Permit Application Status

PRSITE20192719


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20192719
Development - Site
Final Acceptance
ALDERSGATE METHODIST CHURCH
DEVELOPMENT COMPLETE
FIRE LINE EXTENSION
09/23/2019
10/14/2019
05/03/2022
Locations
Contacts
ALDERSGATE METHODIST CHURCH, Address:350 SW M 150 HWY  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 09/23/2019 10/14/2019
Marquelle Williams
Fees
Paid Fees Amount Paid Owing Date Paid
Water Insp Fee $1,164.00 $1,164.00 Paid 09/23/2019
Water Test Fee $200.00 $200.00 Paid 09/23/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Water Line - Hydrostatic Test Passed 10/21/2019
Misc
Informational
10/21/2019
OCTOBER 7, 2019 PASSED Hydrostatic test was performed by Advantage Fire. Test passed
Fire Line - Flush Passed 10/21/2019
Misc
Informational
10/21/2019
OCTOBER 8, 2019 Inspector John DiMauro physically watched Advantage Fire flush the Fire Line for approx 1 hour.
Water - Material Verification Passed 10/21/2019
Water Line - Valve Passed 10/21/2019
Water Line - Construction Taps Removed Passed 10/21/2019
Water - Material Verification Passed 10/21/2019
Erosion Control Inspection Passed 10/21/2019
Water Line - Fire Hydrant Passed 10/21/2019
Misc
Informational
10/21/2019
SEPTEMBER 30, 2019 Inspector arrived on site to inspect Fire Hydrant, 6” gate valve” and 90 degree Dip bends before Advantage Fire installed them.
Misc
Informational
10/21/2019
September 30, 2019 Inspector Inspected Fire Hydrant, Gate Valve, and Dip Bend after Advantage Fire installed them. Crews will be pouring thrust block restraints later on in the evening.
Misc
Informational
10/21/2019
OCTOBER 2, 2019 Inspector came out to Inspect Fire, Hydrant, Tees, Dip Bend, and Gate Valve. All items are installed correctly. @ STA. 1+36.59.
Water Line - Thrust Restraint Passed 10/21/2019
Misc
Informational
10/21/2019
SEPTEMBER 27, 2019 Advantage Fire crew poured restraint thrust block Just outside building.
Misc
Informational
10/21/2019
SEPTEMBER 30, 2019 Advanced Fire crew poured and installed thrust block restraints for the Fire Hydrant, and all the Fire Line Bends that were installed.
Grading/Excavation/Fill Inspection Passed 10/21/2019
Misc
Informational
10/21/2019
SEPTEMBER 26, 2019 Upon Inspectors arrival, Advantage Fire crew was excavating soil and removing old fire line.
Misc
Informational
10/21/2019
SEPTEMBER 27, 2019 Inspector came back on site to verify that Advantage Fire had installed the proper amount of gravel below and above Fire Line before crew could backfill.
Water Line - Construction Inspection Passed 10/21/2019
Misc
Informational
10/21/2019
SEPTEMBER 27, 2019 Advantage Fire had excavated and removed old fire line upon arrival. Crews had also installed new fire line from STA. 3+75.87 to approx. 3+50. Crews left space for thrust blocks and also powder coated bolts. The fire line has been fully poly wrapped.
Misc
Informational
10/21/2019
OCTOBER 1, 2019 Advantage Fire Crews continue to install Fire Line from approx STA 3+50 to STA 1+25
Water - Material Verification Passed 10/21/2019
Water - Material Verification Passed 10/21/2019
Water Line - Fire Hydrant Passed 10/22/2019
Misc
Informational
10/18/2019
SEPTEMBER 30, 2019 Inspector arrived on site to inspect Fire Hydrant, 6” gate valve” and 90 degree Dip bends before Advantage Fire installed them.
Misc
Informational
10/18/2019
September 30, 2019 Inspector Inspected Fire Hydrant, Gate Valve, and Dip Bend after Advantage Fire installed them. Crews will be pouring thrust block restraints later on in the evening.
Misc
Informational
10/21/2019
OCTOBER 2, 2019 Inspector came out to Inspect Fire, Hydrant, Tees, Dip Bend, and Gate Valve. All items are installed correctly. @ STA. 1+36.59.
Water Line - Thrust Restraint Passed 10/22/2019
Misc
Informational
10/18/2019
SEPTEMBER 27, 2019 Advantage Fire crew poured restraint thrust block Just outside building.
Misc
Informational
10/18/2019
SEPTEMBER 30, 2019 Advanced Fire crew poured and installed thrust block restraints for the Fire Hydrant, and all the Fire Line Bends that were installed.
Grading/Excavation/Fill Inspection Passed 10/22/2019
Misc
Informational
10/18/2019
SEPTEMBER 26, 2019 Upon Inspectors arrival, Advantage Fire crew was excavating soil and removing old fire line.
Misc
Informational
10/18/2019
SEPTEMBER 27, 2019 Inspector came back on site to verify that Advantage Fire had installed the proper amount of gravel below and above Fire Line before crew could backfill.
Water Line - Construction Inspection Passed 10/22/2019
Misc
Informational
10/21/2019
OCTOBER 3-4, 2019 At approx. 0+25.68, Fire Line is being installed. Piping has been replaced at both sides of pit. Piping is wrapped and bolts are sprayed. Sump Pumps have been added in pits.
Water Line - Construction Inspection Passed 10/22/2019
Misc
Informational
10/18/2019
SEPTEMBER 27, 2019 Advantage Fire had excavated and removed old fire line upon arrival. Crews had also installed new fire line from STA. 3+75.87 to approx. 3+50. Crews left space for thrust blocks and also powder coated bolts. The fire line has been fully poly wrapped.
Misc
Informational
10/18/2019
OCTOBER 1, 2019 Advantage Fire Crews continue to install Fire Line from approx STA 3+50 to STA 1+25
Water - Material Verification Passed 10/22/2019
Documents & Images
Date Uploaded File Type Document Name
09/23/2019 Receipt Receipt for transaction: 2019-006358
09/24/2019 Letter DE-Permit
10/14/2019 Algersgate Methodist Church
10/18/2019 SEPTEMBER 27, 2019 Fire Line
10/18/2019 SEPTEMBER 27, 2019 Fire Line0
10/18/2019 SEPTEMBER 27, 2019 Fire Line1
10/18/2019 SEPTEMBER 27, 2019 Fire Line2
10/18/2019 SEPTEMBER 27, 2019. Thrust block restraint at outside building
10/18/2019 SEPTEMBER 27, 2019 Gravel and Fill Inspection
10/18/2019 SEPTEMBER 30, 2019 Pre Install Inspection of Hydrant, valve, bend
10/18/2019 SEPTEMBER 30, 2019 Pre Install Inspection Hydrant, Valve,Bend
10/18/2019 September 30, 2019 Pre Install Inspection Hydrant, Valve,Bend0
10/18/2019 SEPTEMBER 30, 2019 Hydrant, Gate Valve, Dip Blend after installation
10/18/2019 SEPTEMBER 30, 2019 Hydrant, Gate Valve, Dip Bend after installation
10/18/2019 SEPTEMBER 30, 2019 Hydrant, Gate Valve, Dip Bend after installation
10/18/2019 SEPTEMBER 30, 2019 Thrust Blocks- Hydrant and Bends
10/18/2019 SEPTEMBER 30, 2019 Thrust Blocks- Hydrants and Bends
10/18/2019 SEPTEMBER 30, 2019 Thrust Blocks -Hydrants and Bends
10/18/2019 SEPTEMBER 30, 2019 Thrust Blocks- Hydrants, and Bends
10/18/2019 3+25 to 1+25
10/18/2019 3+25 to 1+26
10/18/2019 3+25 to 1+27
10/18/2019 3+25 to 1+25
10/18/2019 OCTOBER 1, 2019 Fire Line STA 3+25 to 1+25
10/21/2019 1+36.59 Fire Hydrant, Tees, Bends,Gate Valve
10/21/2019 1+36.59 Fire Hydrant, Tees, Dip Bend, Gate Valve
10/21/2019 OCTOBER 3-4 2019 New Piping at pit
10/21/2019 OCTOBER 3-4 2019 New Piping at pit0
10/21/2019 OCTOBER 3-4 2019 New Piping at pit1
10/21/2019 OCTOBER 3-4 2019 New Piping at pit2
10/21/2019 OCTOBER 3-4 2019 New Piping at pit3
10/21/2019 OCTOBER 7, 2019 Hydrostatic Testing
10/21/2019 OCTOBER 7, 2019 Hydrostatic testing
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter INSPECTION SUMMARY
10/21/2019 Letter DE-Punch List
10/21/2019 Letter DE-Certificate of Substantial Completion Multiple Lot
10/22/2019 Letter Punch List Aldersgate Methodist Church
10/22/2019 Letter Aldersgate Substancial Completion
06/10/2020 Letter DE-Certificate of Final Acceptance (Commercial)
06/10/2020 Aldersgate Methodist Church-Fire Line Extension Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home