Permit Application Status

PRRES20250835


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20250835
Building Permit - Residential
Issued
NEW SINGLE FAMILY
NEW HOUSE. FINISHED/UNFINISHED BASEMENT. WALKOUT BASEMENT. COVERED DECK.
03/13/2025
03/20/2025
09/14/2025
Locations
Contacts
KEVIN HIGDON CONSTRUCTION, LLC, Address:P O BOX 847, Phone:(816) 524-9797  
Kevin higdon, Address:Po box 847  
PRAIRIE CENTER PLUMBING HEATING & A/C, Address:242 N MARION, Phone:(913) 829-6263  
INTERSTATE CONSTRUCTION SERVICES, Address:1450 SE BROADWAY DR, Phone:(816) 524-9797  
MILLER PLUMBING CO, Address:PO BOX 393 , Phone:(913) 851-1333  
DOUG@HIGDONBUILDERS.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Water Tap Fee $3,973.00 $3,973.00 Paid 03/20/2025
Water Meter Fee $748.03 $748.03 Paid 03/20/2025
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 03/20/2025
Right of Way Permit Fee $85.00 $85.00 Paid 03/20/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 03/20/2025
Valuation Fee New Single Family $1,562.36 $1,562.36 Paid 03/20/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Driveway Inspection Pending
Misc
Informational
08/06/2025
07/30/25 Jamie S, DW is formed and compacted. Approved to pour. 08/06/25 Jamie S, DW forms are still up, cannot inspect until forms are pulled. Call back in for reinspection.
Sidewalk Inspection Pending
Misc
Informational
08/06/2025
07/30/25 Jamie S, SW is formed and compacted. Approved to Pour. 08/06/25 Jamie S, SW forms are still up, cannot inspect until forms are removed. Call in for reinspection once forms are pulled.
Erosion Control Inspection Residential Pending
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
08/07/2025
06-02-25 Jamie S, Erosion control needs to be reestablished. Streets need to be cleaned. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 06-05-25 Jamie S, Erosion Control has been reestablished. 07/31/25 Jamie S, Erosion control needs to be reestablished. Storm drains in cul-de-sac need to be cleaned out. 08/05/25 Jamie S, Erosion control has been reestablished. One storm drain has been cleared, The other storm drain in the cul-de-sac needs to be cleaned out.
Footing Inspection - Residential Passed 4/9/2025 4/9/2025 04/09/2025
Informational
04/09/2025
- Egineer report required spead footing of 24" with (3) #4 bars, this is in place. UFER 1' back on south wall from front
Sewer Service Inspection - R Passed 4/24/2025 04/24/2025
Water Service Inspection - R Passed 4/24/2025 4/24/2025 04/24/2025
Underslab Plumbing Inspection - Residential Not Ready 5/2/2025 5/2/2025 05/02/2025
Misc
Corrective Action Required
05/02/2025
inspection denied not ready -need address posted -need complient erosion control
Underslab Plumbing Inspection - Residential Passed 5/6/2025 5/6/2025 05/06/2025
Misc
Resolved
05/06/2025
inspection denied not ready -need address posted -need complient erosion control
Piers/Caissons Inspection - Residential Passed 5/30/2025 5/30/2025 05/30/2025
Erosion Control Inspection Residential Partial 4/9/2025 06/02/2025
Erosion Control Inspection Residential Failed 6/2/2025 6/2/2025 06/02/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/02/2025
06-02-25 Jamie S, Erosion control needs to be reestablished. Streets need to be cleaned. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Erosion Control Inspection Residential Partial 6/5/2025 6/5/2025 06/05/2025
DCM3 ESC REQUIRED 2 DAY
Resolved
06/05/2025
06-02-25 Jamie S, Erosion control needs to be reestablished. Streets need to be cleaned. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 06-05-25 Jamie S, Erosion Control has been reestablished.
All Rough Inspection - Residential Failed 7/2/2025 7/2/2025 07/02/2025
Miscellaneous Correction
Corrective Action Required
07/02/2025
4001 -missing stud in stud pack in garage -fire block the cut out at the dryer vent and the LVL cut out
Gas Service Inspection - Residential Passed 7/2/2025 7/2/2025 07/02/2025
Electrical Service Inspection Passed 7/2/2025 7/2/2025 07/02/2025
All Rough Inspection - Residential Passed 7/8/2025 7/8/2025 07/08/2025
Miscellaneous Correction
Resolved
07/08/2025
4001 -missing stud in stud pack in garage -fire block the cut out at the dryer vent and the LVL cut out
Driveway Inspection Partial 7/30/2025 7/30/2025 07/30/2025
Misc
Informational
07/30/2025
07/30/25 Jamie S, DW is formed and compacted. Approved to pour.
Sidewalk Inspection Partial 7/30/2025 7/30/2025 07/30/2025
Misc
Informational
07/30/2025
07/30/25 Jamie S, SW is formed and compacted. Approved to Pour.
Erosion Control Inspection Residential Failed 7/31/2025 7/31/2025 07/31/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/05/2025
06-02-25 Jamie S, Erosion control needs to be reestablished. Streets need to be cleaned. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 06-05-25 Jamie S, Erosion Control has been reestablished. 07/31/25 Jamie S, Erosion control needs to be reestablished. Storm drains in cul-de-sac need to be cleaned out.
Erosion Control Inspection Residential Partial 8/5/2025 8/5/2025 08/05/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
07/31/2025
06-02-25 Jamie S, Erosion control needs to be reestablished. Streets need to be cleaned. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 06-05-25 Jamie S, Erosion Control has been reestablished. 07/31/25 Jamie S, Erosion control needs to be reestablished. Storm drains in cul-de-sac need to be cleaned out. 08/05/25 Jamie S, Erosion control has been reestablished. One storm drain has been cleared, The other storm drain in the cul-de-sac needs to be cleaned out.
Driveway Inspection Partial 8/6/2025 8/6/2025 08/06/2025
Misc
Informational
07/30/2025
07/30/25 Jamie S, DW is formed and compacted. Approved to pour. 08/06/25 Jamie S, DW forms are still up, cannot inspect until forms are pulled. Call back in for reinspection.
Sidewalk Inspection Partial 8/6/2025 8/6/2025 08/06/2025
Misc
Informational
07/30/2025
07/30/25 Jamie S, SW is formed and compacted. Approved to Pour. 08/06/25 Jamie S, SW forms are still up, cannot inspect until forms are removed. Call in for reinspection once forms are pulled.
Erosion Control Inspection Residential Failed 8/8/2025 8/8/2025 08/07/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
08/05/2025
06-02-25 Jamie S, Erosion control needs to be reestablished. Streets need to be cleaned. EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. 06-05-25 Jamie S, Erosion Control has been reestablished. 07/31/25 Jamie S, Erosion control needs to be reestablished. Storm drains in cul-de-sac need to be cleaned out. 08/05/25 Jamie S, Erosion control has been reestablished. One storm drain has been cleared, The other storm drain in the cul-de-sac needs to be cleaned out.
Documents & Images
Date Uploaded File Type Document Name
03/13/2025 Lees Summit Residental Permit Application 4001 sw mondavi lot 179
03/13/2025 exciseapplication 4001 sw mondavi
03/18/2025 Permit Codes Residential Plan Review
03/19/2025 Plot Plan APPROVED PLOT PLAN
03/20/2025 Approved Plans APPROVED PLANS
03/20/2025 Permit Codes Residential Plan Review
03/20/2025 Permit DS Building Permit
03/20/2025 Receipt Receipt for transaction:2025-001702
04/09/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter INSPECTION SUMMARY
05/02/2025 Letter INSPECTION SUMMARY
05/05/2025 Engineer Report/Study SOIL INSPECTION
05/06/2025 Letter INSPECTION SUMMARY
05/30/2025 Letter INSPECTION SUMMARY
06/02/2025 Letter INSPECTION SUMMARY
06/02/2025 Letter INSPECTION SUMMARY
06/02/2025 Letter INSPECTION SUMMARY
06/05/2025 Letter INSPECTION SUMMARY
06/05/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/08/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/31/2025 Letter INSPECTION SUMMARY
08/05/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
08/06/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home