Permit Application Status

PRSITE20192422


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSITE20192422
Development - Site
Final Acceptance
TOWNSEND SUMMIT LLC
DEVELOPMENT COMPLETE
Full site development for grocery store.
08/29/2019
11/01/2019
06/05/2020
Locations
Contacts
TOWNSEND SUMMIT LLC, Address:1311 MCCORMICK RD STE 470, Phone:(303) 947-2044  
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
JONATHAN MYERS, Address:EMERY SAPP  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/01/2019 10/29/2019
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Right of Way Permit Fee $80.00 $80.00 Paid 10/28/2019
Sanitary Sewer Insp Fees $264.30 $264.30 Paid 10/28/2019
Water Insp Fee $1,869.00 $1,869.00 Paid 10/28/2019
Water Test Fee $200.00 $200.00 Paid 10/28/2019
Storm Sewer Inspection Fee $639.45 $639.45 Paid 10/28/2019
Paved Surface Inspection Fee $9,100.74 $9,100.74 Paid 10/28/2019
Site Grading Fee $1,275.00 $1,275.00 Paid 10/28/2019
Water Tap Fee $32,452.00 $32,452.00 Paid 10/28/2019
Water Meter Fee $3,140.05 $3,140.05 Paid 10/28/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 11/05/2019
Misc
Informational
11/05/2019
11-5-19 They have installed approximately 254ft of sanitary service line.
Sanitary Sewer Construction Inspection Partial 11/6/2019 11/06/2019
Misc
Informational
11/05/2019
11-5-19 They have installed approximately 254ft of sanitary service line.
Misc
Informational
11/06/2019
11-6-19 All of the sanitary service line is in. They are getting compaction test.
Storm - Pipe Partial 11/6/2019 11/06/2019
Misc
Informational
11/06/2019
11-6-19 They have installed 214ft of 12” storm. They have storm box A2 installed and will be pouring collars at 2:30pm. They have approximately 40ft of 18” installed.
Storm - Material Verification Passed 11/06/2019
Storm - Pipe Partial 11/7/2019 11/07/2019
Misc
Informational
11/06/2019
11-6-19 They have installed 214ft of 12” storm. They have storm box A2 installed and will be pouring collars at 2:30pm. They have approximately 40ft of 18” installed.
Misc
Informational
11/07/2019
11-7-19 8:56am They have the last stick of storm installed and the collar and invert is poured.
Grading/Excavation/Fill Inspection Partial 11/16/2019
Misc
Informational
11/16/2019
11-15-19 They have been grading on the site and have the road cut in. They are planning on laying base rock on Monday the 18th.
Pavement-Proof Roll Passed 11/18/2019 11/18/2019
Misc
Informational
11/18/2019
11-18-19 9:05am The proof roll was set up for 9am the truck for the proof roll is not on site at this time. 9:45am We proof rolled all of the base running north and south. and it has passed. They are planning on pouring the road on 11-19-19.
Grading/Excavation/Fill Inspection Partial 11/18/2019
Misc
Informational
11/16/2019
11-15-19 They have been grading on the site and have the road cut in. They are planning on laying base rock on Monday the 18th.
Misc
Informational
11/18/2019
11-18-19 They are setting baskets. They are pouring on 11-19-19.
Street - Surface Course Partial 11/19/2019 11/19/2019
Misc
Informational
11/19/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Street - Surface Course Partial 11/21/2019
Misc
Informational
11/19/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/21/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Street - Surface Course Partial 11/22/2019 11/22/2019
Misc
Informational
11/21/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/21/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Misc
Informational
11/22/2019
11-22-19 1:14pm They got a late start and are half way poured out. They should be done approximately 2:30pm. 2:47pm They are done pouring and are now cleaning up. They will be covering the concrete with blankets. Terricon is on site doing the testing.
Street - Surface Course Partial 11/23/2019 11/23/2019
Misc
Informational
11/22/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/22/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Misc
Informational
11/22/2019
11-22-19 1:14pm They got a late start and are half way poured out. They should be done approximately 2:30pm. 2:47pm They are done pouring and are now cleaning up. They will be covering the concrete with blankets. Terricon is on site doing the testing.
Misc
Informational
11/23/2019
11-23-19 9:09am They have set up two approaches and are pouring on the south side. After the pour they will be covering with blankets due to weather. They have been told to stay ADA compliant on the north end.
Street - Surface Course Partial 11/25/2019 11/25/2019
Misc
Informational
11/23/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/23/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Misc
Informational
11/23/2019
11-22-19 1:14pm They got a late start and are half way poured out. They should be done approximately 2:30pm. 2:47pm They are done pouring and are now cleaning up. They will be covering the concrete with blankets. Terricon is on site doing the testing.
Misc
Informational
11/23/2019
11-23-19 9:09am They have set up two approaches and are pouring on the south side. After the pour they will be covering with blankets due to weather. They have been told to stay ADA compliant on the north end.
Misc
Informational
11/25/2019
11-25-19 9:28am They have set up both approach’s. One at the north end and one at the south end. They will be pouring at 10am.
Storm - Pipe Partial 11/25/2019 11/25/2019
Misc
Informational
11/07/2019
11-6-19 They have installed 214ft of 12” storm. They have storm box A2 installed and will be pouring collars at 2:30pm. They have approximately 40ft of 18” installed.
Misc
Informational
11/07/2019
11-7-19 8:56am They have the last stick of storm installed and the collar and invert is poured.
Misc
Informational
11/25/2019
11-25-19 9:42am They have installed box 102 and are digging out for storm pipe. 101 to 102 is complete.
Street - Surface Course Partial 11/25/2019 11/25/2019
Misc
Informational
11/25/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/25/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Misc
Informational
11/25/2019
11-22-19 1:14pm They got a late start and are half way poured out. They should be done approximately 2:30pm. 2:47pm They are done pouring and are now cleaning up. They will be covering the concrete with blankets. Terricon is on site doing the testing.
Misc
Informational
11/25/2019
11-23-19 9:09am They have set up two approaches and are pouring on the south side. After the pour they will be covering with blankets due to weather. They have been told to stay ADA compliant on the north end.
Misc
Informational
11/25/2019
11-25-19 9:28am They have set up both approach’s. One at the north end and one at the south end. They will be pouring at 10am. 2:40pm They have poured both drives and are now cleaning up.
Street - Surface Course Partial 11/26/2019 11/26/2019
Misc
Informational
11/25/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/25/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Misc
Informational
11/25/2019
11-22-19 1:14pm They got a late start and are half way poured out. They should be done approximately 2:30pm. 2:47pm They are done pouring and are now cleaning up. They will be covering the concrete with blankets. Terricon is on site doing the testing.
Misc
Informational
11/25/2019
11-23-19 9:09am They have set up two approaches and are pouring on the south side. After the pour they will be covering with blankets due to weather. They have been told to stay ADA compliant on the north end.
Misc
Informational
11/25/2019
11-25-19 9:28am They have set up both approach’s. One at the north end and one at the south end. They will be pouring at 10am. 2:40pm They have poured both drives and are now cleaning up.
Misc
Informational
11/26/2019
11-26-19 They have got there breaks for the north south road and pulled blankets off.
Water Line - Construction Inspection Partial 12/6/2019 12/06/2019
Misc
Informational
12/06/2019
12-6-19 2:30pm They have dug out for the water taps and water tie-in.
Water Line - Construction Inspection Partial 12/5/2019 12/06/2019
Misc
Informational
12/06/2019
12-6-19 They have set the vault and poured the floor. They have dug up the water main to prepair for the tie-in.
Water Line - Construction Inspection Partial 12/10/2019 12/10/2019
Misc
Informational
12/06/2019
12-6-19 They have set the vault and poured the floor. They have dug up the water main to prepair for the tie-in.
Misc
Informational
12/10/2019
12-10-19 9:16am The water is shut off for the water main tie-in.
Misc
Informational
12/10/2019
12-10-19 9:16am The water is shut off for the water main tie-in. 11:59am The tie-in is complete and they have poured the thrusts block. They have covered everything with a blanket due to weather.
Site Visit Partial 1/8/2020 01/08/2020
Misc
Informational
01/08/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Water Line - Construction Inspection Partial 01/28/2020
Misc
Informational
12/10/2019
12-6-19 They have set the vault and poured the floor. They have dug up the water main to prepair for the tie-in.
Misc
Informational
12/10/2019
12-10-19 9:16am The water is shut off for the water main tie-in.
Misc
Informational
12/10/2019
12-10-19 9:16am The water is shut off for the water main tie-in. 11:59am The tie-in is complete and they have poured the thrusts block. They have covered everything with a blanket due to weather.
Misc
Informational
01/28/2020
1-28-20 10:15am I inspected the fire line going to the building. They have two forty five’s and have poured thrust blocks. They will be covering them with blankets due to weather.
Site Visit Partial 01/30/2020
Misc
Informational
01/08/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
01/30/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Site Visit Partial 2/10/2020 02/10/2020
Misc
Informational
01/30/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
01/30/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Misc
Informational
02/10/2020
2-10-20 There are no crews working that require inspections from me at this time.
Erosion Control Inspection Partial 2/21/2020 02/21/2020
Misc
Informational
02/21/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Site Visit Partial 2/25/2020 02/25/2020
Misc
Informational
02/10/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
02/10/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Misc
Informational
02/10/2020
2-10-20 There are no crews working that require inspections from me at this time.
Misc
Informational
02/25/2020
2-25-20 The site seems clean and there are no inspections for me at this time.
Erosion Control Inspection Partial 2/25/2020 02/25/2020
Misc
Informational
02/21/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Erosion Control Inspection Partial 03/17/2020
Misc
Informational
02/25/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Misc
Informational
03/17/2020
3-17-20 All erosion controls appear to be correct at this time. I spoke with Chan Simnitt the Superintendent of the site for Crossland Construction about keeping the streets clean from debris from his site and to have a SWPPP book in place and current ASAP. He said he would do so.
Erosion Control Inspection Partial 3/18/2020 03/18/2020
Misc
Informational
03/17/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Misc
Informational
03/17/2020
3-17-20 All erosion controls appear to be correct at this time. I spoke with Chan Simnitt the Superintendent of the site for Crossland Construction about keeping the streets clean from debris from his site and to have a SWPPP book in place and current ASAP. He said he would do so.
Misc
Informational
03/18/2020
3-18-20 Erosion controls are working at this time.
Site Visit Partial 3/19/2020 03/19/2020
Misc
Informational
02/25/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
02/25/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Misc
Informational
02/25/2020
2-10-20 There are no crews working that require inspections from me at this time.
Misc
Informational
02/25/2020
2-25-20 The site seems clean and there are no inspections for me at this time.
Misc
Informational
03/19/2020
3-19-20 There is no activity on site at this time.
Erosion Control Inspection Failed 03/24/2020
Misc
Informational
03/18/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Misc
Informational
03/18/2020
3-17-20 All erosion controls appear to be correct at this time. I spoke with Chan Simnitt the Superintendent of the site for Crossland Construction about keeping the streets clean from debris from his site and to have a SWPPP book in place and current ASAP. He said he would do so.
Misc
Informational
03/18/2020
3-18-20 Erosion controls are working at this time.
Misc
Informational
03/24/2020
3-24-20 9:34am I spoke with the superintendent Chan about keeping the north south road clean it is currently a mess. I told him to install a construction entrance ASAP. I asked him about his SWPPP book and he said it was not on site at this time and they are working on it.
Water Line - Construction Inspection Partial 3/30/2020 03/30/2020
Misc
Informational
01/28/2020
12-6-19 They have set the vault and poured the floor. They have dug up the water main to prepair for the tie-in.
Misc
Informational
01/28/2020
12-10-19 9:16am The water is shut off for the water main tie-in.
Misc
Informational
01/28/2020
12-10-19 9:16am The water is shut off for the water main tie-in. 11:59am The tie-in is complete and they have poured the thrusts block. They have covered everything with a blanket due to weather.
Misc
Informational
01/28/2020
1-28-20 10:15am I inspected the fire line going to the building. They have two forty five’s and have poured thrust blocks. They will be covering them with blankets due to weather.
Misc
Informational
03/30/2020
Steve Robbins witnessed the flush of the fire line.
Misc
Informational
03/30/2020
Steve Robbins witnessed the flush of the fire line.
Grading/Excavation/Fill Inspection Partial 4/10/2020 04/10/2020
Misc
Informational
11/18/2019
11-15-19 They have been grading on the site and have the road cut in. They are planning on laying base rock on Monday the 18th.
Misc
Informational
11/18/2019
11-18-19 They are setting baskets. They are pouring on 11-19-19.
Misc
Informational
04/10/2020
4-10-20 They are still working on cutting grade.
Site Visit Partial 04/13/2020
Misc
Informational
03/19/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
03/19/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Misc
Informational
03/19/2020
2-10-20 There are no crews working that require inspections from me at this time.
Misc
Informational
03/19/2020
2-25-20 The site seems clean and there are no inspections for me at this time.
Misc
Informational
03/19/2020
3-19-20 There is no activity on site at this time.
Misc
Informational
04/13/2020
4-13-20 They have installed Geo Grid and base rock on Friday the 10th. We will be trying a proof roll later today.
Curb - Proof Roll Failed 4/20/2020 04/20/2020
Misc
Informational
04/20/2020
2-20-20 2:13pm The truck for the proof roll is running late. We will be checking all curb line on site. 2:40pm The proof roll failed.
Erosion Control Inspection Partial 04/29/2020
Misc
Informational
03/24/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Misc
Informational
03/24/2020
3-17-20 All erosion controls appear to be correct at this time. I spoke with Chan Simnitt the Superintendent of the site for Crossland Construction about keeping the streets clean from debris from his site and to have a SWPPP book in place and current ASAP. He said he would do so.
Misc
Informational
03/24/2020
3-18-20 Erosion controls are working at this time.
Misc
Informational
03/24/2020
3-24-20 9:34am I spoke with the superintendent Chan about keeping the north south road clean it is currently a mess. I told him to install a construction entrance ASAP. I asked him about his SWPPP book and he said it was not on site at this time and they are working on it. 4-29-20 8:58am All erosion controls are in place and appear to be working.
Proof roll parking lot Partial 4/29/2020 04/29/2020
Misc
Informational
04/29/2020
4-29-20 10:57am The truck for the proof roll has not arrived. The proof roll was for 10:45am. Rain had passed through approximately two hours earlier. John Jackson will be inspecting the proof roll. The truck arrived at approximately 12:30pm. Approximately 70% passed and the rest will need corrections.
Pavement-Curb Construction Partial 4/30/2020 04/30/2020
Misc
Informational
04/30/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled fromn on the same day.
Misc
Informational
04/30/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled from on the same day.
Pavement-Curb Construction Partial 5/4/2020 05/04/2020
Misc
Informational
04/30/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled fromn on the same day.
Misc
Informational
04/30/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled from on the same day. 5-4-20 7:41am They have all of the islands poured and all curb at the south end of the site.
Water Line - Fire Hydrant Partial 05/04/2020
Misc
Informational
05/04/2020
5-4-20 7:50am They have the fire hydrant set on the west side of the parking lot. All thrust blocks have been poured.
Pavement-Curb Construction Partial 5/5/2020 05/05/2020
Misc
Informational
05/04/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled fromn on the same day.
Misc
Informational
05/04/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled from on the same day. 5-4-20 7:41am They have all of the islands poured and all curb at the south end of the site. 5-5-20 7:17am They have forms set up on the west side of the site and the SE corner. I have inspected the grade after the rain and they are good to pour. They have all the curb poured.
Proof roll parking lot Partial 05/06/2020
Misc
Informational
04/29/2020
4-29-20 10:57am The truck for the proof roll has not arrived. The proof roll was for 10:45am. Rain had passed through approximately two hours earlier. John Jackson will be inspecting the proof roll. The truck arrived at approximately 12:30pm. Approximately 70% passed and the rest will need corrections. 5-5-20 John Jackson inspected the proof roll for the parking lot. He informed me that it passed with one small correction at the south west corner by the inlet. They are good for asphalt at this time.
Proof roll parking lot Partial 5/8/2020 05/08/2020
Misc
Informational
05/06/2020
4-29-20 10:57am The truck for the proof roll has not arrived. The proof roll was for 10:45am. Rain had passed through approximately two hours earlier. John Jackson will be inspecting the proof roll. The truck arrived at approximately 12:30pm. Approximately 70% passed and the rest will need corrections. 5-5-20 John Jackson inspected the proof roll for the parking lot. He informed me that it passed with one small correction at the south west corner by the inlet. They are good for asphalt at this time. 5-8-20 We proof rolled again and it passed with corrections to be made at the south west corner and the north west corner.
Pavement-Surface Partial 5/9/2020 05/09/2020
Misc
Informational
05/09/2020
5-9-20 7:08AM Little Joes Asphalt Inc. are setting up to lay asphalt. The current temp is 40 degrees out side with full sun. Law Valley will be doing all testing. ESS cut out some wet rock at the SW corner and will will be adding additional asphalt. The temperature out of the trucks are around 250 degrees.
Street - Surface Course Partial 5/11/2020 05/11/2020
Misc
Informational
05/11/2020
Subcontractor Little Joe’s Asphalt began laying surface level asphalt around 10:00am. Temperatures for the day are forecasted to be low to mid 50 degrees and cloudy. Tickets for the surface asphalt will be provide at the end of the day.
Erosion Control Inspection Partial 05/22/2020
Misc
Informational
04/29/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Misc
Informational
04/29/2020
3-17-20 All erosion controls appear to be correct at this time. I spoke with Chan Simnitt the Superintendent of the site for Crossland Construction about keeping the streets clean from debris from his site and to have a SWPPP book in place and current ASAP. He said he would do so.
Misc
Informational
04/29/2020
3-18-20 Erosion controls are working at this time.
Misc
Informational
04/29/2020
3-24-20 9:34am I spoke with the superintendent Chan about keeping the north south road clean it is currently a mess. I told him to install a construction entrance ASAP. I asked him about his SWPPP book and he said it was not on site at this time and they are working on it. 4-29-20 8:58am All erosion controls are in place and appear to be working. 5-22-20 They have erosion controls in place and they are working at this time.
Site Visit Partial 05/27/2020
Misc
Informational
04/13/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
04/13/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Misc
Informational
04/13/2020
2-10-20 There are no crews working that require inspections from me at this time.
Misc
Informational
04/13/2020
2-25-20 The site seems clean and there are no inspections for me at this time.
Misc
Informational
04/13/2020
3-19-20 There is no activity on site at this time.
Misc
Informational
04/13/2020
4-13-20 They have installed Geo Grid and base rock on Friday the 10th. We will be trying a proof roll later today. 5-27-20 Steve Robbins and I met with Chan Simnitt the Superintendent for Aldi. We showed him 7 panels of sidewalk that they need to replace along with a wing by the ADA ramp. He said he would address the issues and get them fixed.
Site Visit Partial 05/28/2020
Misc
Informational
05/27/2020
1-8-20 10:10am They are working on footings at this time. There is no other activity at this time.
Misc
Informational
05/27/2020
1-30-20 2:45pm Talked with both Superintendent’s about keeping the roads clean of mud and rock when trucks are pulling off site.
Misc
Informational
05/27/2020
2-10-20 There are no crews working that require inspections from me at this time.
Misc
Informational
05/27/2020
2-25-20 The site seems clean and there are no inspections for me at this time.
Misc
Informational
05/27/2020
3-19-20 There is no activity on site at this time.
Misc
Informational
05/27/2020
4-13-20 They have installed Geo Grid and base rock on Friday the 10th. We will be trying a proof roll later today. 5-27-20 Steve Robbins and I met with Chan Simnitt the Superintendent for Aldi. We showed him 7 panels of sidewalk that they need to replace along with a wing by the ADA ramp. He said he would address the issues and get them fixed. 5-28-20 We met on site for C of O.
Storm - Material Verification Passed 05/28/2020
Storm - Inlets Clean Passed 05/28/2020
Erosion Control Inspection Passed 05/28/2020
Misc
Informational
05/22/2020
2-21-20 10:32am All erosion controls appear to be good at this time.
Misc
Informational
05/22/2020
3-17-20 All erosion controls appear to be correct at this time. I spoke with Chan Simnitt the Superintendent of the site for Crossland Construction about keeping the streets clean from debris from his site and to have a SWPPP book in place and current ASAP. He said he would do so.
Misc
Informational
05/22/2020
3-18-20 Erosion controls are working at this time.
Misc
Informational
05/22/2020
3-24-20 9:34am I spoke with the superintendent Chan about keeping the north south road clean it is currently a mess. I told him to install a construction entrance ASAP. I asked him about his SWPPP book and he said it was not on site at this time and they are working on it. 4-29-20 8:58am All erosion controls are in place and appear to be working. 5-22-20 They have erosion controls in place and they are working at this time.
Proof roll parking lot Passed 05/28/2020
Misc
Informational
05/08/2020
4-29-20 10:57am The truck for the proof roll has not arrived. The proof roll was for 10:45am. Rain had passed through approximately two hours earlier. John Jackson will be inspecting the proof roll. The truck arrived at approximately 12:30pm. Approximately 70% passed and the rest will need corrections. 5-5-20 John Jackson inspected the proof roll for the parking lot. He informed me that it passed with one small correction at the south west corner by the inlet. They are good for asphalt at this time. 5-8-20 We proof rolled again and it passed with corrections to be made at the south west corner and the north west corner.
Pavement-Surface Passed 05/28/2020
Pavement-Curb Construction Passed 06/01/2020
Misc
Informational
05/05/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled fromn on the same day.
Misc
Informational
05/05/2020
4-30-20 7:51am MB Concrete are pouring the curb at Aldis. They have started at the south end of the site. I have informed them to use white cure and to completely cover in a even coat. They have also been informed to grout any honey comb a cure any curb that the forms have been pulled from on the same day. 5-4-20 7:41am They have all of the islands poured and all curb at the south end of the site. 5-5-20 7:17am They have forms set up on the west side of the site and the SE corner. I have inspected the grade after the rain and they are good to pour. They have all the curb poured.
Sidewalk Inspection Partial 06/01/2020
Misc
Informational
06/01/2020
6-1-20 They have poured the sidewalk on the North side of Aldi’s at the fire hydrant.
Sidewalk Inspection Passed 06/05/2020
Misc
Informational
06/01/2020
6-1-20 They have poured the sidewalk on the North side of Aldi’s at the fire hydrant.
Curb - Proof Roll Passed 06/05/2020
ESC - (Vegetation/Ground Cover) Passed 06/05/2020
Sewer Service Inspection Passed 06/05/2020
Water Line - Construction Taps Removed Passed 06/05/2020
Water Line - Thrust Restraint Passed 06/05/2020
Water Line - Valve Passed 06/05/2020
Water - Material Verification Passed 06/05/2020
Water - Material Verification Passed 06/05/2020
Water Line - Fire Hydrant Passed 06/05/2020
Misc
Informational
05/04/2020
5-4-20 7:50am They have the fire hydrant set on the west side of the parking lot. All thrust blocks have been poured.
Grading/Excavation/Fill Inspection Passed 06/05/2020
Misc
Informational
04/10/2020
11-15-19 They have been grading on the site and have the road cut in. They are planning on laying base rock on Monday the 18th.
Misc
Informational
04/10/2020
11-18-19 They are setting baskets. They are pouring on 11-19-19.
Misc
Informational
04/10/2020
4-10-20 They are still working on cutting grade.
Water Line - Construction Inspection Passed 06/05/2020
Misc
Informational
03/30/2020
12-6-19 They have set the vault and poured the floor. They have dug up the water main to prepair for the tie-in.
Misc
Informational
03/30/2020
12-10-19 9:16am The water is shut off for the water main tie-in.
Misc
Informational
03/30/2020
12-10-19 9:16am The water is shut off for the water main tie-in. 11:59am The tie-in is complete and they have poured the thrusts block. They have covered everything with a blanket due to weather.
Misc
Informational
03/30/2020
1-28-20 10:15am I inspected the fire line going to the building. They have two forty five’s and have poured thrust blocks. They will be covering them with blankets due to weather.
Misc
Informational
03/30/2020
Steve Robbins witnessed the flush of the fire line.
Misc
Informational
03/30/2020
Steve Robbins witnessed the flush of the fire line.
Water Line - Hydrostatic Test Passed 06/05/2020
Sanitary Sewer Construction Inspection Partial 06/05/2020
Storm - Pipe Passed 3/10/2020 06/05/2020
Misc
Informational
11/25/2019
11-6-19 They have installed 214ft of 12” storm. They have storm box A2 installed and will be pouring collars at 2:30pm. They have approximately 40ft of 18” installed.
Misc
Informational
11/25/2019
11-7-19 8:56am They have the last stick of storm installed and the collar and invert is poured.
Misc
Informational
11/25/2019
11-25-19 9:42am They have installed box 102 and are digging out for storm pipe. 101 to 102 is complete.
Street - Surface Course Passed 06/05/2020
Misc
Informational
11/26/2019
11-19-19 8:25am They have started pouring the north south road that runs between Aldi and Lot 4. They are using 5k mix. 10:39am They have finished pouring and are washing up there equipment.
Misc
Informational
11/26/2019
11-21-19 They are pouring the cut out on the east west road that ties in with the north south road for Aldi’s. They will be covering with blankets.
Misc
Informational
11/26/2019
11-22-19 1:14pm They got a late start and are half way poured out. They should be done approximately 2:30pm. 2:47pm They are done pouring and are now cleaning up. They will be covering the concrete with blankets. Terricon is on site doing the testing.
Misc
Informational
11/26/2019
11-23-19 9:09am They have set up two approaches and are pouring on the south side. After the pour they will be covering with blankets due to weather. They have been told to stay ADA compliant on the north end.
Misc
Informational
11/26/2019
11-25-19 9:28am They have set up both approach’s. One at the north end and one at the south end. They will be pouring at 10am. 2:40pm They have poured both drives and are now cleaning up.
Misc
Informational
11/26/2019
11-26-19 They have got there breaks for the north south road and pulled blankets off.
Documents & Images
Date Uploaded File Type Document Name
10/28/2019 Receipt Receipt for transaction: 2019-007037
11/07/2019 Letter INSPECTION SUMMARY
11/22/2019 N S road
11/22/2019 Road pour
12/10/2019 Tie-in
01/28/2020 Letter INSPECTION SUMMARY
01/30/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/21/2020 Letter INSPECTION SUMMARY
02/25/2020 Letter INSPECTION SUMMARY
02/25/2020 Letter INSPECTION SUMMARY
03/17/2020 Letter INSPECTION SUMMARY
03/17/2020 Letter DE-Permit
03/18/2020 Letter INSPECTION SUMMARY
03/19/2020 Letter INSPECTION SUMMARY
03/24/2020 image
03/24/2020 Entrance to Aldi
03/24/2020 Letter INSPECTION SUMMARY
03/30/2020 Letter INSPECTION SUMMARY
04/10/2020 Letter INSPECTION SUMMARY
04/13/2020 Letter INSPECTION SUMMARY
04/20/2020 Letter INSPECTION SUMMARY
04/29/2020 Letter INSPECTION SUMMARY
04/29/2020 Letter INSPECTION SUMMARY
04/30/2020 Letter INSPECTION SUMMARY
05/04/2020 Letter INSPECTION SUMMARY
05/04/2020 Letter INSPECTION SUMMARY
05/05/2020 Letter INSPECTION SUMMARY
05/06/2020 Letter INSPECTION SUMMARY
05/08/2020 Letter INSPECTION SUMMARY
05/09/2020 Letter INSPECTION SUMMARY
05/11/2020 Letter INSPECTION SUMMARY
05/22/2020 Letter INSPECTION SUMMARY
05/27/2020 Letter INSPECTION SUMMARY
05/28/2020 Letter INSPECTION SUMMARY
05/28/2020 Letter DE-Certificate of Substantial Completion Multiple Lot
05/28/2020 Letter DE-Punch List
05/28/2020 Aldi' Substanial Completion
05/28/2020 Aldi's Punch List
06/01/2020 Letter INSPECTION SUMMARY
06/01/2020 Letter INSPECTION SUMMARY
06/01/2020 Letter INSPECTION SUMMARY
06/05/2020 Letter DE-Certificate of Final Acceptance (Commercial)
06/05/2020 Aldi Final Acceptance
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home