 2:23PM There is no work taking place that needs inspections at this time. 11-20-20 7:57am No inspections needed at this time.
Erosion Control Inspection Partial 11/10/2020 11/10/2020 11/10/2020
Misc
Informational
10/23/2020
10-23-20 9:40am Raining. There are no erosion issues at this time. 11-10-20 2:43pm All erosion controls are in place and working at this time.
Site Visit Partial 11/23/2020 11/23/2020 11/23/2020
Misc
Informational
11/09/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
11/09/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
11/09/2020
3-19-20 There is no activity on site today.
Misc
Informational
11/09/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed.
Erosion Control Inspection Partial 11/25/2020
Misc
Informational
11/10/2020
10-23-20 9:40am Raining. There are no erosion issues at this time. 11-10-20 2:43pm All erosion controls are in place and working at this time. 11-25-20 9:30am All erosion controls are in place and working at this time.
Erosion Control Inspection Partial 12/11/2020
Misc
Informational
11/25/2020
10-23-20 9:40am Raining. There are no erosion issues at this time. 11-10-20 2:43pm All erosion controls are in place and working at this time. 11-25-20 9:30am All erosion controls are in place and working at this time. 12-11-20 7:55am Light rain. All erosion controls are in place and working at this time.
Retaining Wall Inspection Passed 12/14/2020
Misc
Informational
09/21/2020
9-18-20 7:58am They have approximately 5 rows of blocks set and filled with rock. 9-21-20 10:07am The wall on the south side of the site is built. They now need to backfill.
Storm - Pipe Passed 12/14/2020
Misc
Informational
05/13/2020
3-30-20 They installed six sticks.
Misc
Informational
05/13/2020
3-20-20 They are digging out for sanitary and will working on more storm line today. 2:40pm They have hit rock and will be breaking for awhile.
Misc
Informational
05/13/2020
3-18-20 They have the collar poured and invert. They have one stick of storm pipe coming out of box 107.
Misc
Informational
05/13/2020
4-1-20 10:47am They are setting box 106 and installing storm pipe. 2:55pm They have 3 sticks of storm pipe installed and should have 3 more by the end of the day.
Misc
Informational
05/13/2020
3-17-20 They have installed storm pipe up to box 107. They are pouring the collar and invert after 5pm.
Misc
Informational
05/13/2020
3-13-20 8:43am They have board out the storm box and set the pipe. They have poured the collar. They have two sections of storm install at this time. 2:15pm They have a total of 11 sticks installed.
Misc
Informational
05/13/2020
3-30-20 12:45pm They are digging down to install storm pipe. They installed 6 sticks of 30” today
Misc
Informational
05/13/2020
Misc
Informational
05/13/2020
3-25-20 3:23pm They have installed 4 sticks of storm pipe out of box 107 today
Misc
Informational
05/13/2020
3-26-20 10:12am They have one stick of storm installed. They are now switching over to sanitary.
Misc
Informational
05/13/2020
4-2-20 9:24am They have a total of 6 sticks of storm pipe coming out of box 106 at this time.
Misc
Informational
05/13/2020
4-4-20 8:29am They have storm box 105 set and the storm pipe laid into it. They are now switching over to sanitary.
Misc
Informational
05/13/2020
4-4-20 10:40AM At 11am they are pouring the collars and inverts for storm box 105.
Misc
Informational
05/13/2020
4-6-20 3:01pm They have changed out the center section of box 105 for the correct one. They have not installed any pipe today.
Misc
Informational
05/13/2020
4-7-20 2:00pm They have three sticks of storm pipe coming out of box 105. They are going to summit a new plan for changing the storm pipe material.
Misc
Informational
05/13/2020
4-8-20 a They have 4 1/2 sticks coming out of box 105 the box 104. They have poured collars on box 105 and 104. 3:12pm They have set the lid on box 105 and backfilled.
Misc
Informational
05/13/2020
4-14-20 10:59am They have installed two sticks of storm pipe coming out of box 104 heading to box 103. 1:13pm They are digging around obstacles to install more storm pipe.
Misc
Informational
05/13/2020
4-15-20 8:51am They have a total of 5 sticks installed. The crew went home early. 4-16-20 2:33pm They have set storm up to box 103. They are connecting to nyloplast and will be working on the curb inlet with 30” drain. 4-16-20 They installed 5 joints of 30” RCP. 4-17-20 11:45am They are pouring flowable fill and will be reinstalling the fire hydrant.
Misc
Informational
05/13/2020
4-20-20 9:00am Rodriguez is waiting on locates before they can install anymore storm pipe. They are cutting into box 107 to add storm pipe
Misc
Informational
05/13/2020
4-21-20 8:26am Rodrigues has cut into storm box 107. They are waiting on locates to proceed 3:14pm they have installed 1 stick of storm pipe. 4-22-20 9:21am They have a total of 30’ of storm pipe installed. 4-30-20 They have the storm pipe running into the storm manhole.5-5-20 they have four sticks of storm pipe coming out of the existing storm box going for box 101. 5-6-20 Rodrigues has completed storm line 1. They poured all collars and inverts and have back filled. 5-7-20 9:04am They have set box 103 and ran approximately 60’ of pipe to the existing box. They will be pouring collars and inverts at 1pm today. They got the collars and inverts poured.
Misc
Informational
05/13/2020
5-12-20 Rodriguez installed box 301 and 201. All storm pipe has been installed and collars poured with inverts. They are now working on line 4. They have cut Into box 402 and will be installing storm pipe going to box 401. 5-12-20 They installed the storm pipe and poured collars and inverts.
Storm - Material Verification Passed 12/14/2020
Misc
Informational
03/13/2020
3-13-20 All storm material appears to be correct for the job.
Sanitary - Material Verification Passed 12/14/2020
Water - Material Verification Passed 12/14/2020
Storm - Material Verification Passed 12/14/2020
Water - Material Verification Passed 12/14/2020
Sanitary Sewer - Air Test Passed 12/14/2020
Storm - Swales Passed 12/14/2020
Water Line - Coliform Test 1 Passed 12/14/2020
Misc
Informational
05/28/2020
5-28-20 9:30am Raining. We pulled 5 water samples at 10am. 10:35am I have dropped the samples off at the lab. These are for first round.
Water Line - Coliform Test 2 Passed 12/14/2020
Misc
Informational
05/29/2020
5-29-20 We pulled 5 samples for the second round. I will deliver them downtown.
Misc
Informational
05/29/2020
5-29-20 We pulled 5 samples for the second round. I will deliver them downtown. 11:19am The samples have been dropped off at the lab.
Water Line - Coliform Test 2 Passed 12/14/2020
Site Visit Partial 12/14/2020
Misc
Informational
11/23/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
11/23/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
11/23/2020
3-19-20 There is no activity on site today.
Misc
Informational
11/23/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time,
Site Visit Partial 12/15/2020
Misc
Informational
12/14/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
12/14/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
12/14/2020
3-19-20 There is no activity on site today.
Misc
Informational
12/14/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time.
Pavement-Curb Construction Partial 12/15/2020
Misc
Informational
10/06/2020
6-11-20 10:22am Shaw is pouring the curb on the South West corner of the site. They have been informed to use white cure. PSI did a subgrade inspection. They installed geogrid and type 5 base. I was not informed of the pour taking place. 2:50pm Shaw did not cure any of the curb fully the tempature out side 85 degrees. There is approximately 244 ‘ that received no cure at all for over 5 hours. The intire run of curb had no cure on the back side leaving bare concrete exposed in the heat for approximately 5 plus hours. It is my recommendation that it be removed and replaced. Cure should be applied right after final finish.
Misc
Informational
10/06/2020
10-6-20 10:47am Precision Conctete has poured curb along the building. They have used white cure.
Misc
Informational
12/15/2020
12-15-20 I met with the contractor about setting up curb on the south side of the building. They want to pour at 1:30pm. The temp is showing that it will be warm enough. They will be covering with blankets.
Pavement-Curb Construction Partial 12/15/2020
Misc
Informational
12/15/2020
6-11-20 10:22am Shaw is pouring the curb on the South West corner of the site. They have been informed to use white cure. PSI did a subgrade inspection. They installed geogrid and type 5 base. I was not informed of the pour taking place. 2:50pm Shaw did not cure any of the curb fully the tempature out side 85 degrees. There is approximately 244 ‘ that received no cure at all for over 5 hours. The intire run of curb had no cure on the back side leaving bare concrete exposed in the heat for approximately 5 plus hours. It is my recommendation that it be removed and replaced. Cure should be applied right after final finish.
Misc
Informational
12/15/2020
10-6-20 10:47am Precision Conctete has poured curb along the building. They have used white cure.
Misc
Informational
12/15/2020
12-15-20 I met with the contractor about setting up curb on the south side of the building. They want to pour at 1:30pm. The temp is showing that it will be warm enough. They will be covering with blankets. 12-15-20 2:37pm They have poured the curb and are puttin g the finish on. They will covering with blankets.
Pavement-Curb Construction Partial 12/16/2020
Misc
Informational
12/15/2020
6-11-20 10:22am Shaw is pouring the curb on the South West corner of the site. They have been informed to use white cure. PSI did a subgrade inspection. They installed geogrid and type 5 base. I was not informed of the pour taking place. 2:50pm Shaw did not cure any of the curb fully the tempature out side 85 degrees. There is approximately 244 ‘ that received no cure at all for over 5 hours. The intire run of curb had no cure on the back side leaving bare concrete exposed in the heat for approximately 5 plus hours. It is my recommendation that it be removed and replaced. Cure should be applied right after final finish.
Misc
Informational
12/15/2020
10-6-20 10:47am Precision Conctete has poured curb along the building. They have used white cure.
Misc
Informational
12/15/2020
12-15-20 I met with the contractor about setting up curb on the south side of the building. They want to pour at 1:30pm. The temp is showing that it will be warm enough. They will be covering with blankets. 12-15-20 2:37pm They have poured the curb and are puttin g the finish on. They will covering with blankets. 12-16-20 8:18am They are wrecking the forms for the curb and will saw cut. The blankets will be put back on the curb after the cuts are made due to weather.
Pavement-Surface Partial 12/19/2020
Misc
Informational
10/13/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
10/13/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out. 10-9-20 8:40am Seal-O-Matic is on site laying the asphalt for the parking and road on the south side of the site. They are laying Type 1. They will try to lay the surface later today. The Forman for the crew became argumentative with me over the temps of the base. We require 140 degrees before the next lift. Steve Robbins came out to vererify the temps. They were averaging 150 to 165. Steve allowed them to continue. They will be emailing me with copies of the tickets. 10-12-20 9:53am They are setting up the drives on the south side of the buildings for concrete. 2:58pm I have spoke with the superintendent and they will be pouring on 10-13-20. 10-13-20 9:14am They are pouring concrete on the east side of the garage at this time. 12-19-20 1:35pm Seal-O-Matic are laying base asphalt for the patch ti-in on the south side of the building. This is hand work. 2:11pm They are finishing up now.
Pavement-Curb Construction Passed 12/21/2020
Misc
Informational
12/16/2020
6-11-20 10:22am Shaw is pouring the curb on the South West corner of the site. They have been informed to use white cure. PSI did a subgrade inspection. They installed geogrid and type 5 base. I was not informed of the pour taking place. 2:50pm Shaw did not cure any of the curb fully the tempature out side 85 degrees. There is approximately 244 ‘ that received no cure at all for over 5 hours. The intire run of curb had no cure on the back side leaving bare concrete exposed in the heat for approximately 5 plus hours. It is my recommendation that it be removed and replaced. Cure should be applied right after final finish.
Misc
Informational
12/16/2020
10-6-20 10:47am Precision Conctete has poured curb along the building. They have used white cure.
Misc
Informational
12/16/2020
12-15-20 I met with the contractor about setting up curb on the south side of the building. They want to pour at 1:30pm. The temp is showing that it will be warm enough. They will be covering with blankets. 12-15-20 2:37pm They have poured the curb and are puttin g the finish on. They will covering with blankets. 12-16-20 8:18am They are wrecking the forms for the curb and will saw cut. The blankets will be put back on the curb after the cuts are made due to weather.
Site Visit Partial 12/21/2020
Misc
Informational
12/15/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
12/15/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
12/15/2020
3-19-20 There is no activity on site today.
Misc
Informational
12/15/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time.
Pavement-Surface Partial 12/22/2020
Misc
Informational
12/19/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
12/19/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out. 10-9-20 8:40am Seal-O-Matic is on site laying the asphalt for the parking and road on the south side of the site. They are laying Type 1. They will try to lay the surface later today. The Forman for the crew became argumentative with me over the temps of the base. We require 140 degrees before the next lift. Steve Robbins came out to vererify the temps. They were averaging 150 to 165. Steve allowed them to continue. They will be emailing me with copies of the tickets. 10-12-20 9:53am They are setting up the drives on the south side of the buildings for concrete. 2:58pm I have spoke with the superintendent and they will be pouring on 10-13-20. 10-13-20 9:14am They are pouring concrete on the east side of the garage at this time. 12-19-20 1:35pm Seal-O-Matic are laying base asphalt for the patch ti-in on the south side of the building. This is hand work. 2:11pm They are finishing up now. 12-22-20 5:01pm They are putting the surface on the patch on the south side against the curb. They are using Type 3. 5:30pm They have finished the patch.
Site Visit Partial 02/10/2021
Misc
Informational
12/21/2020
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
12/21/2020
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
12/21/2020
3-19-20 There is no activity on site today.
Misc
Informational
12/21/2020
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather.
Site Visit Partial 02/18/2021
Misc
Informational
02/10/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
02/10/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
02/10/2021
3-19-20 There is no activity on site today.
Misc
Informational
02/10/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order.
Site Visit Partial 2/23/2021 2/23/2021 02/23/2021
Misc
Informational
02/18/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
02/18/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
02/18/2021
3-19-20 There is no activity on site today.
Misc
Informational
02/18/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean.
Site Visit Partial 2/24/2021 2/24/2021 02/24/2021
Misc
Informational
02/23/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
02/23/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
02/23/2021
3-19-20 There is no activity on site today.
Misc
Informational
02/23/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time.
Site Visit Partial 3/1/2021 3/1/2021 03/01/2021
Misc
Informational
02/24/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
02/24/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
02/24/2021
3-19-20 There is no activity on site today.
Misc
Informational
02/24/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time.
Site Visit Partial 03/03/2021
Misc
Informational
03/01/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/01/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/01/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/01/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time.
Site Visit Partial 03/09/2021
Misc
Informational
03/03/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/03/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/03/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/03/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting.
Site Visit Partial 03/12/2021
Misc
Informational
03/09/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/09/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/09/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/09/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside.
Site Visit Partial 3/15/2021 3/15/2021 03/15/2021
Misc
Informational
03/12/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/12/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/12/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/12/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me.
Site Visit Partial 03/24/2021
Misc
Informational
03/15/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/15/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/15/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/15/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the grain around the parking lot.
Site Visit Partial 3/31/2021 03/31/2021
Misc
Informational
03/24/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/24/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/24/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/24/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time.
Sidewalk Inspection Partial 04/14/2021
Misc
Informational
04/14/2021
4-14-21 8:28am George Shaw is on site setting up a sidewalk for the employee entrance on the west side of the building. They have a 8. Fall and plenty of rock.
Site Visit Partial 04/26/2021
Misc
Informational
03/31/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
03/31/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
03/31/2021
3-19-20 There is no activity on site today.
Misc
Informational
03/31/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections.
Commercial Curb Inspection Partial 4/27/2021 4/27/2021 04/27/2021
FIFTH FLOOR
Informational
04/27/2021
4-27-21 9:48am Shaw is on site setting up curb on the west side. 2:50pm They are pouring the curb approximately 11 yards.
Commercial Curb Inspection Partial 04/29/2021
FIFTH FLOOR
Informational
04/27/2021
4-27-21 9:48am Shaw is on site setting up curb on the west side. 2:50pm They are pouring the curb approximately 11 yards. 2-29-21 11:24am The curbs are poured and cured white. They have backfilled behind the curbs.
Site Visit Partial 4/30/2021 04/30/2021
Misc
Informational
04/26/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
04/26/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
04/26/2021
3-19-20 There is no activity on site today.
Misc
Informational
04/26/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections. 4-30-21 8:44am There are no inspections needed.
Site Visit Partial 5/4/2021 05/04/2021
Misc
Informational
04/30/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
04/30/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
04/30/2021
3-19-20 There is no activity on site today.
Misc
Informational
04/30/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections. 4-30-21 8:44am There are no inspections needed. 5-4-21 9:09am Light rain. Crowley dump trucks are on site cleaning up the staging lot. There is no other work taking place.
Site Visit Partial 5/6/2021 05/06/2021
Misc
Informational
05/04/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/04/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/04/2021
3-19-20 There is no activity on site today.
Misc
Informational
05/04/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections. 4-30-21 8:44am There are no inspections needed. 5-4-21 9:09am Light rain. Crowley dump trucks are on site cleaning up the staging lot. There is no other work taking place. 5-6-21 2:06pm They are grading the site around the building.
Site Visit Partial 05/07/2021
Misc
Informational
05/06/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/06/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/06/2021
3-19-20 There is no activity on site today.
Misc
Informational
05/06/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections. 4-30-21 8:44am There are no inspections needed. 5-4-21 9:09am Light rain. Crowley dump trucks are on site cleaning up the staging lot. There is no other work taking place. 5-6-21 2:06pm They are grading the site around the building. 5-7-21 Shaw is on site cleaning up around curbs. The superintendent is hoping to have surface for the road next week.
Site Visit Partial 05/10/2021
Misc
Informational
05/07/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/07/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/07/2021
3-19-20 There is no activity on site today.
Misc
Informational
05/07/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections. 4-30-21 8:44am There are no inspections needed. 5-4-21 9:09am Light rain. Crowley dump trucks are on site cleaning up the staging lot. There is no other work taking place. 5-6-21 2:06pm They are grading the site around the building. 5-7-21 Shaw is on site cleaning up around curbs. The superintendent is hoping to have surface for the road next week. 5-10-21 10:28am There is no work taking place on site at this time.
Site Visit Partial 5/11/2021 05/11/2021
Misc
Informational
05/10/2021
3-2-20 2:55pm There is no work on site at this time.
Misc
Informational
05/10/2021
3-10-20 2:13pm I spoke with the super and looked at erosion controls that are in place for the land disturbance permit.
Misc
Informational
05/10/2021
3-19-20 There is no activity on site today.
Misc
Informational
05/10/2021
4-1-20 7:37am Rodriguez is moving material around to get ready for more sanitary and storm. 4-27-20 8:26am Raining. There is no work being done on site at this time due to weather. 5-1-20 9:39am Rodriguez are unloading storm pipe at this time.5-1-20 2:00PM They have done demo on asphalt and backfilled the storm drains. They have hit a live sanitary manhole and are working on the repair. 5-4-20 The crew was working on storm until the rain moved in then they quit for the day. 5-5-20 I met with Steve Robbins and on Burns to go over the water tie-in for the hospital. 6-3-20 I met with water on site to locate valves for a water shut off. 6-4-20 4:39am We are doing a test shutdown for the water. 5:09am The test shutdown went fine. We will be shutting of the water at 11pm tonight. 6-9-20 Rodriguez is not on site today. 6-18-20 There were no inspections needed on site today. 6-29-20 10:58am There is no activity that requires inspections at this time. 6-30-20 9:54am There is no activity that requires inspections at this time. 7-1-20 11:21am There is no activity that requires inspections at this time. 7-6-20 10:25am There is no activity that requires inspections at this time. 7-7-20 9:55am There is no work taking place that requires inspections from me at this time. 7-8-20 2:25pm No activity on site today that requires inspections. 7-9-20 10:34am There is no activity on site at this time. 7-10-20 3:16PM There is no work on site today. 7-13-20 8:18am The activity on site does not require any inspections from me at this time. 7-14-20 7:47am The activity on site does not require any inspections from me at this time. 7-16-20 10:32am The work taking place does not require any inspection from me at this time. 7-20-20 8:21am They have done some grading around the curbs. There is no other activity taking place right now. 7-24-20 2:15pm There is no activity that requires a inspection at this time. 7-31-20 9:49am There is no activity on site today due to weather. 8-5-20 3:36pm There is no activity on site at this time that requires a inspection. 8-6-20 8:45am There is no activity on site today. 8-14-20 11:09am There is no activity on site today that requires inspections. 8-17-20 3:15pm There are no work being done that requires inspections. 8-18-20 2:46pm No inspections needed at this time. 8-21-20 11:38am They have poured a sidewalk panel. I was not notified of this for and inspection. 8-31-20 10:46am I spoke with Travis about the land disturbance on the north side of the hospital. My concern was that there is wet land there. He told me that has been changed and it is no longer wet land. 9-8-20 11:27am There is no work on site that requires inspections at this time. 9-10-20 9:37am There is no activity on site due to rain. 9-11-20 10:44am There is no work taking place today due to weather. 9-145-20 10:20am There is no work taking place today that requires a inspection from me. 9-16-20 3:15pm MSE Hardscapes are on site building the retaining wall along the south side of the site. 9-23-20 11:14am There is no work taking place that requires inspections at this time. 9-24-20 11:02AM Rodriguez is razing the manholes on the driveway at the south side of the building. 10-15-20 8:02am There are no inspections needed at this time. 10-27-20 10:24am No inspections are needed today. 10-28-20 2:55pm There is no work taking place that needs inspections at this time. 11-2-20 8:28am There is no work taking place at this time. 11-4-20 10:35am No work taking place at this time. 11-6-20 10:36am No work needing inspections at this time. 11-9-20 11:03am There is no work taking place at this time that requires inspection. 11-23-20 9:26am No inspections needed. 12-14-20 10:43am There are no inspections needed by me at this time. 12-15-20 8:13am No inspections needed at this time. 12-21-20 7:44am No inspections needed at this time. 2-10-21 11:30am Light snow. There is no work taking place out side due to weather. 2-18-21 8am There is no work taking place and the site is in order. 2-23-21 There is no inspections needed today. The site is clean. 2-24-21 9:50am No inspections are needed at this time. 3-1-21 8:43am There is no activity that requires inspections at this time. 3-3-21 2:11pm The site looks good and there are no inspections needed from me at this time. 3-9-21 11:38am They are setting up the pad for helicopters. The forms are set and they are laying out the lighting. 3-12-21 3:17pm It has been raining and there is no work being done outside. 3-15-21 9:13am The work taking place requires no inspections from me. 3-24-21 1:20pm They have stabilized the graid around the parking lot. 3-31-21 9:04am There is no work taking place that requires inspections at this time. 4-26-21 11:41am The work taking place does not require any inspections. 4-30-21 8:44am There are no inspections needed. 5-4-21 9:09am Light rain. Crowley dump trucks are on site cleaning up the staging lot. There is no other work taking place. 5-6-21 2:06pm They are grading the site around the building. 5-7-21 Shaw is on site cleaning up around curbs. The superintendent is hoping to have surface for the road next week. 5-10-21 10:28am There is no work taking place on site at this time. 5-11-21 8:39am Light rain. There is no work taking place at this time. The road is prepped for surface.
Pavement-Surface Passed 5/12/2021 05/24/2021
Misc
Informational
12/22/2020
6-16-20 9:16am Seal O Matic paving Co. is doing the work. The temps out of the truck are averaging 290 degrees. 306 degrees at the paver. PSI is on site doing all testing. 3:35pm They have base down completely and have a second lift on the road. They are laying surface on the center section of road at this time.
Misc
Informational
12/22/2020
9-21-20 10:31am The have laid 8” of base rock type 5 against the south side of the building. They will be pouring concrete later in the week. 9-22-20 10:20am They are working on laying more base rock. 10-5-20 They have the forms set at the drive on the east side of the site. 10-6-20 2:04pm They are removing the intersection at the south east side of the site. 10-7-20 10:24am They have installed the base rock and are grading it out. 10-9-20 8:40am Seal-O-Matic is on site laying the asphalt for the parking and road on the south side of the site. They are laying Type 1. They will try to lay the surface later today. The Forman for the crew became argumentative with me over the temps of the base. We require 140 degrees before the next lift. Steve Robbins came out to vererify the temps. They were averaging 150 to 165. Steve allowed them to continue. They will be emailing me with copies of the tickets. 10-12-20 9:53am They are setting up the drives on the south side of the buildings for concrete. 2:58pm I have spoke with the superintendent and they will be pouring on 10-13-20. 10-13-20 9:14am They are pouring concrete on the east side of the garage at this time. 12-19-20 1:35pm Seal-O-Matic are laying base asphalt for the patch ti-in on the south side of the building. This is hand work. 2:11pm They are finishing up now. 12-22-20 5:01pm They are putting the surface on the patch on the south side against the curb. They are using Type 3. 5:30pm They have finished the patch. 5-12-21 11:25am Seal-O-Matic is on site prepping to lay surface between the parking on the south and the road to the north. 12:06pm The first truck has arrived. It will take three trucks to do the job. 12:51pm The last truck just pulled off. They have put down 65.70 ton of type 3 asphalt. There was no third party inspector on site for testing. The temperatures out of the trucks are in spec.
Documents & Images
Date Uploaded File Type Document Name
02/13/2020 Receipt Receipt for transaction: 2020-000592
02/18/2020 Letter DE-Permit
02/18/2020 sign permit St. Luke's
03/02/2020 Letter INSPECTION SUMMARY
03/10/2020 Letter INSPECTION SUMMARY
03/10/2020 Letter INSPECTION SUMMARY
03/13/2020 Storm pipe NW
03/13/2020 Storm box inside
03/13/2020 Storm pipe
03/13/2020 Storm pipe0
03/13/2020 Sanitary pipe
03/13/2020 Letter INSPECTION SUMMARY
03/13/2020 Wye and clamps
03/13/2020 Storm pipe joint
03/13/2020 Storm pipe1
03/13/2020 Letter INSPECTION SUMMARY
03/13/2020 Letter INSPECTION SUMMARY
03/13/2020 Letter INSPECTION SUMMARY
03/17/2020 Storm Box 107
03/18/2020 Letter DE-Daily Inspection Summary
03/18/2020 Letter INSPECTION SUMMARY
03/18/2020 Letter INSPECTION SUMMARY
03/19/2020 Letter INSPECTION SUMMARY
03/20/2020 Letter INSPECTION SUMMARY
03/23/2020 Letter INSPECTION SUMMARY
03/24/2020 Letter INSPECTION SUMMARY
03/25/2020 Letter INSPECTION SUMMARY
03/25/2020 Storm pipe2
03/25/2020 Letter INSPECTION SUMMARY
03/27/2020 Letter INSPECTION SUMMARY
03/30/2020 Letter INSPECTION SUMMARY
03/30/2020 Letter INSPECTION SUMMARY
03/31/2020 Manhole
03/31/2020 Letter INSPECTION SUMMARY
03/31/2020 Letter INSPECTION SUMMARY
04/01/2020 Letter INSPECTION SUMMARY
04/01/2020 Letter INSPECTION SUMMARY
04/02/2020 Storm box 106
04/02/2020 Letter INSPECTION SUMMARY
04/03/2020 Letter INSPECTION SUMMARY
04/04/2020 Storm box 105
04/04/2020 Letter INSPECTION SUMMARY
04/04/2020 Letter INSPECTION SUMMARY
04/06/2020 Letter INSPECTION SUMMARY
04/06/2020 Storm box with wrong center section
04/06/2020 Letter INSPECTION SUMMARY
04/07/2020 Storm
04/07/2020 Letter INSPECTION SUMMARY
04/07/2020 Letter INSPECTION SUMMARY
04/08/2020 Storm from 105 to 104
04/08/2020 Letter INSPECTION SUMMARY
02/19/2020 Plans 2020-02-18---SLE FLEX FACILITY EXPANSION--SITE UTILITY MAIN RELOCATIONS
04/09/2020 Plans Sanitary
04/09/2020 Approved Plans Approved revisions 2020-04-08--UTILITY UPDATE--Sheets C302 & C303
04/09/2020 Letter INSPECTION SUMMARY
04/13/2020 Sanitary line
04/13/2020 Letter INSPECTION SUMMARY
04/14/2020 Letter INSPECTION SUMMARY
04/14/2020 Letter INSPECTION SUMMARY
04/15/2020 Letter INSPECTION SUMMARY
04/15/2020 Approved Plans Approved Saint Luke's Flex Utility Relocate C401
04/16/2020 .jpg
04/16/2020 Storm pipe3
04/16/2020 Letter INSPECTION SUMMARY
04/17/2020 Letter INSPECTION SUMMARY
04/20/2020 Letter INSPECTION SUMMARY
04/21/2020 Box 107 storm pipe
04/21/2020 Letter INSPECTION SUMMARY
04/22/2020 Letter INSPECTION SUMMARY
04/23/2020 Waterline
04/23/2020 Letter INSPECTION SUMMARY
04/24/2020 Thrust block
04/24/2020 Thrust blocks
04/24/2020 Thrust blocks0
04/27/2020 Letter INSPECTION SUMMARY
04/28/2020 Fire hydrant thrust block
04/28/2020 Straddle block
04/28/2020 Fire hydrant east side
04/28/2020 Letter INSPECTION SUMMARY
04/30/2020 Letter INSPECTION SUMMARY
04/30/2020 Letter INSPECTION SUMMARY
05/01/2020 Letter INSPECTION SUMMARY
05/01/2020 Letter INSPECTION SUMMARY
05/04/2020 Letter INSPECTION SUMMARY
05/05/2020 Storm box 101
05/05/2020 Storm pipe4
05/05/2020 Letter INSPECTION SUMMARY
05/06/2020 Letter INSPECTION SUMMARY
05/07/2020 Letter INSPECTION SUMMARY
05/08/2020 Letter INSPECTION SUMMARY
05/13/2020 Letter INSPECTION SUMMARY
05/13/2020 Letter INSPECTION SUMMARY
05/14/2020 Air test sanitary
05/14/2020 Letter INSPECTION SUMMARY
05/14/2020 Letter INSPECTION SUMMARY
05/15/2020 Letter INSPECTION SUMMARY
05/15/2020 Letter INSPECTION SUMMARY
05/18/2020 Letter INSPECTION SUMMARY
05/19/2020 Letter INSPECTION SUMMARY
05/19/2020 Letter INSPECTION SUMMARY
05/21/2020 Thrust blocks1
05/21/2020 Water line 90
05/22/2020 Letter INSPECTION SUMMARY
05/26/2020 Pressure gauge.jpg
05/26/2020 Letter INSPECTION SUMMARY
05/26/2020 Letter INSPECTION SUMMARY
05/26/2020 Letter INSPECTION SUMMARY
05/28/2020 Letter INSPECTION SUMMARY
05/28/2020 Letter INSPECTION SUMMARY
05/29/2020 Letter INSPECTION SUMMARY
05/30/2020 image Temporary Fire & water main rough as-built draft.jpg
05/30/2020 Letter INSPECTION SUMMARY
05/30/2020 Letter INSPECTION SUMMARY
06/01/2020 Letter INSPECTION SUMMARY
06/03/2020 Letter INSPECTION SUMMARY
06/04/2020 Letter INSPECTION SUMMARY
06/05/2020 Letter INSPECTION SUMMARY
06/11/2020 No cure.jpg
06/11/2020 No cure 2.jpg
06/11/2020 No cure3.jpg
06/11/2020 Curb fail4.jpg
06/11/2020 Curb fail5.jpg
06/11/2020 Curb fail 6.jpg
06/11/2020 Letter INSPECTION SUMMARY
06/11/2020 Letter INSPECTION SUMMARY
06/15/2020 Letter INSPECTION SUMMARY
06/16/2020 Letter INSPECTION SUMMARY
06/17/2020 Letter INSPECTION SUMMARY
06/17/2020 Letter INSPECTION SUMMARY
06/18/2020 Letter INSPECTION SUMMARY
06/29/2020 Letter INSPECTION SUMMARY
06/30/2020 Letter INSPECTION SUMMARY
07/01/2020 Letter INSPECTION SUMMARY
07/06/2020 Letter INSPECTION SUMMARY
07/07/2020 Letter INSPECTION SUMMARY
07/08/2020 Letter INSPECTION SUMMARY
07/09/2020 Letter INSPECTION SUMMARY
07/09/2020 Letter INSPECTION SUMMARY
07/09/2020 Letter INSPECTION SUMMARY
07/09/2020 Letter INSPECTION SUMMARY
07/10/2020 Letter INSPECTION SUMMARY
07/13/2020 Letter INSPECTION SUMMARY
07/14/2020 Letter INSPECTION SUMMARY
07/16/2020 Letter INSPECTION SUMMARY
07/20/2020 Letter INSPECTION SUMMARY
07/24/2020 Letter INSPECTION SUMMARY
07/31/2020 Letter INSPECTION SUMMARY
08/05/2020 Letter INSPECTION SUMMARY
08/06/2020 Letter INSPECTION SUMMARY
08/14/2020 Letter INSPECTION SUMMARY
08/21/2020 Letter INSPECTION SUMMARY
08/21/2020 Letter INSPECTION SUMMARY
08/31/2020 Letter INSPECTION SUMMARY
09/08/2020 Letter INSPECTION SUMMARY
09/08/2020 Letter INSPECTION SUMMARY
09/08/2020 Letter INSPECTION SUMMARY
09/10/2020 Letter INSPECTION SUMMARY
09/10/2020 Letter INSPECTION SUMMARY
09/11/2020 Letter INSPECTION SUMMARY
09/14/2020 Letter INSPECTION SUMMARY
05/13/2020 Approved Plans APPROVED SLE FLEX FACILITY--FDP--CIVIL0
09/16/2020 Letter INSPECTION SUMMARY
09/18/2020 Letter INSPECTION SUMMARY
09/21/2020 Letter INSPECTION SUMMARY
09/21/2020 Letter INSPECTION SUMMARY
09/22/2020 Letter INSPECTION SUMMARY
09/23/2020 Letter INSPECTION SUMMARY
09/24/2020 Letter INSPECTION SUMMARY
09/24/2020 Letter INSPECTION SUMMARY
09/24/2020 Approved Plans SLE Flex Facility Pre-Utility Work Revised FH Location Approved 9.24.20
09/29/2020 Cutting the hydrant out.jpg
09/29/2020 Hydrant elbow.jpg
09/29/2020 Hydrant 016-031.jpg
09/29/2020 Letter INSPECTION SUMMARY
09/30/2020 Letter INSPECTION SUMMARY
09/30/2020 Letter INSPECTION SUMMARY
10/05/2020 Letter INSPECTION SUMMARY
10/06/2020 Letter INSPECTION SUMMARY
10/06/2020 Letter INSPECTION SUMMARY
10/08/2020 Letter INSPECTION SUMMARY
10/08/2020 Letter INSPECTION SUMMARY
10/09/2020 Letter INSPECTION SUMMARY
10/09/2020 Letter INSPECTION SUMMARY
10/12/2020 Letter INSPECTION SUMMARY
10/14/2020 Letter INSPECTION SUMMARY
10/14/2020 Letter INSPECTION SUMMARY
10/15/2020 Letter INSPECTION SUMMARY
10/16/2020 Letter INSPECTION SUMMARY
10/23/2020 Letter INSPECTION SUMMARY
10/27/2020 Letter INSPECTION SUMMARY
10/28/2020 Letter INSPECTION SUMMARY
10/28/2020 Letter INSPECTION SUMMARY
10/29/2020 Letter INSPECTION SUMMARY
10/30/2020 Letter INSPECTION SUMMARY
11/02/2020 Letter INSPECTION SUMMARY
11/04/2020 Letter INSPECTION SUMMARY
11/06/2020 Letter INSPECTION SUMMARY
11/06/2020 Letter INSPECTION SUMMARY
11/09/2020 Letter INSPECTION SUMMARY
11/10/2020 Letter INSPECTION SUMMARY
11/12/2020 Letter INSPECTION SUMMARY
11/23/2020 Letter INSPECTION SUMMARY
11/25/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 WO#1E02093 - City of Lees Summit ST LUKES SAMPLE 1
12/14/2020 WO#1E02279 - City of Lees Summit ST LUKES SAMPLE 2
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/14/2020 Letter INSPECTION SUMMARY
12/15/2020 Letter INSPECTION SUMMARY
12/15/2020 Letter INSPECTION SUMMARY
12/15/2020 Letter INSPECTION SUMMARY
12/16/2020 Letter INSPECTION SUMMARY
12/19/2020 Letter INSPECTION SUMMARY
12/21/2020 Letter INSPECTION SUMMARY
12/22/2020 Letter INSPECTION SUMMARY
12/22/2020 Letter INSPECTION SUMMARY
02/10/2021 Letter INSPECTION SUMMARY
02/18/2021 Letter INSPECTION SUMMARY
02/23/2021 Letter INSPECTION SUMMARY
02/24/2021 Letter INSPECTION SUMMARY
03/01/2021 Letter INSPECTION SUMMARY
03/03/2021 Letter INSPECTION SUMMARY
03/09/2021 Letter INSPECTION SUMMARY
03/12/2021 Letter INSPECTION SUMMARY
03/24/2021 Letter INSPECTION SUMMARY
03/24/2021 Letter INSPECTION SUMMARY
03/31/2021 Letter INSPECTION SUMMARY
04/14/2021 Letter INSPECTION SUMMARY
04/26/2021 Letter INSPECTION SUMMARY
04/27/2021 Letter INSPECTION SUMMARY
04/29/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
05/04/2021 Letter INSPECTION SUMMARY
05/06/2021 Letter INSPECTION SUMMARY
05/07/2021 Letter INSPECTION SUMMARY
05/10/2021 Letter INSPECTION SUMMARY
05/11/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter DE-Certificate of Substantial Completion Multiple Lot
11/03/2021 Plans 1212_UTILITY AS BUILTS_20211103
11/03/2021 Plans 1212_Final COLS Comments_20211103
12/03/2021 St. Lukes Maintenance Bond
12/06/2021 St. Lukes East Facility Final Affidavit and Agreement
12/06/2021 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home